Professional Documents
Culture Documents
Document
0430WD-N-WM-CP00-ML-REP-0001 Rev B01
Number:
Document
CATHODIC PROTECTION DESIGN REPORT
Title:
CPS 1-5 SOURCE WATER TRUNKLINES REPLACEMENT PRE-
Project Title:
FEED
Tag No’s
(if applicable)
Contractor: Wood
Contractor
Rev
Document No:
Change Log
Rev Section Change Description
A01 All First issue
B01 All Reference list fully updated
Project description text updated
Pipeline route map references updated
Pipeline lengths updated
CP calculations fully updated
CPS buried piping segments added
MTO updated
Document Holds
Hold Brief Description of HOLD Location of HOLD
No.
1
2
3
4
Table of Contents
1 Executive Summary ....................................................................................... 8
2 Introduction .................................................................................................... 9
2.1 Project Description ................................................................................................... 9
2.2 Process Schematic ................................................................................................. 10
3 Preliminary Pipeline Routing ....................................................................... 11
3.1 General ................................................................................................................... 11
3.2 Route Maps ............................................................................................................ 11
3.3 Routing – Pre-FEED phase .................................................................................... 11
4 Material Selection and Corrosion Control .................................................. 12
4.1 External Corrosion .................................................................................................. 12
4.1.1 Protective Coatings ........................................................................................................... 12
4.1.2 Cathodic Protection ........................................................................................................... 12
4.1.3 CP System Options ........................................................................................................... 12
4.1.4 Independent ICCP ............................................................................................................. 14
4.1.5 Design Parameters and Assumptions ............................................................................... 16
5 ICCP System Design .................................................................................... 18
5.1 General ................................................................................................................... 18
5.2 Soil Resistivity ........................................................................................................ 18
5.3 Existing CP Installations ......................................................................................... 18
5.3.1 Surface Area and Design Current Demand ...................................................................... 18
5.3.2 Design Protected Potential................................................................................................ 20
5.3.3 Pipeline Attenuation Calculations...................................................................................... 20
5.3.4 Design Life ........................................................................................................................ 22
5.4 ICCP Groundbed Configurations ............................................................................ 22
5.4.1 Semi-deepwell Groundbed Resistance Calculation .......................................................... 22
5.5 Temporary Protection ............................................................................................. 24
5.6 CP Ancillaries ......................................................................................................... 25
5.6.1 Test Facilities .................................................................................................................... 25
5.6.2 Cable-to-Pipe Connections ............................................................................................... 26
5.6.3 Anode and Cathode Distribution Boxes ............................................................................ 26
5.6.4 Road Crossings ................................................................................................................. 26
5.6.5 Pipeline Crossings ............................................................................................................ 27
5.6.6 AC Mitigation ..................................................................................................................... 27
5.6.7 Electrical Isolation ............................................................................................................. 27
5.6.8 Transformer Rectifier Unit (TRU) Rated Output................................................................ 27
5.6.9 CPS Piping Underground Sections ................................................................................... 29
5.6.10 Anchor Blocks ................................................................................................................... 30
5.6.11 Protection Levels and Over-Protection ............................................................................. 30
5.6.12 Onshore Coating Integrity Assessment ............................................................................ 31
6 Preliminary ICCP MTO ................................................................................. 32
References Summary
Ref Document Number Description
1. 0000RO-N-WM-CP00-OP-SOR-0002 STATEMENT OF REQUIREMENTS:
(9-Sep-22) REPLACEMENT OF TRUNKLINES FROM CPS1-
5 STATIONS TO MISHRIF FIELD MANIFOLDS
(FM1 TO FM10)
2. 0430WD-N-WM-CP00-EM-BOD-0001 CPS 1 - 5 Source Water Trunklines Replacement
Pre-FEED Basis of Design
3. 0430WD-N-WM-CP00-PL-LST-0001 CPS 1 - 5 Source Water Trunklines Replacement
Pre-FEED Pipeline Crossing Schedule
4. 0430WD-N-WM-CP00-PR-REP-0003 CPS 1 - 5 Source Water Trunklines Replacement
Pre-FEED Flow Assurance Report
5. 0430WD-N-WM-CP00-PI-MTO-0001 CPS 1 - 5 Source Water Trunklines Replacement
Pre-FEED Piping Preliminary MTO
6. 0430WD-N-WM-CP01-PL-DAG-0001- CPS 1 - 5 Source Water Trunklines Replacement
001 Pre-FEED CPS1 to FM5 Pipeline Routing
Drawing
7. 0430WD-N-WM-CP01-PL-DAG-0002- CPS 1 - 5 Source Water Trunklines Replacement
001 Pre-FEED CPS1 to FM7 Pipeline Routing
Drawing
8. 0430WD-N-WM-CP02-PL-DAG-0001- CPS 1 - 5 Source Water Trunklines Replacement
001 Pre-FEED CPS2 to FM9 Pipeline Routing
Drawing
9. 0430WD-N-WM-CP03-PL-DAG-0001- CPS 1 - 5 Source Water Trunklines Replacement
001 Pre-FEED CPS3 to FM10 Pipeline Routing
Drawing
10. 0430WD-N-WM-CP04-PL-DAG-0001- CPS 1 - 5 Source Water Trunklines Replacement
001 Pre-FEED CPS4 TO FM6 Pipeline Routing
Drawing
11. 0430WD-N-WM-CP04-PL-DAG-0002- CPS 1 - 5 Source Water Trunklines Replacement
001 Pre-FEED CPS4 TO FM8 Pipeline Routing
Drawing
12. 0430WD-N-WM-CP05-PL-DAG-0001- CPS 1 - 5 Source Water Trunklines Replacement
001 Pre-FEED CPS5 TO FM1 Pipeline Routing
Drawing
13. 0430WD-N-WM-CP05-PL-DAG-0002- CPS 1 - 5 Source Water Trunklines Replacement
001 Pre-FEED CPS5 TO FM2 Pipeline Routing
Drawing
14. 0430WD-N-WM-CP05-PL-DAG-0003- CPS 1 - 5 Source Water Trunklines Replacement
001 Pre-FEED CPS5 TO FM3 Pipeline Routing
Drawing
15. 0430WD-N-WM-CP05-PL-DAG-0004- CPS 1 - 5 Source Water Trunklines Replacement
001 Pre-FEED CPS5 TO FM4 Pipeline Routing
Drawing
16. BS EN 12954 Cathodic Protection of Buried or immersed
Metallic Structures – General Principles and
Application for Pipelines
1 Executive Summary
For buried steel pipelines, protective coatings, of whatever material or extent, are the primary barrier to
corrosion; with temporary GACP and permanent ICCP providing backup protection to the pipeline at
points where the coating is imperfect (i.e. at holidays) or becomes damaged. This is particularly
important in saline and/or high chloride soil environments.
The replacement trunklines will nominally be provided with 3-Layer Polyethylene (3LPE) external
coating (note that at Basra Railway and MOD Canal Crossing, the recommendation is to use a
Polyurethane coating), an internal FBE coating and permanent ICCP systems installed at each CPS
using semi-deepwell vertical groundbeds.
Each groundbed will consist of six (6) vertically installed MMO anodes on a single string in a borehole
20 metres deep, with an active length of approximately 12 metres. This configuration will be refined as
necessary during later Detail Design. Based on a pessimistic groundbed site soil resistivity of 2,500
Ωcm, groundbed and circuit resistance is calculated to be 1.72 ohms.
Given the high chloride and sulphate content and attendant low resistivity along the trunkline corridors,
temporary GACP is considered necessary to protect the trunklines for a maximum two-year period prior
to energizing a permanent ICCP system.
In accordance with ISO 15589-1 [Ref 17] the design current density for an onshore pipeline with this
coating type for the required system life of 25 years is conservatively taken as 0.2 mA/m2 and for a 2-
year life TCP system is taken as 0.02 mA/m2. This specification factors Coating Breakdown Factor
(CBF) into a single, overall current density figure and is the baseline for this project.
Temporary CP and test facilities will be provided in accordance with ISO 15589-1.
2 Introduction
2.1 Project Description
In the Rumaila fields, source water is injected via Cluster Pumping Stations into two different reservoirs:
Mishrif and Main Pay. At each CPS station, injection water is routed from the CPS high pressure pumps
to Main Pay and Mishrif water injection manifolds. Main Pay manifolds are located within the CPS fence
line and Mishrif manifolds are in the field, outside the CPS. Mishrif manifolds are connected to the CPS
via a trunkline. Water is distributed from the manifolds via flowlines to reinjection wells for enhanced oil
recovery. Refer to Figure 2.1 for CPS WI pump schematic.
Each CPS station has Four (4) fixed speed source water injection pumps which take suction from a
common supply header and discharge to Main Pay and Mishrif manifolds. In CPS1 to CPS4, two (2) of
four (4) CPS pumps are dedicated to Main Pay manifold and other two (2) pumps discharge are
connected both Main Pay and Mishrif manifolds. In CPS5, only one (1) pump is dedicated to Main Pay
manifold and remaining three (3) CPS pumps are connected to both Main Pay and Mishrif manifolds.
Mishrif production plays a critical role in maintaining field production and in time, with the decline of the
Main Pay reservoir, will become the principle producing reservoir. Analysis of operating data has
confirmed high pressure drop in the trunklines which needs to be debottlenecked for increase flow to
mantain arrival pressure at the field manifolds. The replacement trunklines should therefore not just be
a like-for-like replacement. The selected sizes need to debottleneck current and future injection
requirements.
The existing trunklines supply high pressure water in the range of 165 - 200 bar (with design pressure
of 233 barg) from the CPS pumps to the Mishrif field manifolds. They also suffer from corrosion/ erosion
problems. Inspections carried out at CPS1 and CPS2 have identified wall thickness reduction below the
MAWT. There is also uncertainty over the specification of the pipeline material used in the construction
of the trunklines; many have been built to #900 rather than 1500#. These trunklines have been identified
as having a high risk of catastrophic failure with consequential risk of fatalities to personnel close to the
rupture point. The failure of these lines will also lead to a significant loss of injection capabilities and
consequently substantial production losses. An Emerging Risk Notification has been raised with an
ORA in place as a short-term safeguard to continue the operation of these sections of pipes [Ref. 28].
Thus, replacement trunklines are required to eliminate the risk of fatalities to personnel, reduce the
water injection losses, achieve wells target injection rates, and improve the integrity of the pipeline.
The scope of the study is limited to the replacement of the trunklines only. Existing CPS facilities, Main
Pay manifolds, Mishrif manifolds, flowlines and injection wells are all excluded from the scope; if
mentioned it is only to provide a complete description of the process. Ten source water trunklines are
to be replaced in two orders of priority. The priority order is based on the severity of corrosion in existing
trunklines.
1 CPS1 FM7
2 CPS2 FM9
3 1 CPS3 FM10
4 CPS4 FM8
5 CPS5 FM4
6 CPS1 FM5
7 CPS4 FM6
8 2 CPS5 FM1
9 CPS5 FM2
10 CPS5 FM3
CPS1-FM5 0430WD-N-WM-CP01-PL-DAG-0001-001
CPS1-FM7 0430WD-N-WM-CP01-PL-DAG-0002-001
CPS2-FM9 0430WD-N-WM-CP02-PL-DAG-0001-001
CPS3-FM10 0430WD-N-WM-CP03-PL-DAG-0001-001
CPS4-FM6 0430WD-N-WM-CP04-PL-DAG-0001-001
CPS4-FM8 0430WD-N-WM-CP04-PL-DAG-0002-001
CPS5-FM1 0430WD-N-WM-CP05-PL-DAG-0001-001
CPS5-FM2 0430WD-N-WM-CP05-PL-DAG-0002-001
CPS5-FM3 0430WD-N-WM-CP05-PL-DAG-0003-001
CPS5-FM4 0430WD-N-WM-CP05-PL-DAG-0004-001
Such a system requires no external power source but is reliant upon a low environmental resistivity and
has a limited and finite current capability and throwing power (the distance protective current can be
spread).
As noted above, GACP systems have the benefit of being totally independent and they are not reliant
upon an external power supply. However, once designed, their capacity and output is fixed; and this
will naturally decrease with increasing age, as anodes deplete and coatings breakdown. In addition,
should site circumstances change, a GACP system’s output and/or longevity cannot be increased
without retrofitting additional anodes.
A large current demand and/or long system life necessitates a large volume and weight of anode
material, which can become impractical to install. GACP systems therefore tend to be used on short
onshore pipelines, locations where a suitably reliable mains power supply is unavailable, small subsea
structures, very large structures where anode weight can be easily distributed or offshore pipelines and
flowlines.
For this project, ICCP has been stipulated [Ref 1, 2] and GACP is therefore considered only for provision
of temporary protection during construction, not for permanent CP. Magnesium alloy anodes are
specified for temporary CP prior to energising of the permanent ICCP system and will be utilised for this
project. Packaged Zinc anodes or Zinc Ribbon will be used for stray current dissipation or as earthing
electrodes.
4.1.3.2 ICCP
An impressed current cathodic protection system (ICCP) achieves the same ultimate result as GACP
but uses a generally inert anode material that is driven by an external DC supply (often a transformer
rectifier), thereby ‘impressing’ a current upon the parent metal. Such a system can be effectively used
in a much higher soil resistivity and can be designed to provide a large current output that is adjustable
and/or controllable and, with a much larger driving voltage, greater throwing power.
ICCP systems can be designed to cater for high current demands and/or long system life requirements
for onshore installations and can be automatically controlled to cater for changing soil/groundbed
conditions, such as water table level and deterioration of pipeline coating integrity with time. This makes
such systems very flexible and able to cater for changing circumstances. However, ICCP systems rely
on a constantly available external power supply and if, for whatever reason, that fails, CP is entirely lost
(albeit a well-coated pipeline, particularly onshore, may take several days to depolarise).
Individual ICCP anodes can provide a much higher current output and, for a given current output, are
much lighter than equivalent GACP anodes.
Even when utilising standard construction materials, there is a risk of overprotection with ICCP that
could result in dis-bonding of the pipeline coating and, dependent on the overall system output, a
likelihood of interference on other adjacent structures or pipelines.
Pipelines with ICCP systems installed can be fitted with fixed reference electrodes to monitor potentials.
These can be used to maintain a fixed minimum protection potential that will be adjusted as soil
conditions change and/or the pipeline coating deteriorates.
In accordance with the Statement of Requirements [Ref 1], ICCP is the selected permanent CP system
for this project.
Although the replacement trunklines will be laid approximately parallel to and close to the existing
trunklines, each will be treated as a separate, independent entity with respect to provision of ICCP, on
the premise that any existing CP system(s) will be de-energised. This will need to be confirmed during
Detail Design.
In areas with soft soil or high water table it is essential that the borehole be cased to prevent collapse
and, dependent on total depth, this would usually be with a metallic casing deeper down and non-
metallic casing closer to the surface. It is possible to utilise drilling rigs that can install and recover
casings during installation, but in areas with a high water table such as for this project, leaving the
casing in place is a better option because it becomes part of the groundbed and eventually corrodes
away.
Anode strings, or individual anodes (sometimes bare, sometimes themselves cased), are lowered into
the borehole and the borehole is backfilled with coke breeze (either poured or liquefied and pumped)
as each anode is installed.
Such groundbeds can be conveniently designated as ‘Semi-deep’ or ‘Deep’.
4.1.4.4 Semi-deep
If the resistivity profile indicates that a ‘shallow’ vertical installation will achieve the required circuit
resistance, then a semi-deep installation can be used; thus avoiding the specialist equipment necessary
for a deeper borehole. This can be for a single anode at, say 4-metre depth, and up to 10 anodes in a
30-metre deep borehole.
With the high water table and available site soil resistivity data, the resistivity profile permits the use of
a 20-30 metre deep borehole; placing the anodes well below pipeline invert level and thus enabling a
good spread of current to the selected portion of the flowline network.
Given the CPS and trunkline network configuration, semi-deepwell groundbeds up to 30 metres deep
are viable for independent provision of ICCP, dependent on actual site soil resistivity profile.
4.1.4.5 Deep
Dependent on the location and geology, a deepwell installation can be upwards of 100-200 metres
deep, with multiple anodes in the lower, active portion and a considerable upper inactive length with no
anodes. Boreholes to this depth permit the groundbed to be placed geographically closer to the
pipeline(s) to be protected, since they are already remote as a result of their depth and they can
distribute current for considerable distances.
The downside is that an extensive drilling operation and attendant specialist equipment is required and
for this application is unlikely to be necessary. Given the relatively short pipeline lengths and resultant
low current demand; coupled with low resistivity, an extensive ‘deepwell’ installation will not be
considered further for this application.
4.1.4.6 Wire anode
Continuous wire anodes are run closely alongside the pipeline(s) to be protected and therefore need
no additional space; and can generally be fitted after pipeline installation but prior to back filling. This
combination of operations would not necessarily be carried out in a single day. Wire anodes can provide
an extremely even and easily controllable current output (and thus pipeline potential), in a very local
area; thus minimising interference risk and over-protection of CP-sensitive pipeline materials.
Wire anodes are particularly useful in congested areas, where they can be conveniently positioned
between parallel pipelines in order to provide even current distribution to both without risk of shielding.
Wire anodes are thus ideal for pipelines where low, even current is required and/or where minute control
of protective potential is required.
Given that this project will incorporate individual flowlines from each CPS, wire anodes will not be
considered further for this project.
4.1.4.7 Selected ICCP Groundbed Solution
Given the CPS and trunkline network configuration, semi-deepwell groundbeds are selected for
provision of ICCP for this application.
Full design of cathodic protection systems will require a ground survey to determine soil resistivity vs
depth.
4.1.5 Design Parameters and Assumptions
4.1.5.1 General
Design parameters used in the cathodic protection design have been extracted from the Statement of
Requirements [Ref 1] unless stated otherwise and are reproduced herein for information.
The CP system for the onshore pipelines shall consist of multiple ICCP installations, with supplementary
packaged Magnesium anodes for temporary protection during construction and prior to energisation of
the ICCP systems.
The design code requirement for cathodic protection of the trunklines is ISO 15589-1 [Ref 17].
4.1.5.2 Design Life
In accordance with the BOD [Ref 2]., the design life of the system is 25 years.
4.1.5.3 Pipeline Design Data
Materials selection and internal corrosion analysis is still ongoing although individual trunkline diameters
have been confirmed as being 24” NPS and wall thickness is confirmed as 30.96mm with a nominal
3mm CA .
For each pipeline the nominal WT, excluding corrosion allowance, is assumed for attenuation purposes.
4.1.5.4 Temperature Data
The maximum operating temperature is taken to be 60°C.
4.1.5.5 Soil Resistivity
Sample soil resistivity data is available from basic surveys conducted by FUGRO and reported in
Geotechnical Interpretative Reports [Ref 29, 30]. Two electrical resistivity tests were performed using
the 4 pin Wenner vertical electrical sounding method and the apparent resistivities were between 0.4
Ωm to 0.9 Ωm, which corresponds to severely corrosive soils. This is in line with the significant sulphate
and chloride contents also reported.
Mean pH value is 8.3, meaning that the soils are classified as moderately alkaline.
Based on this data and the fact that the Rumaila field has a high water table; for preliminary design
purposes, an assumed pessimistic maximum groundbed resistivity value of 2,500 Ωcm is assumed for
CP design purposes. This will need to be confirmed by a dedicated soil resistivity survey.
4.1.5.6 Burial Status
All flowlines within the scope will be totally buried for their entire length, rising above ground only at
each end, where each will be electrically isolated using Monolithic Isolation Joints (MIJ).
4.1.5.7 Crossings
The preliminary routing of the trunklines between CPS and FM locations has highlighted that there are
a variety of crossings of roads, canals and railways. As routings become finalised during Detail Design,
all potential crossings and any required adverse potential mitigation and/or cross-bonding will need to
be taken into consideration.
Crossings have been identified and tabulated based on trunkline routing maps [Ref 6 and Refs 7 to 15
inclusive] and the Pipeline Crossing Schedule [Ref 3] and for this preliminary Pre-FEED design, an
initial allowance for additional testposts, bonding boxes, cabling and zinc anodes for possible mitigation
purposes has been made.
4.1.5.8 Assumptions
The following assumptions have been made in processing the initial CP calculations:
1) Resistivity data is limited and the lack of definitive location-specific data makes confirmation of
a specific groundbed configuration difficult; but for preliminary design purposes a maximum
2500 Ωcm is pessimistically assumed. This will be refined during later Detail Design once
resistivity data becomes available or a full resistivity survey has been conducted. Vertical semi
deep groundbeds have been selected as the optimal solution for this application on the premise
that ROO has approved drilling contractors;
2) It is assumed that access to plant power supply can be made available at all locations and
TRUs for that location will be configured to utilise the available voltage and frequency. It is
further assumed that in the first instance a domestic single phase 220-240VAC supply can be
accessed. An assessment of available power supplies at each CPS will need to be made before
TRU input supply can be confirmed;
3) Given the anticipated high chloride content soil, allowance will be made for a magnesium
anode-based Temporary CP (TCP) system to provide protection during pipe laying operations
and prior to energization of the permanent ICCP system;
4) Onshore pipeline coating is taken as a minimum of 3mm factory-applied 3LPE, with
polyurethane being selected for railway and canal crossings;
5) Current density for onshore buried pipelines has been conservatively taken as 0.2 mA/m²
following ISO 15589-1 [Ref 17] recommendation;
6) A monolithic isolation joint (MIJ) will be fitted at each pipeline soil entry/exit point, between
which the onshore ICCP system will provide protection;
7) The average pipe joint length is taken as 12.2m.
Table 5.1: Source Water Trunkline Surface Area and ICCP Current Demand
(1) (2) (3) (4) (5) (6) (7)
Priority CPS FM OD OD WT Length SA Coating CD Current
2 2
(") (m) (mm) (m) (m ) (mA/m ) (A)
2 CPS1 FM5 24 0.6096 27.96 4258 8970.0 3LPE 0.2 1.97
1 CPS1 FM7 24 0.6096 27.96 3832 8072.6 3LPE 0.2 1.78
1 CPS1 FM7 24 0.6096 27.96 560 1179.7 PU 0.3 0.39
1 CPS2 FM9 24 0.6096 27.96 1781 3751.9 3LPE 0.2 0.83
1 CPS3 FM10 24 0.6096 27.96 2279 4801.0 3LPE 0.2 1.06
2 CPS4 FM6 24 0.6096 27.96 1192 2511.1 3LPE 0.2 0.55
1 CPS4 FM8 24 0.6096 27.96 3755 7910.4 3LPE 0.2 1.74
1 CPS4 FM8 24 0.6096 27.96 550 1158.6 PU 0.3 0.38
2 CPS5 FM1 24 0.6096 27.96 4267 8989.0 3LPE 0.2 1.98
2 CPS5 FM2 24 0.6096 27.96 5053 10644.8 3LPE 0.2 2.34
2 CPS5 FM3 24 0.6096 27.96 4034 8498.1 3LPE 0.2 1.87
1 CPS5 FM4 24 0.6096 27.96 5898 12424.9 3LPE 0.2 2.73
(1)
OD values confirmed
(2)
Quoted WT of 30.96mm less 3mm CA
(3) Quantities in accordance with pipelines MTO [Ref 5] (without any margin/contingency). These lengths do not
include the piping from pig trap areas to/from CPS/FM, which is above‐ground piping (ASME B31.3)
(4)
All surface areas include 10% contingency
(5)
Bulk trunkline coating is 3LPE, HDD crossings have PU coating
(6)
Most conservative CD quoted for 3LPE in ISO 15589‐1
(7)
Includes 10% allowance
Table 5.2: Source Water Trunkline Surface Area and Temporary GACP Current Demand
(1) (2) (3) (4) (5) (10) (11)
Priority CPS FM OD OD WT Length SA Coating CD Current
2 2
(") (m) (mm) (m) (m ) (mA/m ) (mA)
2 CPS1 FM5 24 0.6096 27.96 4258 8970.0 3LPE 0.02 197.34
1 CPS1 FM7 24 0.6096 27.96 3832 8072.6 3LPE 0.02 177.60
1 CPS1 FM7 24 0.6096 27.96 560 1179.7 PU 0.03 38.93
1 CPS2 FM9 24 0.6096 27.96 1781 3751.9 3LPE 0.02 82.54
1 CPS3 FM10 24 0.6096 27.96 2279 4801.0 3LPE 0.02 105.62
2 CPS4 FM6 24 0.6096 27.96 1192 2511.1 3LPE 0.02 55.24
1 CPS4 FM8 24 0.6096 27.96 3755 7910.4 3LPE 0.02 174.03
1 CPS4 FM8 24 0.6096 27.96 550 1158.6 PU 0.03 38.23
2 CPS5 FM1 24 0.6096 27.96 4267 8989.0 3LPE 0.02 197.76
2 CPS5 FM2 24 0.6096 27.96 5053 10644.8 3LPE 0.02 234.19
2 CPS5 FM3 24 0.6096 27.96 4034 8498.1 3LPE 0.02 186.96
1 CPS5 FM4 24 0.6096 27.96 5898 12424.9 3LPE 0.02 273.35
(1)
OD values confirmed
(2)
Quoted WT of 30.96mm less 3mm CA
(3) Quantities in accordance with pipelines MTO [Ref 5] (without any margin/contingency). These lengths do not
include the piping from pig trap areas to/from CPS/FM, which is above‐ground piping (ASME B31.3)
(4)
All surface areas include 10% contingency
(5)
Bulk trunkline coating is 3LPE, HDD crossings have PU coating
(10)
Conservative CD for TCP quoted for 3LPE in ISO 15589‐1
(11)
Includes 10% allowance
For the proposed 3LPE coating, a pessimistic coating resistance value of 100,000 Ωm2 is assumed for
‘start-of-life’ and 10,000 Ωm2 for ‘end-of-life’ will be used, as this provides considerable contingency.
Figure 5.1 on the following page details the calculation for a finite length of trunkline for this project and
these calculations show that:
For the smallest diameter, basic WT 24” trunkline, (less assumed 3mm WT loss as corrosion
allowance) the maximum distance current will spread from a single groundbed is approximately
39.8km
Pipeline Attenuation
The attenuation of current and cathodic protection potentials along a pipeline is estimated using the specified and indicated pipeline
design parameters and their relation to the specified pipeline coating type. Standard formulae are applied to these parameters to
approximate the attenuation model along the pipeline according to the locations and quantities of current drain points.
Where:
Ex = polarization along the pipeline a distance x metres from the drain point (V)
Em = polarization at the end of the pipeline, a distance L from the drain point (V)
= attenuation constant (m-1)
L = pipeline length - from drain point to end of the pipeline (m)
Where: And:
RL = r O/( Ds) RT = RI/( D)
Where:
rO = pipe steel resistivity (Ohm.m) D = pipeline diameter (m)
RI = coating insulation resistance (Ohm.m²) s = pipeline w all thickness (m)
To provide a contingency for end-of-life conditions, a substantial reduction in coating resistance is assumed, such that:
RI = 10000 Ohm.m2
and :
= 2.53728E-05 m-1
Considering the specified limits of potential along the pipeline; minimum -0.95 V vs. Cu/CuSO4, maximum -1.200 V vs. Cu/CuSO4,
and assuming a natural potential of -0.500 V vs. Cu/CuSO4, minimum and maximum allow able degrees of polarization are
d
E t i d = 0.45 V
MIN
EMAX = 0.70 V
Attenuation must be sufficiently low w hereby the maximum polarization is not exceeded at the drain point w hile at least the
minimum polarization is achieved at the end of the pipeline.
So: And:
Em = EMIN EO = EMAX
= 0.45 V = 0.70 V
Note that to provide for a worst-case attenuation situation, the pipeline WT is taken to be exclusive of
any corrosion allowance to cater for minimum end-of-life WT. No specific allowance for current drain to
earth or foreign structures has been included in the calculations.
An ICCP TRU could thus be placed at either end of any given trunkline to provide an adequate current
distribution to the entire pipeline length, with an anode configuration to suit. TRUs will thus be placed
at selected CPS locations.
5.3.4 Design Life
The required system design life, in accordance with Ref 2, is 25 years.
ICCP groundbeds, of whatever configuration, can readily be designed for this duration and provided
that all buried connections are carefully sealed during installation there should be no issue with
underground components.
TRUs are to be located at relevant CPS sites and will thus be in secured locations, whereby the required
design life is not an issue. However, it should be noted that other above-ground facilities such as test
posts, JBs, etc. may suffer damage due to building works, collision, vandalism, etc.
Calculation Results
Anode Resistance ( ) :
2,500 4 48.0
R = . ln - 1
2 48.0 7.5
= 8.29 . 2.24
= 18.590
1750 - 950
I (a) =
18.590
= 43.03 mA
Anode Life :
Y . 8766 . I
W =
1000 . C . U
= 4.846 kg
Therefore;
5.6 CP Ancillaries
5.6.1 Test Facilities
ISO 15589-1 2015 [Ref 17] and other generic cathodic protection specifications, stipulate that test
stations shall be fitted at the following locations and frequency as a minimum:
Every 1.0 km for pipe-to-soil potential monitoring
At all cased crossings (none anticipated for this scope)
At all isolation joints
At all HV and foreign pipeline crossings
All test stations will be fitted with a permanent reference electrode, a polarization coupon and one or
more magnesium anodes for temporary protection, as applicable.
Crossings have been identified and tabulated based on trunkline routing maps [Ref 6 and Refs 7 to 15
inclusive] and the Pipeline Crossing Schedule [Ref 3].
Pipeline bonding/interference testing boxes have been assigned for each identified crossings corridor,
or as test posts for individual pipelines if so listed.
(1)
OD values confirmed
(12)
4.1kg Mg anodes to provide 2 years TCP
XTP Crossing Test Post (1 each side of road/rail/canal)
IJTP Isolation Joint Test Post
Pipe XTP Individual pipe crossing
STP Standard Test Post
Current Span Current Span Test Post
(13)
6‐way resistor bonding/interference testing Junction Box at pipeline corridor crossings
Note that during Detailed Design, once all routes and crossings are confirmed, actual quantities can be
rationalised by multi-purposing test facilities where possible.
TRUs are designed as identical at each of the required CPS, such that there is consistency and
interchangeability, plus a simplification of maintenance and ease of providing across-the-board
commissioning and operational spares. Each TRU shall be 15A36V DC output and capable of voltage
or current control and shall be designed and configured for manual control. Each shall be equipped with
facilities to feed output and fault condition data to a central control room, if so required.
Current shall be distributed to individual pipelines via a dedicated cathode return junction box, fitted
with balancing resistors and shunts to proportionally split the current to different pipeline diameters
and/or lengths.
Note that new trunkline tie-in points are, in some cases, several hundred metres from the TRU location
within the CPS perimeter. Allowance has been made to utilise greater cross-section feeder cables in
these instances. Full voltage drop balancing will be required during Detail Design.
5.6.9 CPS Piping Underground Sections
Above ground piping between trunkline CPS tie-in point and pig traps is generally run above ground on
sleepers but there are two locations where part of this will be buried:
i. CPS4-FM8 Road Crossing
For the CPS4-FM8 buried road crossing segment, assumed to be direct buried, galvanic CP will be
required. Recommendation is to use flanged upper bend and fit flange isolation kits above ground to
isolate the crossing section. CP test post with cables to be connected to 'live' and 'dead' sides of isolated
flange each side of road; plus 2 x 17kg 1.7V packaged magnesium (Mg) anodes, connected via link bar
to 'live' (crossing) side. Note that Mg anodes are necessary due to high local resistivity but Mg anodes
will need to be replaced after 10-12 years due to self- corrosion.
For the CPS5 buried segment, assumed to be direct buried, galvanic CP will be required.
Recommendation is to use flanged upper bend and fit flange isolation kits above ground to isolate the
crossing section. CP test post with cables to be connected to 'live' and 'dead' sides of isolated flange
each end of the buried section of each trunkline; plus 2 x 17kg 1.7V packaged magnesium (Mg) anodes,
connected via link bar to 'live' (buried) side. Note that Mg anodes are necessary due to high local
resistivity but Mg anodes will need to be replaced after 10-12 years due to self- corrosion.
5.6.10 Anchor Blocks
If anchor blocks are fitted to any of the pipelines, it is essential that:
a. The pipeline is electrically isolated from any metallic portion of the anchor block, including
rebars;
b. Any CP associated with the anchor block is independent GACP, with independent monitoring
facilities
5.6.11 Protection Levels and Over-Protection
In accordance with industry norms and site carrion history, a design protected potential at least as
negative as -0.95 V vs. Cu/CuSO4 is to be considered for buried onshore piping. Note that the definition
of cathodic protection being achieved is when a polarized (Instant ‘OFF’) structure-to- soil potential of
–0.95V wrt Cu/CuSO4 is achieved. For most types of modern coatings, a maximum negative instant
‘OFF’ should not exceed –1.50V wrt Cu/CuSO4 to minimize the risk of cathodic disbondment.
These criteria are industry standards utilised to determine the effectiveness of the cathodic protection
systems and the level of protection achieved.
As stated above, a pipe-to-soil potential more negative than the recommended values can lead to over-
protection of the substrate, which can in turn lead to cathodic disbondment of coatings or the risk of
hydrogen embrittlement.
Susceptibility to hydrogen-induced cracking (‘embrittlement’) can be a result of the introduction of
hydrogen during forming, coating, plating, cleaning, and finishing operations’. Hydrogen can also be
introduced over time through environmental exposure (soils and chemicals, including water), corrosion
processes (especially galvanic corrosion), cathodic protection, and/or from hydrogen generated by
corrosion under a coating. To be susceptible, a combination of three factors is required: presence of
(and diffusion of) hydrogen, susceptible material, and stress, which is application-dependent.
For susceptible materials (such as coated high-strength bolts, where hydrogen is often present after
manufacturing and may also be added over time by cathodic protection, galvanic connections, etc.),
cracking will initiate when a sufficient stress has been reached.
Careful control of CP potential will ensure that hydrogen embrittlement does not occur.
3 MMO Anode (1000 x 25mm dia tubular) string c/w integral, fully sealed, 40m x each 6
25mm2 KYNAR/HMWPE cable tail, comprising 6 off anodes at 1.2m spacing from (incl 1
bottom anode (approx 12m active length), 40m x 6mm polypropylene support rope, spare)
6 off anode spacers, end weight
Groundbed headworks to be provided by Civils Contractor
4 Calcined Petroleum coke breeze tonne 5
Density approx 800‐900kg/m3
Bulk resistivity <50 ohm cm
Suitable for pumping into deepwell borehole
5 SS316 Anode Junction Box, typically 600h x 500w x 320d each 5
fitted with backing board, shunts, bus bar
2 way, glanded to suit
c/w galvanised steel mounting frame
6 SS316 Cathode Junction Box, typically 600h x 500w x 320d each 5
fitted with backing board, resistors and shunts, bus bar
6 way, glanded to suit
c/w galvanised steel mounting frame
7 SS316 Bonding/Interference Test Box, typcially 600h x 500w x 320d each 53
fitted with backing board, resistors and shunts, bus bar
6 way, glanded to suit
c/w galvanised steel mounting frame
8 Lockable Big Fink test post cap and fittings, c/w 11‐way terminal panel and Ni‐plated each 236
brass bolts/washers/nuts, 1.75m x 3"Φ galvanised steel conduit; for IJ testing, CP
testing, bonding
9 MC Miller, or equivalent, Polarisation Coupon, c/w 10m x twin 4mm2 THHN cable tail each 246
* Nominal AC supply only, to be amended to suit actual supply available (which may be 440VAC 3‐phase)
Monolithic isolation joints and flange insulation kits to be specified and supplied by pipeline contractor on confirmation of all
relevant pipeline and flange details