System Installation Manual


Installation

System Installation Part 1


SmartPath to AlluraClarity Upgrade

Table of Contents

1 INTRODUCTION .............................................................................................................................. 3
1.1 Document History ............................................................................................................................. 3
1.2 Required Tools ................................................................................................................................. 3

2 WORKFLOW .................................................................................................................................... 4
2.1 Before Installing ................................................................................................................................ 4
2.2 Parts that are Reused ....................................................................................................................... 4
2.3 Workflow Overview ........................................................................................................................... 6

3 INSTALLING REAR COVER EXTENDER ...................................................................................... 7

4 INSTALLING MCS AND MCC ....................................................................................................... 11


4.1 Putting MCS into Examination Room ............................................................................................. 11
4.2 Installing the Actuator or Fixed Column ......................................................................................... 11
4.3 Lifting Monitor Ceiling Suspension ................................................................................................. 13
4.4 Installing Actuator or Fixed Column to MCC .................................................................................. 18
4.5 Installing 56-inch Large Screen Monitor ......................................................................................... 21
4.5.1 Installing 56-inch Monitor on Monitor Ceiling Suspension ........................................................... 21
4.5.2 Installing Cables and Covers for 56-inch Monitor ........................................................................ 28
4.6 Installing 19-inch or 21-inch monitors ............................................................................................. 30
4.6.1 Insulation Plate for LCD 19- or 21-inch monitors ......................................................................... 30
4.6.2 Installing 19- or 21-inch Monitors and Interface on MCS ............................................................. 32
4.6.3 Installing Top Monitors with Insulation Plate ................................................................................ 34
4.6.4 Installing Top Monitors ................................................................................................................. 36

CSIP Security Labeling: CSIP Level 1:


This document and the information contained in it is strictly reserved for current Philips Healthcare (“Philips”) personnel, Philips licensed
representatives and Philips customers who have purchased a valid service agreement for use by the customer’s designated in-house service
employee on equipment located at the customer’s designated site. Use of this document by unauthorized persons is strictly prohibited. This
document must be returned to Philips when the user is no longer licensed and in any event upon Philips’ first written request.
Proprietary Notice:
This document and the information contained in it is proprietary and confidential information of Philips Healthcare ("Philips") and may not be
reproduced, copied in whole or in part, adapted, modified, disclosed to others, or disseminated without the prior written permission of the Philips
Legal Department. Use of this document and the information contained in it is strictly reserved for current Philips personnel and Philips customers
who have a current and valid license from Philips for use by the customer’s designated in-house service employee on equipment located at the
customer’s designated site. Use of this document by unauthorized persons is strictly prohibited. Report violation of these requirements to the
Philips Legal Department. This document must be returned to Philips when the user is no longer licensed and in any event upon Philips’ first
written request.
Warranty Disclaimer Language:
Philips provides this DOCUMENT without warranty of any kind, implied or expressed, including, but not limited to, the implied warranties of
merchantability and fitness for a particular purpose.
Limitations of Liability Language:
Philips has taken care to ensure the accuracy of this document. However, Philips assumes no liability for errors or omissions and reserves the
right to make changes without further notice to any products herein to improve reliability, function, or design. Philips may make improvements or
changes in the product(s) or program(s) described in this document at any time.

DMR163546, Rev: 01 CSIP Level 1 1 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4.7 Installing Intercom Microphone-Speaker Unit on MCS .................................................................. 37
4.8 Installing MCS Cable Hose ............................................................................................................. 39
4.9 Connecting the Examination Light .................................................................................................. 43
4.10 Installing Sealing Cap on X-ray-On Bracket ................................................................................... 44

5 INSTALLING SYSTEMS WITHOUT PHILIPS MCS ...................................................................... 45

6 INSTALLING CONTROL ROOM CONNECTION BOX ................................................................. 46


6.1 Installing Control Room Connection Box on Wall or Frame ........................................................... 46
6.2 Installing CRCB System Cables ..................................................................................................... 47

7 INSTALLING WALL CONNECTION BOX CABLE SETS............................................................. 50

8 INSTALLING AD7 PATIENT SUPPORT (IF AD5 IS REPLACED) ............................................... 50

9 UPGRADING EQUIPMENT RACK ................................................................................................ 50

10 PREPARING CABINET REUSED AND RELABELED CABLES ................................................. 51


10.1 M-Cabinet Cables ........................................................................................................................... 51
10.2 R-Cabinet Cables ........................................................................................................................... 52
10.3 2R-Cabinet Cables ......................................................................................................................... 53

11 CABINETS ..................................................................................................................................... 53

DMR163546, Rev: 01 CSIP Level 1 2 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
1 INTRODUCTION
This instruction is part 1 of the module that gives the procedure to install the SmartPath to AlluraClarity
upgrade.

1.1 Document History


Revision Reason of changes
01 AD5 replacement included
00 First issue

1.2 Required Tools

Tool kit, standard (TC129)


Hand pallet truck

Service PC (TC092) USB smart card reader (TC059)

Erroneous Ground Alarm Device (EGAD, TC029) Extractor tool (TC046)

DMR163546, Rev: 01 CSIP Level 1 3 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
Torque wrench (100 Nm) Transport wheel set (TC133)

2 WORKFLOW
2.1 Before Installing

WARNING
Make sure that all hospital power supplies are off.

WARNING
Do not manually lift heavy objects. Labor protection rules give the maximum weight for one
person (guideline is 23 kg).
For heavy objects, use tools or lift with more persons.

2.2 Parts that are Reused


For an overview of reused parts, refer to the Installation manual “Disassembly System” (DMR163545).
A schematic overview of reused parts is shown on the next page.

DMR163546, Rev: 01 CSIP Level 1 4 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
Cockpit
CB
M
R Gbe switch KVM witch
DRC
Video switch Video switch
PC box
Control Video Video Geo IPC 2k2 display PC Power on/off PS/2 extenders
RCB WCB WCB Monitor Monitor Monitor Monitor

EPNav PC
LUC
Rack mount
Geo PCU & Rotor control
Ext. Injector
EPmed Chameleon
Ethernet switch

Rec.&Mon. Scan converter


Chiller E2S E2S
(Ft) Converter
Geo Imaging Monitor Monitor Monitor (Lt)
Hand view data
Module Module switch Chiller
Scan converter
(Ft)
Xper
Speed Review Carto MPDU
(Lt) KVmA control
MPDU
Foot pedals controller Module
Module
Tube cooling Tube cooling
HT tank
DVD (Ft) (Lt)
XV EPNav
recorder KVM Xcelera EPC
TSM
M-cabinet R-cabinet 2R-cabinet E-cabinet K-cabinet
inter
com
M R 2R E K

Keyboard Mouse Keyboard Mouse Keyboard Mouse


Control room Technical room

Exam room Legend:


- re-use part (green)
- always replace part (black with red cross)
M/R - conditionally replace part (green with red dotted cross)
Ceiling rails - upgrade part (green dotted)

M inter
com
M
R 2R

Aux Monitor Monitor Monitor


WCB X-ray 2k2 ext.
Shield Video Video Pedestal
OK lamp WCB WCB box WCB
MCS

C-arm FDXD
5M
Grid monitor Xper
View
pad Module
Xper
Module
Table Equipment Rack Geo Imaging
accessories Pan Module Module
handle TTCB

Imaging Geo
Module Module
Trolley
collimator
IPC
Stand Tube (Witt)
injector Table
Hand
switch TBCB
floorplate
Foot pedals
AD7 remains, AD5 is
Foot pedals replaced

M R/E R

DMR163546, Rev: 01 CSIP Level 1 5 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
2.3 Workflow Overview

Disassembly is done.

Equipment
Install CRCB to existing wall bracket or Install new system cables from WCBs.
Install MCS. New AD7? rack
frame. (use cabling diagram) Yes Yes
present ?

See Note
56" or Install new AD7, refer
reused Prepare re use cables (MDVR, RTL Do an upgrade of
Install rear cover extender for M-cabinet to DMR162948 (AD7)
monitors? fiber) Install WCBs. Equipment rack,
and/or B-Cabinet. or to DMR166936
Refer to DMR165213.
(AD7 swivel).
Installation part 1 Yes

These installation
activities can be done Install monitor(s).
independently from each Install system cables
other. No from AD7
(use cabling diagram).
No No
Rework MCC/MCS:
· Cable hose
· X-ray-on light
· Intercom speaker Install system cables from CRCB: Install re used cables
· Install cables to the technical room (rack mount injector,
first, Then you can work in parallel hemo, local options)
with the cabinet installation.
Install system cables from MCS · Install other CRCB cables.
(use cabling diagram). (use cabling diagram).

All cabling prepared for


connecting the new
cabinets.

Prepare the cabinets for Unpack cabinets, refer to DMR101237.


cable connection.

Connect EGAD.

Note
Install M-cabinet, refer to Install R-cabinet, refer to
Do the MCS rework after or at the same DMR107785. DMR138821. FlexVision or EP
time with the cabinets. cockpit ?
Install cabinets It is important to have the cable hose on- Yes
time available in the technical room
Re-install the tube coolers. Install B-cabinet,
Install the detector chiller(s). refer to
Re-install scan converters DMR133796.
(option).

Installation part 2
Connect all system cabling to Install and connect control
Install and connect exam room
the cabinets (use cabling room equipment (UIs, Update generator firmware.
Cabinet cabling is most equipment (UIs, pedestal,
diagram), include EMC monitors, equipment to
time consuming and equipment to WCBs).
measures. WCBs, DVD receivers, ..)
difficult to work parallel
because of limited access.
Combine with parallel
activities in blocks next to
it.
Disconnect
EGAD.

Installation finished,
continue with setting to
work.

DMR163546, Rev: 01 CSIP Level 1 6 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
3 INSTALLING REAR COVER EXTENDER
Do this procedure for the M-cabinet.

The cabinet rear cover extender kit


contains:
· Two sides (left and right side)

· Top bracket
· Top ventilation cover
· Two ground cables and mounting
material

1. Remove the top ventilation cover.


2. Install one of the two sides.
3. The side must be hooked in the
existing rear cover at the top,
to get some room between the rear
cover and the top bracket, loosen the
left or right side lightly.

DMR163546, Rev: 01 CSIP Level 1 7 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4. Hook the side between the rear cover
and the top bracket.
5. Tighten the screws of the top bracket
by hand.

6. Tighten the top bracket again with the


tools.

7. Install the side at the lower part with a


bracket.
 Make sure that the correct
installation of the bracket and
make sure that the sides and rear
cover sides are aligned.
 Tighten the bracket.

DMR163546, Rev: 01 CSIP Level 1 8 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
8. To install the other side, use the same
procedure.

9. Install the top bracket between the


two sides.

10. Connect the two ground cables to the


protective ground stud of the existing
cabinet rear cover (CRC).

DMR163546, Rev: 01 CSIP Level 1 9 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
11. Prepare the top ventilation cover:

If necessary, make additional cable


inlet holes:
 Cut a cable inlet hole into the
ventilation cover.
 Remove sharp edges.
 Use the supplied materials with the
rear cover for the cable protection.

12. Tighten the top ventilation cover at the


inner side of the rear cover with the
screw.
Tighten the two screws (left and right
side).

DMR163546, Rev: 01 CSIP Level 1 10 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4 INSTALLING MCS AND MCC
4.1 Putting MCS into Examination Room
1. Move the monitor ceiling suspension
(MCS) into the examination room.
2. Put the MCS below the monitor ceiling
carriage (MCC).

3. Cut all straps and remove the


cardboard boxes and the support
block.

4.2 Installing the Actuator or Fixed Column


1. Remove the installation material from
the MCS package.
The package is on top of the MCS.

NOTE

The bag contains two


safety bolts, four bolts with
two washers each, and a
sealing cap for the X-ray-
on lamp.

2. Put the actuator or fixed column on top


of the MCS.
3. For the actuator, connect cable WMA-
SV1 to the MCS.
4. If you cannot access the WMA-SV1
connector, remove the cover of the
utility box.
5. If necessary, install the cover of the
utility box.

DMR163546, Rev: 01 CSIP Level 1 11 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
6. Put the actuator or fixed column in the
vertical position.

7. Assemble the four bolts and Nord-Lock


washers as shown.

WARNING
Use the new bolts. The bolts
that are removed from the
old MCS are not reliable to
use again.

8. Install the four bolts with the Nord-Lock


washers on the corner of the actuator
or fixed column.
9. Tighten the four bolts with a torque of
45 - 50 Nm.

10. Apply Loctite 243 to the two safety


bolts. Loctite is included in the
expendable kit in the documentation
box.
11. Install the two safety bolts in the
flange.
12. Tighten the safety bolts with a torque
of 15 - 20 Nm.

NOTE

The two safety bolts have


different lengths. It does
not matter which bolt is
installed on the left or on
the right side.

DMR163546, Rev: 01 CSIP Level 1 12 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4.3 Lifting Monitor Ceiling Suspension

NOTE

For a fixed column, do


NOT remove the cover
ring.

1. If not done already, remove the cover


ring from the MCC transversal
carriage.

2. Install the support block on top of the


MCC transversal carriage.

3. Cut the cable binders that prevent that


the lifting bars drop off.

4. Install the hoist on the supplied


bracket.

DMR163546, Rev: 01 CSIP Level 1 13 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
5. Install the hoist assembly to the
hoisting frame of the MCS.

DMR163546, Rev: 01 CSIP Level 1 14 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
6. Install the wire along the guiding
wheels.

DMR163546, Rev: 01 CSIP Level 1 15 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
7. Attach the end of the wire to the
hoisting frame.

8. Put tension on the hoist wire.


9. Loosen the hoisting frame (four bolts)
from the transport frame.
10. Lift the MCS a few centimeters.

11. Remove one beam on top of the


transport frame. Remove the beam on
the monitor side of MCS.

12. Remove the cable box to the monitor


side of the MCS.

NOTE

Make sure that you do not


damage the ornamental
hose when you remove the
cable box and when you
operate the hoist.

DMR163546, Rev: 01 CSIP Level 1 16 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
13. Lift the MCS a few centimeters.
14. If there are monitors on the MCS,
make sure that you move the monitors
carefully out of the transport frame.

15. Remove the pallet with transport frame


from of the examination room.

16. Lift the MCS into the MCC. To keep


the actuator vertical, give some
support on one side.

DMR163546, Rev: 01 CSIP Level 1 17 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4.4 Installing Actuator or Fixed Column to MCC
1. Install the nylon bearing plate.

NOTE

Make sure that the


actuator is centered in the
transversal carriage,
because the Teflon bearing
plate must fit fully around
it.

2. Put the guiding bush on top of the


Teflon bearing plate.

3. Install the support pin.

4. Install a spring locking pin on the two


sides of the support pin.

CAUTION

Make sure that the spring


locking pins are fully
inserted.

DMR163546, Rev: 01 CSIP Level 1 18 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
5. Loosen the wire.
6. Wind the wire.

7. Remove the hoist with the attached


part of the hoisting frame.

8. Remove the remaining part of the


hoisting frame in one piece.

9. Remove the support block.

10. Install the rotation lock washer.

DMR163546, Rev: 01 CSIP Level 1 19 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
Spring locking pins

Rotation lock washer


Securing screw

Guiding bush

Securing screw
Support pin
Bearing plate

Stop block Transversal carriage

Decoration plate

Actuator

Actuator assembly

DMR163546, Rev: 01 CSIP Level 1 20 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4.5 Installing 56-inch Large Screen Monitor
If there is a 56-inch monitor, do this procedure.

4.5.1 Installing 56-inch Monitor on Monitor Ceiling Suspension

1. If the release bracket is not against


the MCS rear plate, turn the bolts of
the bracket in a clockwise direction
as far as possible.
2. Move the monitor mounting arms on
top of the monitor frame backwards to
create sufficient space for the hoist
tools.

NOTE

The inside bracket moves


to the rear plate, which
creates room to install the
monitor.

3. Move the pallet with the monitor box


below the MCS.

NOTE

These installation tools are


stored in the monitor
package:
· hoist tool (2x)
· chain bag to store the
chain (2x)
· strap 100 cm
· strap 200 cm
· strap 400 cm (4x)

NOTE

If an old 56-inch monitor


was removed, the new
monitor is in the box and
the old monitor is on the
pallet.

DMR163546, Rev: 01 CSIP Level 1 21 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4. Put the strap of 200 cm through the
handles of the new monitor.

5. To limit the length to 50 cm, fold the


strap of 100 cm, and put the folded
strap on top of the MCC.

CAUTION

To prevent damage, use


protective material between
the strap and the monitor
ceiling carriage (MCC)

6. Install the two hoist tools between the


two straps.

7. To prevent damage to the monitor,


catch the loose ends of the hoist
chains in the chain bags.

DMR163546, Rev: 01 CSIP Level 1 22 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
8. Set the up/down lever to the correct
(up) position.

Up/down lever

9. Lift the monitor carefully until


approximately 10 mm below the utility
box.

10 mm
10 mm

DMR163546, Rev: 01 CSIP Level 1 23 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
NOTE

After you lifted the


monitors, the four lugs on
the interface plate are on
the correct height with
respect to the four studs
on the monitor frame.
Lugs Lugs

Studs Studs

10. Move the monitor frame towards the


monitor.
11. Make sure that the lugs on the
interface plate are aligned with the
studs on the monitor frame.

Alignment stud

Stud

Lug
tud

DMR163546, Rev: 01 CSIP Level 1 24 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
12. Put the strap (400 cm) around the
monitor and MCS.

CAUTION

To prevent damage, use


protective material between
the strap (400 cm), the
monitor (front), and the
MCS (rear)

13. To pull the monitor in the MCS,


tighten the strap (400 cm) until
approximately 15 mm along the
bottom of the utility box.

Strap 400 cm

15 mm

DMR163546, Rev: 01 CSIP Level 1 25 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
14. Let the monitor carefully down and
make sure that the distance between
monitor and utility box is
approximately 25 mm in height and
30 mm in depth direction.

WARNING
25 mm 25 mm
Before you remove the
hoist tools, make sure that
the monitor is locked in the
monitor frame. The monitor
can fall when not correctly
locked.

30 mm

15. To tighten the monitor, turn the bolts


of the release bracket in a
counterclockwise direction.
16. Make sure that the monitor is locked.

WARNING
When the monitor is not
correctly locked, a monitor
collision with other objects
can cause the monitor to
fall.

DMR163546, Rev: 01 CSIP Level 1 26 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
17. Remove the two hoist tools from the
strap (200 cm) on the monitor side.

WARNING
Do not remove only one
hoist tool from the strap on
top of the MCC. The other
hoist tool falls and can
cause serious injuries,
damage to the monitor, or
monitor frame.

First remove here.

18. Remove the two hoist tools together


with the strap (100 cm) from top of the
MCC at the same time.

19. Release and remove the strap


(400 cm) from the monitor and MCS.
20. Remove the protective material.
21. Attach the identification label of the
56” large screen monitor (supplied
with the FRU package).

22. Put the plastic bag of the new monitor


around the old monitor.
23. Put the packaging middle/bottom
cover of the new monitor on top of the
old monitor.
24. Attach the internal monitor box with
two straps (delivered with monitor
installation tools) on the pallet.
25. Remove the pallet with the old monitor
from the examination room.

DMR163546, Rev: 01 CSIP Level 1 27 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4.5.2 Installing Cables and Covers for 56-inch Monitor

1. Connect the power cable.


Ground Power
2. Connect the ground cable.

3. Connect all DVI connectors (with DVI


receivers Dual Link).
DVI 3 DVI 1

WME1–
X(DVI1)

WME1–
X(DVI4)

WME1– WME1–
X(DVI3) X(DVI2)

4. Connect the Ethernet cable.


5. Move the RS232/Ethernet select
switch towards the Ethernet cable.

Move switch
to the right.

DMR163546, Rev: 01 CSIP Level 1 28 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
6. Connect the ground cable on the
center panel.
Ground

7. Put the power switch in the ON (I)


position. The switch is on the rear
bottom side of the monitor.

8. Connect the ground cable to the


aesthetic cover.

CAUTION

Make sure that the monitor


cables do not get jammed
between the aesthetic
cover and the monitor
frame.

9. Install the aesthetic cover to the


bottom side of the monitor with six
screws.

DMR163546, Rev: 01 CSIP Level 1 29 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
10. Install the rear covers on the MCS
(center cover shown).

4.6 Installing 19-inch or 21-inch monitors


If there are 19-inch or 21-inch monitors, do this procedure.

4.6.1 Insulation Plate for LCD 19- or 21-inch monitors


If a monitor, for example, a haemo monitor, gets its power supply from the hospital mains instead of
from the Allura system, then install the monitor with an insulation plate.

1. Remove the monitor isolation kit from Insulation


the package. The monitor isolation kit bushes (4x)
is stored in one of the cardboard
boxes.

NOTE

With the monitor isolation


kit, the monitor is
galvanically isolated from
the frame.

DMR163546, Rev: 01 CSIP Level 1 30 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
CAUTION

When you loosen the


monitor, hold the monitor.
The monitor can fall.

1. Pull the monitor out


2. Remove the Vesa plate from the
monitor.

3. Install the insulation plate with (4x)


insulation bushes, plain washers
(small) and bolts 25 mm on the
monitor.

4. Install the monitor in the monitor


frame.
5. Align the monitor with the other
monitors in depth, with bolts (B.)

DMR163546, Rev: 01 CSIP Level 1 31 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
6. Connect the DVI, power, and ground
cables.

NOTE

For DVI monitor


configurations, connect the
cables in this sequence:
1. Ground cable
2. Power cable
3. Signal cable (DVI
cable with receiver)

4.6.2 Installing 19- or 21-inch Monitors and Interface on MCS


If there are reused 19-inch or 21-inch monitors, install these monitors on the MCS.

The monitor interface is installed with the


4x bolts B. The old monitor interfaces are
reused.

1. Apply Loctite 243 to the top of the 4x


bolts B.
2. Install the 4x nuts A onto the bolts B,
distance is 5 mm ± 1 mm as shown.
3. Connect the ground cable to the
monitor interface.

DMR163546, Rev: 01 CSIP Level 1 32 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
Monitor interface with four nuts A.

4. Install the VESA plate on the monitor.


5. Tighten the 4 screws on the rear of
the monitor.
6. Put the monitor into the MCS.

7. Install 2x washers and bolts.


8. Tighten the 2 bolts on the monitor
interface.
9. Install the monitor rear cover.
10. Connect the DVI cable, power cable,
and ground cable to the monitor.
11. Remove the 2x bolts and spring
washers.

DMR163546, Rev: 01 CSIP Level 1 33 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4.6.3 Installing Top Monitors with Insulation Plate
If there is a top monitor with a power supply from the hospital mains instead of the Allura system power,
for example a haemo monitor, then install the monitor with an insulation plate.

1. Remove the monitor isolation kit from Insulation


the package. The monitor isolation kit bushes (4x)
is stored in one of the cardboard
boxes.

NOTE

The monitor isolation kit is


to galvanically isolate the
monitor from the monitor
frame.

2. Remove the two M6 bolts from the


Insulation
insulation plate.
bushes (4x)
3. Install the insulation plate with (4x)
insulation bushes, plain washers
(small) and bolts 25 mm on the
monitor.

4. Install the monitor.

DMR163546, Rev: 01 CSIP Level 1 34 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
5. Adjust the position of the monitor with
bolts 1, 2 and 3.
6. Tighten all bolts to make sure that the
monitor stays in position during
start/stop movements and collisions.
Tighten bolts 1 and 2 with a torque of
20 - 25 Nm.
7. Do this procedure again for monitor 8.
Use bolt 3 to adjust the monitor
height.

NOTE

Make sure the monitor


cannot hit the MCC during
height movement.

8. Connect the ground, power and DVI


cables.

DMR163546, Rev: 01 CSIP Level 1 35 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4.6.4 Installing Top Monitors
If there are one or two top monitors install the monitors on top of the MCS.

1. Install the mounting arm with four bolts


on top of the MCS.

NOTE

Put the arm to make sure


that the weight of both
monitors is balanced. Do
not use dummies or
different monitors.

2. Install monitor 7 (four bolts + washer +


spring washer).
3. Connect the ground, power and DVI
cables. Fixation bolts

NOTE

For DVI monitor


configurations, connect the
cables in this sequence:
a) Ground cable
b) Power cable
c) Signal cable (DVI
cable with
receiver)

Power

Ground
Signal

DMR163546, Rev: 01 CSIP Level 1 36 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4. Adjust the position of the monitor with
bolts 1, 2 and 3. Use bolt 3 to adjust
the monitor height.

NOTE

Make sure that the monitor


cannot hit the MCC during
height movement.

5. Tighten all bolts to make sure that the


monitor stays in position during the
start or stop of movements and
collisions.
Tighten bolts 1 and 2 with a torque of
20 - 25 Nm.
6. Do this procedure again for monitor 8.

End result
(with 56” monitor)

4.7 Installing Intercom Microphone-Speaker Unit on MCS


Install the reused intercom microphone-speaker unit.

DMR163546, Rev: 01 CSIP Level 1 37 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
1. Remove the cover of the utility box
from the top of the Monitor Ceiling
Suspension.
2. Install the Microphone-Speaker (MS)
unit cable through the cover of the
utility box.
3. Install the utility box cover.
4. Attach the two pieces of Velcro tape
on the cover of the utility box.

5. If there is no Velcro tape on the MS


unit, attach the other side of the
Velcro tape on the MS unit.

6. Install the intercom MS cable in the


MS unit:
a) Open the MS unit
b) Loosen the four screws on the
terminal block.
c) Install the intercom cable as
shown.
d) Close the MS unit.

DMR163546, Rev: 01 CSIP Level 1 38 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4.8 Installing MCS Cable Hose

NOTE

The MCS cables are routed. When applicable, install any additional cables in the MCS
cable hose now.

1. Unwind the cables with their full length


along the floor.
2. Divide the cables in bundles that apply
to the local situation, for example, to
divide the weight, divide between
signal cables and power cables.

3. On the position of the cut in the cable


hose, add soapstone powder in the
two hoses.

NOTE

Two cables leave the hose


on the position of the cut:
one ground cable and one
cable for the examination
light.

4. To divide the soap stone powder,


shake the hoses.

5. Put the two cable hose parts in the


fixed cable carrier.

NOTE

The two cables must leave


the cable carrier in the
center.

DMR163546, Rev: 01 CSIP Level 1 39 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
6. Install the upper part of the fixed cable
carrier.

7. Divide the length of the cable hose as


shown in the table and figure.
8. Attach the cable hose at the correct
positions to the cable carriers.

MCS type Distance A to B for Actuator Distance A to B for Fixed


(short/long) Column
2- and 3-fold MCS 1060 mm 1000 mm
4 - 6 and 8-fold MCS 800 mm 740 mm

NOTE

The distances between B and C and between C and D must be equal.

DMR163546, Rev: 01 CSIP Level 1 40 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
9. Attach the cable hose with a cable
binder to the bracket of the MCS.

10. Make sure that the cable loops are of


equal length.
11. If necessary, install the cable carriers
again.
12. Push the monitors to the end of the rail
and make sure that the cable moves
smoothly.
13. If necessary, turn the hose in the cable
carrier.

14. Attach the cables together with cable


binders.

NOTE

For USA only:


Bundle and do the routing
of the power and signal
cables separately.

15. Attach the cables temporarily to the


location where the ceiling inlet is
installed.

DMR163546, Rev: 01 CSIP Level 1 41 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
16. Install the cables to their destination.
Refer to the cable diagram.

NOTE

Use the pull wire that was


left when the system was
disassembled.

NOTE

The ceiling inlet is reused.

17. Install the cable hose ceiling inlet.

DMR163546, Rev: 01 CSIP Level 1 42 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4.9 Connecting the Examination Light
1. Attach the ground wire of the
examination light to the ground stud
on the MCC.

2. Install the two cables of the


examination light on top of the MCC.
3. Attach the cables with the clamps.

TF-X1
4. Connect the power cable from the
MCS to cable TF-X1/TF-X3.

Safety bracket

TB-X1

Tie wrap

TF-X3

TF-X3

DMR163546, Rev: 01 CSIP Level 1 43 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4.10 Installing Sealing Cap on X-ray-On Bracket
If there is an X-ray-on light on the MCC rails, do this procedure.

The bracket for the X-ray-on light is


installed on the MCC rails.

1. Remove the threaded orange cap.


2. Remove the light bulb.

3. Put the sealing cap in the opening.

DMR163546, Rev: 01 CSIP Level 1 44 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
5 INSTALLING SYSTEMS WITHOUT PHILIPS MCS
1. Install the reused or new monitors.
2. Install the cables to these monitors.

DMR163546, Rev: 01 CSIP Level 1 45 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
6 INSTALLING CONTROL ROOM CONNECTION BOX
6.1 Installing Control Room Connection Box on Wall or Frame
· Install the CRCB on the bracket that was kept after the disassembly of the old CRCB
· If the CRCB is installed on a support frame, it is kept after the disassembly of the old CRCB.

1. If there is a bracket at the rear side of


the control room connection box,
remove the bracket.

2. Remove the cover.

3. Remove the installation material.

NOTE

If there is no geometry
module connected to this
control room connection
box, the connector labeled
with “stop” is necessary.

DMR163546, Rev: 01 CSIP Level 1 46 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
4. If cable installation makes it
necessary, remove one corner or put
it on another position.

5. Attach the control room connection


box to the bracket.

6.2 Installing CRCB System Cables

NOTE

To optimize the workflow, first install the cable sets from the control room to the cabinets.

System cables to
Control room
To connect cables, refer to the cable cabinets and
equipment
drawings. examination room
Control room
connection box

CAUTION

Because of EMC, attach


the cables together for
each connection location.

1. Connect the ground cables as shown


in the picture.

DMR163546, Rev: 01 CSIP Level 1 47 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
2. Connect the power cables as shown
in the picture.

3. Connect the signal cables.


4. Install the signal cables as shown in
the picture.
5. Connect the Ethernet cables to the
Ethernet switch along the metal
housing of the CRCB and:
 cross the ground cables diagonal
(see picture).
 install as far away as possible from
the other cables until the point
where the bundles leave the
CRCB.

DMR163546, Rev: 01 CSIP Level 1 48 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
6. Attach all cables together, include
cables from KM extender (mouse,
keyboard, and UTP), except the
Ethernet cables connected to the
Ethernet switch.
7. Attach the Ethernet cables together
and separated from the other cable
bundles to at least 50 cm outside the
CRCB.

DMR163546, Rev: 01 CSIP Level 1 49 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
7 INSTALLING WALL CONNECTION BOX CABLE SETS
· Install the WCB cable sets to the R- or B-cabinet.
· For each video source, there is a wall connection box.

8 INSTALLING AD7 PATIENT SUPPORT (IF AD5 IS REPLACED)


To install the AD7 patient support:
· For the AD7, refer to DMR162948
· For the AD7 swivel, refer to DMR166936

9 UPGRADING EQUIPMENT RACK


To upgrade the equipment rack, refer to the system installation instruction VGA-to-DVI Upgrade of
Equipment Rack (DMR165213).

DMR163546, Rev: 01 CSIP Level 1 50 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
10 PREPARING CABINET REUSED AND RELABELED CABLES
10.1 M-Cabinet Cables
1. Make sure that the reused cables are present. Refer to the table that follows.

CAUTION

Put fiber optics in a safe place on the wall or in a protective sleeve.

2. Where shown in the table, apply new labels to the cables.


3. If not already done, remove the old cables.

Label M-cabinet New label Description Label other end


(Old) M-cabinet

MD(FDC)1 – X3 BC – X10 Flat detector RX frontal BB – X4 (TX)


MD(FDC)1 – X4 BC – X9 Flat detector TX frontal BB – X3 (RX)
MD(FDC)1 – X5 BC – X3 Flat detector ID frontal BB – X5
(orange)
MD(FDC)1 – X7 BC – X4 Flat detector FR frontal
MD(FDC)1 – X8 BC – X5 Flat detector XW frontal BB – X2 (X)
MD(FDC)1 – X17 BC – X15 Analog dose rate control frontal EZ – X300

MD(FDC)2 – X3 2BC – X10 Flat detector RX lateral 2BB – X4 (TX)


MD(FDC)2 – X4 2BC – X9 Flat detector TX lateral 2BB – X3 (RX)
MD(FDC)2 – X5 2BC – X3 Flat detector ID lateral 2BB – X5
(orange)
MD(FDC)2 – X7 2BC – X4 Flat detector FR lateral 2BB – X1 (FX)
MD(FDC)2 – X8 2BC – X5 Flat detector XW lateral 2BB – X2 (X)
MD(FDC)2 – X17 2BC – X15 Analog dose rate control lateral 2EZ – X300

MDY – X12 no change injector


MDY – X15 no change Auxiliary connection box ATY – X2
MDY – X21 no change Footswitch SD1-X19
MDY – X24 no change ECG control SD-X21
MDY – X33 no change Video switch
MDY – X35 no change DVD controller lateral CY – X41
MDY – X34 no change DVD controller frontal CY – X30
MDY – X55 no change CAN generator lateral 2EZ – X400
MDY – X61 no change CAN UI SD1-X22
MDY – X63 no change CAN collimator frontal LA2 – X11
MDY – X71 no change CAN generator frontal EZ – X400
MDY – X73 no change CAN collimator lateral 2LA2 – X1
MDY – X74 no change CAN SUZ1, pedestal
MDY – X82 no change SAN generator frontal EZ – X420
MDY – X83 no change SAN generator lateral. 2EZ – X420
MDY – X84 no change SAN geo SCC-X21
MDY – X401 no change Ethernet TS-X16

MG – X25 NC – X21 Power AD7


MG – X27 NC – X22 Pedestal TBCF SD1 – X2
MG – X29 no change 24V supply detector frontal BB – X6
MG – X31 no change 24V supply detector lateral 2BB-X6

DMR163546, Rev: 01 CSIP Level 1 51 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
Label M-cabinet New label Description Label other end
(Old) M-cabinet
MG – X32 no change Power collimator frontal LA – X2

TP – X12 no change Real Time Image link TG-X21

MG – X39 no change Power flat detector lateral 2BB – X6)


MG – X32 no change Power collimator lateral 2LA – X2

NP – X100 no change Keep the ground wire to the Auxiliary ATY – X100
connection box, remove other external
ground wires.
NP – X301 no change Power on or off generator frontal EZ – X550
NP – X302 no change Power on or off generator lateral 2EZ – X550

WARNING
Make sure that there is no voltage on NP – X106. NP – X106 connects to the room light
switch.

10.2 R-Cabinet Cables


1. Make sure that the reused cables are present. Refer to the table that follows.

CAUTION

Put fiber optics in a safe place on the wall or in a protective sleeve.

2. If not already done, remove the old cables.

Label R-cabinet New label Description Label other end


(Old) R-cabinet

WHG – X(out) no change Video to M-DVR frontal CY – X42

TG – X23 no change Optical DVI X(150-1) (XtraVision)

SCC – X11 no change 230 Vac frontal stand SPP – X21


SCC – X13 no change 230 Vac AD7 SAP1 – X1
SCC – X17 no change 230 Vac AD7 SAP2 – X1

TS – X3 no change Internal Internet SD1 – X17


SCC – X142 no change Stop SD1 – X11

SCC – X12 no change Larc control SLB6 – X11


SCC – X24 no change Larc control SLB6 – X12
SCC – X11 no change Larc control SLD1 – X1
SCC – X22 no change Larc control SLB6 – X1
SCC – X21 no change Larc control SLB6 – X11

DMR163546, Rev: 01 CSIP Level 1 52 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved
10.3 2R-Cabinet Cables
1. Make sure that the reused cables are present. Refer to the table that follows.
2. If not already done, remove the old cables.

Label 2R-cabinet New label Description Label other end


(Old) 2R-cabinet

2WHG – X(out) no change Video to M-DVR lateral CY – X43

11 CABINETS
1. The 2R cabinet is reused. For an FD20/10 system, install the new flat detector temperature control
unit (chiller). Refer to the system installation instruction Installation, System Installation Part 1
(DMR138821).
2. Unpack the cabinets. Refer to the system installation instruction Unpack, Transport, Mount
Cabinets (DMR101237).

NOTE

To return the old cabinets, use the new cabinet packing materials.

3. Install the M-cabinet. Refer to the system installation instruction Installation, M-cabinet-FD
(DMR107785).
4. Install the R-Cabinet. Refer to the system installation instruction System Installation Part 1
(DMR138821).
5. If there is a FlexVision or EP cockpit subsystem, Install the B-cabinet, Refer to the system
installation instruction Installation, B-cabinet (DMR133796).

DMR163546, Rev: 01 CSIP Level 1 53 of 53


ATTENTION: THIS PAGE CONTAINS COPYRIGHTED MATERIALS THAT ARE CONFIDENTIAL AND/OR PROPRIETARY.
ANY RELEASE OR DISTRIBUTION OF THIS MATERIAL, WITHOUT PERMISSION, IS A VIOLATION OF LAW.
Copyright © 2013 Koninklijke Philips N.V. All rights reserved

You might also like