Professional Documents
Culture Documents
Tag No’s
N/A
(if applicable)
Contractor
103150AC-C-G0-G000-ML-PRO-0001 Rev A01
Document No:
A01 Issued for COMPANY Review and approval 08/01/2023 Abdulilah M. Saleh Bassim A. M Bassim A. M
TABLE OF CONTENT
1.0 INTRODUCTION
2.0 SCOPE
3.0. REFERENCE DOCUMENTS
4.0. DEFINITION OF TERMS
6.0. INSTALLATION
1.0 INTRODUCTION
Cathodic Protection is mean of reducing corrosion of a metal by artificially causing direct
current to flow from external anodes, through the electrolyte (soil or water), and onto the
structure to be protected. The two types of CP systems are galvanic anode and impressed
current.
Galvanic anode CP system provide cathodic current by galvanic corrosion or by sacrificing
one material to prevent corrosion of the other. This type of system is often referred to as
sacrificial anode CP system. Both the structure and the anode must be in contact with the
electrolyte.
This Document describe the installation procedure for the cathodic protection and the
methods and techniques used for this purpose.
2.0 SCOPE
Purpose and Scope of this Procedure is to establish a detailed method, equipment, quality control
and HSE measures to be planed, prepared and implemented to ensure that the installation of the
CATHODIC PROTECTION are met with Client requirement.
The boundary to which this Document will be applied will be for above ground piping/flowlines: Oil
Flowline/WH/MF, Flexline, Trunkline + pruduced water injection flowline/WH/MF.
ANODE: Sacrificial Magnesium + Zinc anode pre-packaged in permeable calico/ cotton bag with
gypsum bentonite shall be used for the cathodic protection for road crossings of oil pipelines.
Zinc Anodes to be used in North Rumaila, Magnesium Anodes to be used in South Rumaila
TEST POINT: Standpost conduit 3 inch’s hot-dip galvanised steel pipe with 306mm tall X
306mm wide X150mm deep with lockable front door, zone2, IP56 Box
CABLES:
• materials to be received from ROO according to the approved MIT for free issued materials and
will be installed according to manufacturer recommendations
TEST POINT FOUNDATION: a concrete block with implanted pipe will be used to install the
test point box
6.0 INSTALLATION
- All material received at site shall be inspected, handled and stored upon receipt in
accordance with Project Procedure for “Field Material Control”.
- Preparation of required tools and materials necessary for the installation work.
- All traces of oil, grease, mill scale and any other contamination shall be removed on
the coating or steel before any filing or grinding.
- The connection area shall be cleaned to bright metal using a small hand grinder with a
non-metallic coarse grinder.
- Ensure that the minimum pipe wall thickness is not compromised during grinding.
6.1 INSTALLATION OF CATHODIC PROTECTION EQUIPMENT
Equipment shall be installed accurately with respect to their position, arrangement and
directions.
Lifting shall be carried out using properly tested and approved slings.
After completion of installation the following points shall be checked and corrected if
necessary.
Check the level and alignment with the adjacent equipment are correct.
Check if there is any damage to the paint coating.
Check the anchor bolts and set bolts have been tightened.
6.1.1 TEST BOX INSTALLATION
Cathodic Protection installation Procedure Rev: A01
Date: 08/01/2023
103150AC-C-G0-G000-ML-PRO-0001 Page No.: 6 of 12
During working period, inspection shall be carried out on insulation testing by suitable
instrument on insulating joints before and after welding or fitting.
Visual inspection of cathodic protection anodes and cables.
Visual inspection of transformer-rectifiers, test boxes and stations prior to installation.
All cathodic protection removable links inside the accessible equipment shall be left
open and no impressed current stations shall be energized without COMPANY’s
approval.
Checking of all accessible cathodic protection equipment; their wiring, correct polarity
(+/-), terminations and cable tagging.
6.1.5 TESTING AND RECORDS
Cathodic Protection installation Procedure Rev: A01
Date: 08/01/2023
103150AC-C-G0-G000-ML-PRO-0001 Page No.: 7 of 12
All monitoring and measuring devices used shall be calibrated and have valid calibration
certificate during the time of inspection as per Control of Monitoring and Measuring
Equipment Procedure.
Quality records shall be prepared as per Inspection and Test Plan (ITP), inspect and
signed by Electrical Inspector for the completion of Mechanical Completion prior
for Commissioning Phase.
8.1 CLEANING
- For pin brazing it is crucial that to achieve a successful pin braze, the area of connection
onto the pipeline (or other metal substrate) has a clean bright metal finish. In order to
achieve this some degree of surface preparation will be required.
-
- If necessary, the surface encompassing the pin braze area and adjacent earth connection
shall be degreased before any grinding operation.
Cathodic Protection installation Procedure Rev: A01
Date: 08/01/2023
103150AC-C-G0-G000-ML-PRO-0001 Page No.: 9 of 12
- Scrape and clean the steel and clean an area for the earth device as near as possible to the
braze area as illustrated in STEP ONE - figure
- The metal surface must then be prepared to a bright clean finish to ensure a sound
electrical connection between the earth device and the substrate.
- Never continuously work the metal such that any wall thickness is reduced.
- An area sufficient to accommodate the brazing pin and cable lug must be correctly located
and cleaned to a bright metal finish. To prevent the cleaned metal surface re-oxidising,
recommend that pin brazing must take place as soon as possible after surface preparation,
i.e. not more than 60 minutes delay.
- Load the gun with a brazing pin and ceramic ferrule individually by hand. Ensure that they
are both back fully inserted and tight with the palm of your hand, as illustrated in STEP
TWO – figure
- The legs of the pin holder must be adjusted as necessary to ensure a firm grip of the pin
while maintaining concentricity with the ferrule holder.
- Before connecting the earth device to the steel, adjust the brazing
pin "Lift Height" as follows:
- Hold the cable lug or stinger flat on the steel surface (for direct pin
connection). Insert a loaded brazing pin into the hole in the lug and
press the gun/ferrule against the surface of the lug evenly
overcoming the internal spring. Turn the ferrule holder until the
white adjustment indicator tube is flush with the gun's rear face.
The brazing gun should now be correctly set, as illustrated in STEP
THREE – figure.
- When using threaded brazing pins, i.e. M8 brazing pin, the ceramic
ferrule must be flat against the steel surface when checking the
white adjustment indicator tube.
Cathodic Protection installation Procedure Rev: A01
Date: 08/01/2023
103150AC-C-G0-G000-ML-PRO-0001 Page No.: 10 of 12
If the surface of the broken pin is proud of the surface of the lug this is an
indication that the brazing time was too short * (figure 9 [B]). The reason for a
short braze time is usually the result of excessive current being drawn due to the
gun "lift height" being incorrect. This short time can also be caused by a poor
earth connection. If the surface of the broken pin is below the surface of the lug,
this is an indication that the brazing time was too long (figure 9 [C]). The reason
for a long braze time is the result of insufficient current being drawn. Insufficient
current is usually the result of a poor battery condition. If it is known that the
battery is good then the cause may be incorrect setting of the gun "lift height". If
the ferrule is not held against the copper lug and is in partial contact then the arc
can escape out of the gap and this will result in the side of the copper lug burning
away. PIN brazing shall be proven by suitably qualified procedure qualification
testing.
Warning: Repeated bond attempts must not be made at the same position
as this may cause structural/metallurgical damage to the base steel.
No arc or there is a short “pop” Circuit not Check fuse wire on pin is
of the pin complete engaged Check earth
or highly device is connected
resistive
Arc time too short 9Figure 9 Excessive current drawn Poor earth Check gun adjustment
(B) connection Reset earth connection
Arc time too long Figure 9 Insufficient current drawn Check gun adjustment
(C) Recharge batteries
Bond falls off when tested Too short brazing time Base metal See above Thoroughly
Cathodic Protection installation Procedure Rev: A01
Date: 08/01/2023
103150AC-C-G0-G000-ML-PRO-0001 Page No.: 12 of 12
Fuse wire stuck in contact Pin loose in holder Failure to eject Tighten fit of pin holder
nipple previous fuse wire jaws Replace contact
nipple
Brazing pin fails to push into Pin is out of line from the ferrule Take care not to bend
molten braze material due to off centre ferrule holder ferrule holder jaws when
jaws caused by heavy removal of removing spent ferrule
spent ferrule
Replace ferrule holder
END OF PROCEDURE