Wadi AD Dawasir Solar PV Solar Photovoltaic Independent Power Project

MEETING TITLE: Weekly Co-ordination Meeting #27

MEETING LOCATION: Online MOM REFERENCE NO. : #27 Week

MEETING DATE: 01/Nov/2023


REPORT DATE: 01/11/2023
MEETING TIME: 10.30 A.M (India)

REPORTED BY: Rahul Mandal CONFIDENTIAL: No

THE PARTIES ACKNOWLEDGE THIS IS AN ACCURATE REPORT OF THIS MEETING

Sargent & Lundy SEPCO

Name: Rakesh Raghav


Name:
Title: Renewables Manager
Title :
Name: Rahul Mandal
(electronic initial)
(electronic initial)

ATTENDEES
Organization Name Email Address
SAMT Fouad Maksoud
Wang Guodong
Xia Mingwen
SEPCO Zhang Mingfei
Guan Shousuo
Zhang Shuhao
Rakesh Raghav
Sargent &
Rahul Mandal
Lundy
Imran Mushtaq
Other

Minutes of Meeting (date) Page PAGE 1 of NUMPAGES 8


Minutes of Meeting

Date & Location

No. Contents By Due


1 N.A

ACTION ITEMS

Item Action Items Designation Assigned To Due Date


Additional information requests on ESF (if any) will be prepared and
shared by S&L

10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.

17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. S&L 19/05/23
will check and feedback.
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23

Minutes of Meeting (date) 2 13


Minutes of Meeting

Date & Location

ACTION ITEMS

Item Action Items Designation Assigned To Due Date


Additional information requests on ESF (if any) will be prepared and
shared by S&L

10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.

17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. S&L 19/05/23
will check and feedback.
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23

Minutes of Meeting (date) 3 13


Minutes of Meeting

Date & Location

ACTION ITEMS

Item Action Items Designation Assigned To Due Date


Additional information requests on ESF (if any) will be prepared and
shared by S&L

10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.

17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. S&L 19/05/23
will check and feedback.
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23

Minutes of Meeting (date) 4 13


Minutes of Meeting

Date & Location

ACTION ITEMS

Item Action Items Designation Assigned To Due Date


Additional information requests on ESF (if any) will be prepared and
shared by S&L

10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.

17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. S&L 19/05/23
will check and feedback.
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23

Minutes of Meeting (date) 5 13


Minutes of Meeting

Date & Location

07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. S&L 14/06/23
09/08 – Awaiting TTE’s response for the TQ raised earlier.
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. S&L 14/06/23
09/08 – Awaiting TTE’s response for the TQ raised earlier.
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.

Minutes of Meeting (date) 6 13


Minutes of Meeting

Date & Location

07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. S&L 14/06/23
09/08 – Awaiting TTE’s response for the TQ raised earlier.
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. S&L 14/06/23
09/08 – Awaiting TTE’s response for the TQ raised earlier.
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.

Minutes of Meeting (date) 7 13


Minutes of Meeting

Date & Location

07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. S&L 14/06/23
09/08 – Awaiting TTE’s response for the TQ raised earlier.
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. S&L 14/06/23
09/08 – Awaiting TTE’s response for the TQ raised earlier.
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.

Minutes of Meeting (date) 8 13


Minutes of Meeting

Date & Location

07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. S&L 14/06/23
09/08 – Awaiting TTE’s response for the TQ raised earlier.
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. S&L 14/06/23
09/08 – Awaiting TTE’s response for the TQ raised earlier.
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
3. SMB Grouping S&L General
Due to the discussion with TTE, it is required to reduce the number
of trenches, causing the change of layout.

07/09- SMB grouping is being discussed with SEPCO, PVH.


13/09- Under discussion. S&L will send the constraints on the
bidding stage layout.
27/09- SEPCO confirmed to follow Option -2 (with 4 trenches).
04/10 -Under preparation. S&L has shared the final layout with
SEPCO. Same to be forwarded to PVH.

Minutes of Meeting (date) 9 13


Minutes of Meeting

Date & Location

11/10 – S&L will submit the SMB grouping by 11/10/23.


Submit Level & Grading drawing and SEPCO has confirmed the
clarification.

07/09- Substation are grading drawing submitted by S&L on


06.09.2023
13/09 – S&L submitted. S&L to check and confirm that the excavated
material can be used for backfilling also for the structures.
20/09- Need to be concluded with TTE.
27/09- S&L to check the cut and fill qty. for 0mm, 50 mm , 100mm,
4. S&L General
150 mm and 200mm tolerance.
04/10 – S&L has submitted. To be forwarded to TTE.
11/10- S&L has submitted the revised drawing. SEPCO requested to
submit IFC version.
18/10 – S&L will submit the leveling and grading drawing of the PV
area by 18/10.
25/10- S&L has already submitted the document and awaited
comments from DNV/TTE.

Required input information for the suppliers

07/09- S&L clarified that all the required documents form vendor are
listed in the respective technical specification.
However, SEPCO informed that delivery timeline of the vendor
documents are very long which is not suitable for the overall project
progress. Hence, SEPCO requested S&L to provide the critical input
5. document list from vendor for the critical items like: AIS, GIS, ITS, S&L General
Power transformer.
13/09 – S&L is working on it and share progressively.
20/09 – Ongoing.
27/09 – S&L has shared one set of input list. SEPCO is following up
with vendors for inputs.
04/10 – On going.
11/10- S&L has submitted a revised list on 10/10/23.
Internal Road of Substation including DWG and CAL to release.
27/09- S&L has submitted the Internal road design. SEPCO to
6. forward the document to TTE. CIV
04/10 – SEPCO to forward to TTE. Awaiting for TTE response.
11/10 – Awaiting TTE’s comments.
Design calculation for 132/33kV Power Transformers Foundations &
Fire wall Foundation shall be released by 27th Sept 2023.
Kindly provide the required input for SEPCO.
27/09- S&L has shared the required input list with SEPCO.
04/10 – Awaiting inputs from OEM.
7. 11/10 – Input from vendor is required. SEPCO will follow up with CIV
vendor for the same.
18/10 – S&L will review the input received by vendor and shall
provide feedback by 21/10.
25/10- S&L has already submitted the clarification to SEPCO; Vendor
response is awaited on the same.
8. Please update the weather station technical specification , due to ELE
cancel the cloud sensor.
27/09 – SEPCO will revert back on this requirement.
04/10- Separate sensors (cloud CAM, pyranometers etc) and
separate servers, PC etc are not required for Weather and Power

Minutes of Meeting (date) 10 13


Minutes of Meeting

Date & Location

forecasting system.
11/10 – For the forecasting system : point shall be open till
finalization of SCADA vendor.
Turnkey Technical Specification for Fire protection and detection
system RC.

L&T-S&L_ Considerations for Fire Protection & Detection system.


27/09- S&L has submitted the specification. SEPCO to submit to TTE.
9. 04/10 – S&L has submitted the technical speciation. Awaiting TTE’s MEC
response.
18/10- S&L shall response against the clarification by vendor on Dt.
27/10.
25/10- S&L shall respond on the above point by 27/10.

Please update the HCIS Asset Characterization Form according to the


project condition.
04/10 – S&L to provide a broad overview of the main assets of the
project.
10. General
18/10 – S&L to check the HCIS document received from vendor.
25/10- S&L submit the HCIS document received from vendor by
25/10.

Calculation for DC Solar cable and DC power cable ELE


18/10 – S&L submit above document on Dt. 17/10. Awaiting
11. SEPCO/TTE response.
25/10- Awaiting TTE/DNV response. .

CRS Reply of DC Cable、LV & Control Cable、MV Cable

18/10 – LV & Control Cable already submitted on 18/10. Balance


12. document shall be submitted by on Dt. 20/10. ELE
25/10- S&L shall submit above document by 26/10.

Review LV& MV switchgear tech proposal ELE


18/10 – LV& MV switchgear tech proposal is under by S&L team and
13. shall revert asap.
25/10- S&L shall submit comment/resolution on LV& MV switchgear
tech proposal by 27/10.
Issue Earthing MTO & Calculation
18/10 – S&L shall submit earthing calculation of the PV area on
21/10. Subsequently after receipt of the observation on calculation
14. ELE
document from TTE, MTO shall be furnished by S&L.

Technical Specification & RFQ for Plumbing System


S&L to respond the CRS for SEPCO reviewing
18/10 – S&L shall submit TS for plumbing on 20/10.
15. 25/10- CSR shall be submitted by 26/10. MEC

16. PVH Documentation to be reviewed by S&L and revert asap CIV


18/10 – PVH Documentation is under by S&L team and shall revert
asap.
Minutes of Meeting (date) 11 13
Minutes of Meeting

Date & Location

25/10- PVH Documentation is under by S&L team and shall revert


asap.
Design calculation of Foundation for 33 KV Substation Building by
Oct 30.
18/10 – SEPCO shall arrange the meeting with Pre-cast vendor.
Based on discussion with vendor/input, design calculation of
17. foundation for 33kv substation building shall be carried out and plan CIV
date shall be communicated to SEPCO accordingly.
25/10- SEPCO shall arrange the meeting with pre-cast vendor based
on the comments from S&L team on vendor document.

GA & RC Details of Foundation, Column (upto FFL), Plinth Beam and


Grade slab for 33kV Substation Building by by Oct 15.
18/10 – SEPCO shall arrange the meeting with Pre-cast vendor.
18. CIV
25/10- SEPCO shall arrange the meeting with pre-cast vendor based
on the comments from S&L team on vendor document.

Foundation Drawing for NGR Foundation by Oct 30.


18/10 – Foundation drawing for NGR shall be provided after
finalization of vendor.
19. CIV
25/10- NGR foundation shall be part of SST foundation document
based on available GA from the vendor.

Foundation Drawing for 132/33kV Power Transformer & Fire wall. By


Oct 18
18/10 – S&L submit the above document by 31/10.
20. CIV
25/10- S&L submit Foundation Drawing for 132/33kV Power
Transformer & Fire wall by 31/10 post receipt of the rail drawing.

Architectural Drawing - Plan, Section & Elevation of 132/33kV


Substation Pump House.by Oct 27
18/10 – SEPCO shall arrange the GA drawing of pump building from
21. Vendor. CIV
25/10 – SEPCO shall arrange the GA drawing of pump building from
Vendor.

GA & RC Details of Foundation, Column (upto FFL), Plinth Beam and


Grade slab for Pump House.by Oct 27
18/10 – SEPCO shall arrange the GA drawing of pump building from
22. Vendor. CIV
25/10- SEPCO shall arrange the meeting with pre-cast vendor based
on the comments from S&L team on vendor document.

Precast Vendor inputs. Kindly to issue the specification/requirements


to launch this work by Oct 13
18/10 – SEPCO shall arrange the meeting with Pre-cast vendor.
23. CIV
25/10- SEPCO shall arrange the meeting with pre-cast vendor based
on the comments from S&L team on vendor document.

BAHAR cable manufacturer's second round of clarification ,the TQ


had send email by 2023-10-16,please reply by 2023-10-17.
18/10 – S&L has already response to the above TQ on 17/10.
24. ELE
25/10 - S&L will the check the clarification on cable ( Sunway Co.
Ltd) and revert by 26/10.

Minutes of Meeting (date) 12 13


Minutes of Meeting

Date & Location

CRS Reply of PV area earthing layout ( Please consider considering


the main grounding network first in the drawing. Since there are
many CRS in the grounding of the equipment, can you distinguish the
grounding drawing of the equipment from the main grounding
network drawing)
25. ELE
18/10 – S&L shall submit the drawing as suggested by SEPCO team
for earthing layout showing earthing grid arrangement.
25/10 - S&L shall share the technical requirement of earthing
material. SEPCO team shall check and confirm the availability.

Drawing for cables.


18/10 – Drawing for Cable means DC Power, MV Cable and Earthing.
Details of cables/trenches shall be provided in the respective
26.
deliverables.
25/10 - MV cable sizing calculation shall be submitted by 27/10.

Indoor Lighting Layout - 33kV Substation Building.


18/10 – S&L team is working on the above deliverable shall be
27. release by end of next week. ELE
25/10 - MV cable sizing calculation shall be submitted by 27/10.

Please provide the documents required by the HCIS Fire Consultant


28. in order to input the FP FEED package. GEN
25/10 - S&L shall check and revert on the above point asap.
The limitation of Site Urgent Drawing List shall be reviewed and filled
asap.
29. 25/10 - S&L shall check internally and update the site urgent GEN
drawing to SEPCO.

Reply CRS pended in S&L.


30. 25/10 – S&L shall check pending CRS. GEN

Draft TQ of SVG for canceling transformer.


25/10 – S&L shall provide TQ of SVG for canceling transformer.
31. ELE
SEPCO shall arrange the datasheet from SVG Vendors to attach the
same in the TQ.
Confirm TQ for Combiner BOX _sungrow.
25/10 – S&L check the document and revert on the combiner box by
32. ELE
26/10.

Review GIS layout


33. ELE
25/10 – S&L check and revert on the GIS layout asap.
About SST&NGR manufacturer's TQ,it was send by 2023-10-24,it is
urgent ,so please reply by 2023-10-25.
34. ELE
25/10 – S&L shall check and revert on above point by 26/10.

Reviewing the RFQ for Precast Building and feedback by Oct 25th.
35. 25/10 – S&L shall check and revert on above point asap.

Minutes of Meeting (date) 13 13