Work Sequence

81.00
RUNWAY

℄ FLEXIBLE RUNWAY

30.00 7.50 3.00


RUNWAY SHOULDER BLAST PAVING
℄ BOX CULVERT

AXIS RUNWAY
LINE R

10 - Coring and light installation


9 - Wearing Course
8 - Binder course
7 - Base Course 4th layer +2.30
SLOPE = -1.5%
SLOPE = -1.5%
6 - Subbase on Shoulder SLOPE = -2.
5%

+1.45

0.42
+1.15

0.30
N.T.S

1 - SUBGRADE
-0.10

0.50

2 - Drainage layer
3 - Subbase
4 - Deep base and duct Bank
TO DRAINAGE SYSTEM

5 - Base Course 3 first layers


6 - Subbase on Shoulder

In few quantities: Pavement area : 1 150 000 Sq.m.


Subbase : 1 000 000 Tons
Hotmix Asphalt : 810 000 Tons