Item Description Tag Disc Cat Raised Date Cleared Date Accepted Date
SubSystem : PD40-726-29 - ESP OHTL Power Distribution for Phase 2 Ring Main 2 Section 29 Phase : Phase 2 Ring Main 2
Punchlist : PL-PD40-726-29-MC - MC Punchlist - ESP OHTL Power Distribution for Phase 2 Ring Main 2 Section 29
1 IP washer of the FOC gland entering the RMU need to be re- E B 17 Jan 2024
installed correctly (PD40-726-T0062)
2 IP washer of the FOC gland entering the RMU need to be re- PD40-726-T0063 E B 17 Jan 2024
installed correctly
PUNCHLIST TOTAL 2 0 0
OVERALL TOTAL 2 0 0