Professional Documents
Culture Documents
23109-ETYS 2012 Document
23109-ETYS 2012 Document
Year Statement
UK electricity transmission
NOVEMBER 2012
Electricity Ten Year Statement
November 2012
ETYS is produced by National Grid with the proposed NDP is a National Grid policy
assistance of the two onshore Transmission and applies to the onshore electricity
Owners (TOs), Scottish Power Transmission transmission system in England & Wales.
(SPT) and Scottish Hydro Electric Transmission
(SHE Transmission). The objective of We hope that you will agree that we have
the publication is to provide clarity and met these targets, although we do recognise
transparency on the potential development that this is the first edition and that future
of the National Electricity Transmission publications will benefit from further input
Systems (NETS). The document considers from its readership.
this development through strategic network
modelling and design capability, while trying In order to make the 2013 edition of
to capture future uncertainty with regards to the ETYS even better and ensure that
the generation mix, operation of the network we continue to add value through the
and technology development. information that we provide, I encourage you
to tell us what you think by writing to us at
In delivering the ETYS we set ourselves transmission.etys@nationalgrid.com. Please
various key objectives based upon your views also refer to the way forward chapter of this
expressed in our April 2012 consultation: document for further information on our 2013
ETYS consultation process and how you can
To provide a document with a high level provide feedback.
of clarity.
To ensure that there is a high degree of I hope that you find this an informative
transparency around our assumptions and useful document and look forward to
and the analysis that we provide. receiving your feedback.
To publish an electricity document that
utilises enhanced modelling capability
to illustrate the development of the
transmission system, taking into account
the considerable future uncertainties and
the interaction between the onshore and
offshore network going forwards.
Page 3
Electricity Ten Year Statement
November 2012
Contents
Page 5
Executive summary
The UK has legislation in place setting limits on Generation, demand and the evolution of
the emissions of greenhouse gases as far ahead regulatory policies are captured by considering
as 2050. There is also legislation mandating a the future energy scenarios outlined above. These
minimum level of renewable energy in 2020. scenarios provide the basis for technical analysis
A single forecast of energy demand does not to identify transmission network development
give a sufficiently rich picture of possible future needs. A credible range of potential developments
developments so National Grid now carries and opportunities are identified and assessed to
out analysis based on different scenarios that ensure an economic and efficient transmission
between them cover a wide range of possible system is maintained.
energy futures.
As a means to assess and report transmission
A significant part of these energy scenarios is system capability it is useful to consider the
the future power generation and demand mix. transmission system split by boundaries.
The scenarios used to underpin our network Boundaries separate the system across multiple
development present significant challenges in parallel transmission routes. The boundary
terms of transmission planning, in light of the capability is an expression of the maximum
uncertainties surrounding the energy landscape power transfer that can be securely transferred
as the UK makes the transition to a low carbon across the transmission routes. A review of the
economy in 2020 and onwards. boundary capabilities is provided in this document
and for each boundary the transmission network
The development of the NETS is influenced by a reinforcements required to securely enable the
number of key factors including: maximum expected power transfer is provided.
More than 25 local and wider boundaries have
the generation and demand outlook been analysed in this way.
generation type
regulatory policy changes (e.g. offshore Some of the northern boundaries could grow
integration review) by up to five times their current capability under
offshore design approaches certain scenarios. The southern boundaries see
technology development less pronounced changes in power transfer
management of future uncertainty and requirements but there is still enough generation
investment risk. development to potentially warrant significant
Page 6
Electricity Ten Year Statement
November 2012
future transmission reinforcement. Additionally The key output of the NDP is the identification of
very large new generation connections are the best course of action to take in the current
anticipated in many parts of the network, such year, selected through minimising investment
as the potential new nuclear connections or regrets against a range of credible scenarios
multiple large offshore wind connections around and sensitivities. Given the uncertainty that
the Humber area. To capture the impact of these we face, the decision process with which the
types of connections, these localised transmission preferred combination of transmission solutions
areas have been enclosed with local boundaries will be chosen needs to be well-structured
to investigate the power transfer requirements and transparent. This will allow stakeholders to
and identify suitable network reinforcements. understand why decisions to build, and not to
Such reinforcements are particularly sensitive to build, have been taken.
transmission investment risk.
Having identified how the transmission system
Offshore transmission development and the may be developed, we also need to consider
development of technologies such as High how the operation of the network may change.
Voltage Direct Current (HVDC) transmission This requires identifying the key changes to
technologies will play a very big part in both the system, the impact of such changes, and
the future requirements and delivery of future a careful assessment of mitigating measures
transmission capability. An integrated approach required to ensure continued safe and secure,
to the development of the offshore networks helps reliable, and efficient design and operation of
provide capacity, control and flexibility that are the transmission system.
needed for the effective development of the future
transmission network across many of the critical One key change to the network is the transition
system boundaries. from a relatively predictable/controllable
generation portfolio dominated by fossil fuel
In addition to the uncertainty facing the synchronous generation, to one including a
transmission network with regard to the quantity, significant level of non-synchronous plant with
type and location of new generation and the intermittent output. There are also important
extent and location of new interconnection, changes to consider related to electricity demand,
the lead-time for reinforcement of the wider where loads may become more flexible and price
transmission network can also be greater than the sensitive. This could be combined with increasing
lead-time for the development of new generation levels of embedded generation, and in the longer
projects. In order to manage this difference in term increased levels of electricity storage, which
lead-times, we are developing and formalising combined could see less predictable levels of
a Network Development Policy (NDP), some of transmission system demand. The degree of
which is detailed in Chapter 3. change will depend on the future energy outlook
and the key system design and operational
The NDP aims to identify the requirements for challenges associated with those scenarios are
further transmission investment and considers the as follows:
balance between the risks of investing too early in
wider transmission reinforcements, which include The falling level of synchronous generation in
the risk of inefficient financing costs and an service, particularly at low demand periods,
increased stranding risk, with the risks of investing will reduce system inertia making frequency
too late, which include inefficient congestion costs. management more of a challenge.
Page 7
w
Executive summary
Electricity Ten Year Statement
November 2012
Falling fault levels on the system could We are confident that mitigating measures can be
jeopardize the functionality of certain protection developed to tackle these issues. We envisage
devices, the commutation of High Voltage that this will include innovative approaches and
Direct Current (HVDC), and impact on a range will create new opportunities for customers through
of quality of supply issues. There are already commercial solutions to these problems, such as
difficulties in managing the voltage profile flexible demand and fast frequency response.
at low demand periods in certain areas of
the network and this may be increased by a In summary there are significant challenges
reduction in system strength. ahead with respect to both the development and
operation of the transmission network, with both
Rapid changes in renewable output, including these areas providing commercial opportunities
wind generation ‘cutting out’ at high wind for customers.
speeds, will have to be matched by changes
in conventional generation. As this plant Finally, one important aspect to consider
is connected at different locations on the when reading this document is that the future
network, there will be significant power energy outlook is uncertain, hence the range of
flow volatility. scenarios presented in this document. The actual
development of the NETS can and may differ
from the illustrations included in this document
and the outcomes included in this document
should therefore not be used as the basis for
any financial, planning consent, commercial or
engineering decisions.
Page 9
Chapter one
Introduction
Electricity Ten Year Statement
November 2012
Page 11
1.1
Background
In April 2012 we conducted an industry Our view is that the harmonisation of a number
consultation process for the development of an of our previous publications, including the SYS
ETYS publication which resulted in overwhelming and ODIS, enables customers to access relevant
stakeholder support for the overall approach and timely information in a single document
outlined below. We have detailed this consultation that captures both the onshore, offshore and
programme, the feedback received from our interconnected network.
customers and the output from the process in
our ‘ETYS Way Forward’ publication which can The first ETYS publication also represents the
be found on our website. start of a new stakeholder consultation process.
Following the publication of the first edition of the
The 2012 ETYS is the first GB electricity ten document we will gather views from the industry
year statement to be published and has been to enable us to continually evolve the document
produced as a direct result of feedback from our and incorporate the views of our stakeholders.
customers. The document forms part of a new Our planned approach to future stakeholder
suite of publications which is underpinned by engagement is outlined in Chapter 5.
our Future Energy Scenarios. This enables the
analysis in both the ETYS and its sister publication
– the Gas Ten Year Statement (GTYS) – to have
a consistent base when assessing the potential
future development of both the gas and electricity
transmission networks.
Page 12
Electricity Ten Year Statement
November 2012
1.2
Methodology
The document itself will focus on the potential The main focus of the network modelling and
development of the NETS using network analysis contained within the ETYS uses the
modelling and analysis around a range of energy Gone Green scenario; however analysis has also
scenarios: Slow Progression, Gone Green and been undertaken using the Slow Progression
Accelerated Growth, while ensuring that the and Accelerated Growth scenarios, in order to
network is developed in such a way to meet provide a range of potential future developments
customer connection dates. These energy and provide greater clarity on potential future
scenarios are detailed in our Future Energy connection opportunities.
Scenarios publication, which can also be found
on our website. An overview of these scenarios To help align the ETYS with other National
can also be found in Chapter 2. Grid publications and to assist in providing a
longer-term view, the analysis contained within
Future Energy Scenarios the document covers a detailed ten-year study
In addition to these three scenarios, further period, with ‘lighter touch’ less detailed analysis
analysis has been produced focusing on the considering the period from 2022 to 2032.
contracted background, which includes any
existing or future project that has a signed
connection agreement with us.
Page 13
1.3
Navigation through the document
Following this introductory chapter the ETYS This chapter also discusses the potential
consists of a further five sections which are: development of an integrated offshore
network and the impact of increased levels
Scenarios – this chapter describes the key of interconnection and outlines our Network
elements in each of the three main scenarios Development Policy (NDP). This defines how
as well as an overview of the contracted we will assess the need to progress wider
background. It also includes analysis on ‘plant transmission system reinforcements to meet the
margins’ under the three energy scenarios to requirements of our customers in an economic
further assist customers in identifying future and efficient manner.
market opportunities.
System Operation – Following the identification
Network Capability and Future Requirements of how the network may look in the future,
– This section builds on the previous chapter this chapter focuses on the challenges and
and illustrates the potential development of the opportunities associated with the operation of
network under the scenarios previously detailed. the transmission system in the future. The focus
Future network requirements and reinforcements is on how network operation will need to change
required under these scenarios are identified given the changing generation mix and increase of
here, along with an identification of different renewable generation.
transmission design strategies. This is the section
where the illustration of the NETS, including This section also highlights where there may be
detailed system maps of opportunities for customers to provide services in
both the onshore and offshore areas, can be found. support of system operation such as balancing or
ancillary services.
In order to assess the potential impact of future
requirements on the transmission system it is Way Forward – We are committed to ensuring
useful to consider the NETS in terms of specific that the ETYS continues to evolve over time
regions separated by boundaries across which and that each year our customers have the
bulk power is transmitted. This section is therefore opportunity to shape the development of this
structured in a way that discusses each of these document. This chapter details the process
boundaries, and therefore regions, in turn. which will run alongside production of the 2013
ETYS to ensure that the publication continues
For each boundary there is a description of the to evolve and that our stakeholders can shape
boundary, detail of the generation background, an the document.
identification of the potential reinforcements under
the different scenarios analysed and a discussion Appendices – In addition to the main ETYS
of the potential future boundary capability and document itself there are also several data
therefore opportunities. This analysis forms the appendices to this publication which can be
bulk of the document. found on our website. The appendices contain
all the relevant technical and numerical data in
support of the analysis shown in the ETYS.
Page 14
Electricity Ten Year Statement
November 2012
Page 15
Chapter two
Scenarios
Electricity Ten Year Statement
November 2012
2.1
Future Energy Scenarios
Page 17
2.2
ETYS background and scenarios
Growth and the renewable energy target for 2020 gases. Renewables are governed by the 2009
is not met until some time between 2020 and Renewable Energy Directive which sets a
2025. The carbon reduction target for 2020 is target for the UK to achieve 15% of its total
achieved but not the indicative target for 2030. energy consumption from renewable sources
by 2020.
Gone Green – this is the main analysis case for The Climate Change Act of 2008 introduced
the ETYS and assumes a balanced approach with a legally binding target to reduce greenhouse
contributions from different generation sectors in gas emissions by at least 80% below the 1990
order to meet the environmental targets. Gone baseline by 2050, with an interim target to
Green sees the renewable target for 2020 and reduce emissions by at least 34% in 2020. The
the emissions targets for 2020, 2030 and 2050 Act also introduced ‘carbon budgets’, which
all met. set the trajectory to ensure the targets in the
Act are met.
Accelerated Growth – this scenario has more These budgets represent legally binding limits
low carbon generation, including renewables, on the total amount of greenhouse gases that
nuclear and Carbon Capture and Storage can be emitted in the UK for a given five-year
(CCS), coupled with greater energy efficiency period. The fourth carbon budget covers the
measures and electrification of heat and transport. period up to 2027 and should ensure that
Renewable and carbon reduction targets are all emissions will be reduced by around 60%
met ahead of schedule. by 2030.
Page 18
Electricity Ten Year Statement
November 2012
2.3
Demand
This section describes the electricity demand The electricity transmission peak day demand
assumptions for each of the scenarios. forecast is derived from detailed analysis on
annual electricity consumption. The historic
relationship between annual electricity
consumption and transmission system peak
2.3.1 demand is used to form the basis for future
Demand Definition relationships between the annual and peak
demands, taking into account how future changes
For the purposes of the ETYS demand is included may affect this relationship. Our annual electricity
at its assumed peak day level. The assessment demand projections are derived from a number of
of electricity network adequacy tends to focus key drivers, including:
on the transmission system peak day demand as historic annual electricity consumption
this is often the most onerous demand condition economic background, including fuel price
the network needs to be able to accommodate energy efficiency measures.
and will therefore drive many of the required
reinforcements. Detailed description of projections for economic
assumptions, energy efficiency measures, electric
Peak demand is defined within the ETYS as vehicles, heat pumps and the impact of time-of-
transmission peak demand including losses use tariffs can be found in National Grid’s 2012
and excluding station demand and exports. Also UK Future Energy Scenarios document.
no pumping demand at pumped storage stations
is assumed to occur at peak times and Peak demand projections for all three scenarios
is therefore excluded. and user-based forecasts are shown in Figure 2.1.
Page 19
2.3 continued
Demand
Figure 2.3.1:
Peak outturn and forecast
70
65
60
GW
55
50
45
40
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Transmission peak demand was 56.1 GW in When accounting for small embedded generation,
2011/12, compared to 58.1 GW in 2010/11. we make an assumption regarding the level of
The main reason for this difference is the effect output to include at the time of peak demand.
of the ‘double-dip’ in the economy with other This methodology is similar to that outlined in
factors such as increases in energy efficiency and Section 2.5 which covers plant margins and
a rise in embedded generation. The lower levels the treatment of generation at the time of peak
of economic growth have seen a reduction in demand. Small embedded wind generation
electricity demand, particularly in the industrial is included at 5% of maximum capacity to
and commercial sectors. Energy efficiency account for the intermittent nature of wind
measures, such as more efficient light-bulbs and generation. This allows an assessment of the
appliances have also helped to reduce underlying most onerous condition in respect of transmission
demand, with the growth in distribution network demand, with sensitivity analysis undertaken to
connected (embedded) generation, noticeably assess the impact of higher levels of embedded
renewable generation, reducing demand on the wind generation (which effectively reduces
transmission network. transmission demand).
Page 20
Electricity Ten Year Statement
November 2012
Page 21
2.4
Generating capacity
scenarios and outlines the key changes over the Slow Progression 2012 station classed as?
www.nationalgrid.
com/uk/Electricity/
period to 2032 in each of the cases. GettingConnected/FAQs/
This scenario has a lower emphasis on renewable Question+12.htm
generation over the period. The key messages for
this scenario are shown below:
2.4.1
Generating Capacity Gas capacity increases over the period to 2020
by 7 GW and to a total of 49 GW by 2032
Definition showing a total increase over the period of
16 GW.
The values shown within this section are only Growth in wind capacity is considerably slower
for capacity that is classed as ‘transmission in this scenario in comparison to Gone Green
capacity’. This is generally generation capacity and Accelerated Growth and reaches 13 GW
that is classified as ‘large’1 and therefore does by 2020 and 28 GW by 2032 (19 GW being
not include any small embedded generation. offshore wind), showing a total increase over
Embedded generation not included in these the period of approximately 22 GW (the vast
values is accounted for in the assessment of majority of this being offshore wind).
transmission demand as discussed in the Other renewables excluding wind remain fairly
Section 2.3. static over the full period to 2032 showing only
approximately a 300 MW increase.
Coal capacity shows a slower decline than
in the Gone Green scenario showing a
7 GW decrease by 2020 leaving 18 GW
of coal capacity. Between 2020 and 2032
coal declines further, to 4 GW by the end of
the period.
Nuclear capacity remains fairly static over the
period rising from 10 GW in 2012 to 13 GW by
2030 before falling back to 11 GW by 2032.
Page 22
Electricity Ten Year Statement
November 2012
Figure 2.4.1:
Slow progression generation mix
120 60%
G W (Ins ta lled C a pa c ity )
100 50%
80 40%
60 30%
40 20%
20 10%
0 0%
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Nuclear Coal Gas/CHP Offshore Wind Onshore Wind
Other Renewables Interconnector Other (Oil/Pumped) Demand % Renewables
The existing level of renewables at 2012 in this Gas/CHP generation capacity increases overall
scenario is 8.5% of total generating capacity over the full period showing a 3.3 GW increase
which will rise to 17% in 2020 and finally between 2012 and 2020 and a further 3 GW
increasing to 30% in 2032. by 2032, resulting in an overall increase of
6.3 GW.
Coal capacity decreases dramatically over
the period to 2032, with the existing 25 GW
2.4.3 decreasing to 18 GW by 2020 and to 12 GW
Gone Green 2012 by 2032. This is due to the LCPD and Industrial
Emissions Directive (IED) legislation.
As described in section 2.2 the Gone Green Carbon Capture and Storage (CCS)
scenario assumes a generation mix that will assumptions within this scenario show
meet the CO2 and renewable targets. The key the introduction of this technology into the
messages from this generation background and generation capacity mix from 2025 onwards
how it develops over time are: with a total of 1.2 GW of CCGT plant fitted with
CCS by the end of the period in 2032.
Wind reaches 25 GW of capacity by 2020 Nuclear capacity increases by a total of
(17 GW of this being offshore) and 49 GW by approximately 5 GW over the period taking the
2032 (37 GW of this being offshore). total nuclear generating capacity to 14.7 GW
Other renewables excluding wind and including in 2032.
hydro, biomass and marine show an increase
on current levels of 1.3 GW to 2020 and
2.9 GW over the full period to 2032.
Page 23
2.4 continued
Generating capacity
Figure 2.4.2:
Gone green installed capacity mix
140 70%
120 60%
GW (installed capacity)
100 50%
80 40%
60 30%
40 20%
20 10%
0 0%
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Nuclear Coal Gas/CHP Offshore Wind Onshore Wind
Other Renewables Interconnector Other (Oil/Pumped) Demand % Renewables
Figure 2.4.2 illustrates the capacity mix for the Gas-fired capacity shows a total increase over
Gone Green background over the study period. the period to 2032 of approximately 5 GW.
Coal capacity shows a net decrease over the
The existing level of renewables at 2012 in this period to 2032 of approximately 12 GW, the
scenario is 8.5% which will rise to 28.5% in 2020 total coal capacity in 2020 is 20 GW with the
and finally increasing to 41.5% in 2032. total decreasing to 12 GW in 2030 but rising
slightly again by 2032 as new CCS capacity
comes on line.
Nuclear generation decreases over the period
2.4.4 to 2020 by 1 GW, however increases over the
Accelerated Growth 2012 full period to 2032 by a total of 8 GW, with the
introduction of new nuclear plant.
The Accelerated Growth scenario shows a Other renewables which include marine, hydro
much steeper increase in the level of renewables and biomass also increase steeply over the
generation capacity than Gone Green and Slow period to 2032 showing a total generating
Progression. The key messages for this scenario capacity increase of approximately 6 GW,
are shown below: taking the total installed capacity to 7.7 GW.
Page 24
Electricity Ten Year Statement
November 2012
Figure 2.4.3:
Accelerated growth installed capacity mix
160 80%
140 70%
GW (installed capacity)
120 60%
100 50%
80 40%
60 30%
40 20%
20 10%
0 0%
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Nuclear Coal Gas/CHP Offshore Wind Onshore Wind
Other Renewables Interconnector Other (Oil/Pumped) Demand % Renewables
Figure 2.4.3 illustrates the capacity mix for Some of the key messages for the contracted
Accelerated Growth. background are:
With Accelerated Growth being the scenario A large increase in contracted wind overall
with the most rapid build up of renewables the but especially offshore wind with a starting
percentage level of installed renewable capacity in level of 3.6 GW in 2012 rising to a total of
2020 is 34% which increases to 46% in 2032. 40 GW of generation that currently has a
signed connection agreement.
A decrease in coal generation amounting to
5.5 GW over the full period, this reflects the
2.4.5 known LCPD closures.
Contracted Background A rise in nuclear generation capacity which
currently has a signed connection agreement
The contracted background used for ETYS results in a total increase over the period to
was taken from the Transmission Networks 2032 of 20 GW.
Quarterly Connections Update (TNQCU), issued
in September 2012. It should be noted that
when analysing the contracted background
the generation mix includes all projects that
have a signed connection agreement and no
assumptions are made about the likelihood of
a project reaching completion.
Page 25
2.4 continued
Generating capacity
Figure 2.4.4:
Contracted background capacity mix
180
160
140
GW (installed capacity)
120
100
80
60
40
20
0
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Page 26
Electricity Ten Year Statement
November 2012
Figure 2.4.5:
System development and use of generation backgrounds
Page 27
2.5
Plant margins
This section brings together the information In addition Figure 2.5.1 includes the level of
described earlier in this chapter on demand ‘existing’ generation assumed in each of the
projections and future generation capacity mix three energy scenarios. These figures include
and assesses the status of future generation assumptions on plant closures within each of the
projects and the ‘plant margin’ assumed in the scenarios and highlights when new generation will
different energy scenarios. The plant margin is be required in these scenarios. This is explored
defined as the amount of generation capacity further in the assessment of plant margins later
available over and above the level of peak demand. in this section, but the impact of environmental
legislation and ageing plant can be seen as
existing generation falls due to these plant closures.
2.5.1 A significant proportion of the contracted
Project Status generation is in the scoping phase, with the
majority of this being low-carbon generation such
Figure 2.5.1 shows the current status of the as offshore wind and new nuclear plant. Around
projects included in the contracted generation 15 GW of plant has the relevant consents with just
background. These categories are broadly defined over 9 GW of this being CCGT plant.
as follows:
Page 28
Electricity Ten Year Statement
November 2012
Figure 2.5.1:
Contracted background Vs existing scenarios
180
160
140
120
100
GW
80
60
40
20
0
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Existing Under Construction Consents Approved Awaiting Consents Without Consents
SP Existing GG Existing AG Existing GG Demand
Page 29
2.5 continued
Plant margins
Figure 2.5.2:
20% scenario plant margins
40%
35%
Plant Margin
30%
25%
20%
15%
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Slow Progression Gone Green Accelerated Growth
Page 30
Electricity Ten Year Statement
November 2012
Figure 2.5.3:
Scenario de-rated plant margins
20%
16%
Plant Margin
12%
8%
4%
0%
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Slow Progression Gone Green Accelerated Growth
A key aspect of this calculation is that wind is mainly by coal plants closing due to the Large
de-rated down to 8%, a slightly more optimistic Combustion Plant Directive (LCPD). The lowest
view than the 5% used in the traditional approach. plant margin in all scenarios is in 2015 when
Wind is de-rated to a low level as experience all of the plant affected by the LCPD is due to
has shown that at times of high system demand, close. The figures reported here for the Gone
levels of output from wind can be lower than Green scenario are slightly higher than in Ofgem’s
10% of the maximum potential output. However, Capacity Assessment due to a slight difference in
given the unpredictable nature of wind generation methodology relating to the treatment / inclusion
output, Figure 2.5.4 shows the plant margin of reserve for the single biggest infeed loss.
calculation if wind generation capacity is
de-rated to various levels of output. In the short term the difference between
the scenarios is driven by differing demand
Figures 2.5.2 and 2.5.3 show the different de- assumptions as the generation assumptions for
rated plant margins calculations for each of the each scenario are broadly similar for the first three
scenarios and show that these all decrease from to four years of the outlook.
their current levels. This is principally due to the
relatively high plant margins that are evident in
the market today, driven mainly by a reduction
in electricity demand due to the economic
climate. In addition 10 GW of CCGT plant has
either connected since 2009 or is currently
under construction. The fall in plant margins in
all scenarios over the next few years is driven
Page 31
2.5 continued
Plant margins
Figure 2.5.4:
Gone green wind sensitivities
80%
70%
60%
50%
Plant Margin
40%
30%
20%
10%
0%
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Figure 2.5.4 shows how these de-rated margins will have a significant effect on how we operate
would be affected by different assumptions for the the transmission system, with the amount of
level of wind generation availability in the Gone capacity assumed in each scenario based on an
Green scenario. This highlights the importance assumption that, for security of supply purposes,
this assumption has, with the range growing wind availability is low. These operational
significantly as the amount of wind capacity challenges are explored in detail in Chapter 4 of
in this scenario increases. This also highlights this document.
that the variance in wind generation availability
Page 32
Electricity Ten Year Statement
November 2012
2.6
Renewables
One of the key elements for all of the scenarios is Suppliers meet their obligations by presenting
the level of renewable generation assumed, as this sufficient ROCs. Where they do not have sufficient
has a major impact on both network development ROCs to meet their obligations, they must pay
and network operation. The focus on renewables an equivalent amount into a fund, the proceeds
in this section is a direct consequence of the ETYS of which are paid back on a pro-rata basis to
document replacing the Offshore Development those suppliers that have presented ROCs.
Information Statement (ODIS) in addition to the The RO had an original operational end date of
Seven Year Statement. The aim is to ensure 2027, which has subsequently been extended
that information provided in the ODIS continues to 2037 with an associated limit of 20 years
to be available, recognising that other types of support for accredited generation.
generation are just as important when focusing on
the development of the transmission network. A banding review for the period 2013 to 2017,
which details the number of ROCs available
This section discusses in more detail four of for each MWh generated by different types of
the renewable generation types that could have renewable generation, was undertaken by the
a direct impact on the transmission system government earlier this year2. More detail can
– offshore wind, onshore wind, marine and be found in the government report, with the key
biomass. Other renewable generation types that elements related to transmission connected
connect principally to the distribution networks are generation being:
discussed later in this chapter.
The ROC level for offshore wind will be 2
Renewables Obligation1 ROCs per MWh over the first two years of the
1 www.decc.gov.uk/en/
The Renewables Obligation (RO) is currently the banding review period, falling to 1.9 in 2015/6
content/cms/meeting_ main support scheme for renewable electricity and 1.8 in 2016/7.
energy/renewable_ener/
renew_obs/renew_obs.aspx projects in the United Kingdom. The key elements The level of support for onshore wind for the
2 www.decc.gov.uk/assets/
of the obligation are: banding review period will be reduced to 0.9
decc/11/consultation/ro-
banding/5936-renewables- The RO was introduced in 2002 and is ROCs per MWh, guaranteed until at least
obligation-consultation-the- set to continue until 2017 when the new March 2014, with a review into onshore wind
government.pdf
arrangements that will form part of the industry costs being undertaken before ROC
Electricity Market Reform (EMR) outputs will levels for 2014 to 2017 are finalised.
replace the RO. The support levels for dedicated biomass
It places an obligation on UK suppliers of plant will be 1.5 ROCs per MWh, decreasing
electricity to source an increasing proportion of to 1.4 ROCs per MWh in 2016/17. Biomass
their electricity as renewable generation. conversions will receive 1 ROC per MWh over
Accredited renewable generators are issued the banding review period.
with Renewable Obligation Certificates (ROCs) Tidal generation to receive 2 ROCs per MWh
for each megawatt hour (MWh) of eligible in 2013/14 and 2014/15; 1.9 in 2015/16 and
energy generated, multiplied by a factor 1.8 in 2016/17. Wave generation to receive 5
that is dependent on the type of generation ROCs per MWh up to a 30 MW capacity limit
technology. Renewable generators can sell and 2 ROCs per MWh above the cap.
their ROCs to electricity suppliers.
Page 33
2.6 continued
Renewables
Figure 2.6.1:
Renewables contracted background by stage
80
70
60
50
GW
40
30
20
10
0
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
The analysis shown in Figure 2.11 includes increase of 8 GW on current existing levels. There
offshore wind, onshore wind, biomass, hydro and is around 7 GW of further renewable generation
marine generation comparing the split contracted currently with consents.
background against the scenario backgrounds.
Accelerated Growth shows a steep increase in
Figure 2.6.1 shows there is an existing level of renewable generation capacity by 2020 resulting
around 7 GW of renewable generating capacity, in an increase on current existing levels of 30 GW.
with the Gone Green scenario renewable capacity In the longer term there is an assumed growth in
level in 2020 at approximately 30 GW. Therefore renewable generation that exceeds the current
if the Gone Green scenario is to be met then a level of contracted renewable generation.
further 25 GW of renewable generation (out of
a total 45 GW of renewable contracted future In summary, renewable generation plays a large
generation with completion dates before 2020), part in all of the scenarios over the period to
will need to connect to the transmission system 2032 and there is currently enough contracted
by 2020. generation capacity to meet the levels required
under the Slow Progression and Gone Green
Slow Progression shows a level of 15 GW of scenarios. The majority of these generation
renewable generation capacity connected to projects, however, are currently in the scoping or
the transmission system by 2020, showing an without consents phase of development.
Page 34
Electricity Ten Year Statement
November 2012
Page 35
2.6 continued
Renewables
Figure 2.6.2:
Offshore wind contracted Vs scenarios
60
50
40
GW
30
20
10
0
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Offshore Wind Existing Offshore Wind Under Construction Offshore Wind Consented
Offshore Wind Scoping SP GG AG
In the Gone Green scenario there is 17 GW Slow Progression shows that the level of
of offshore wind in 2020. The current level of offshore wind in this scenario at 2020 is 6 GW.
offshore generation capacity that is either existing As mentioned above, 4 GW of this generation
or will be under construction by 2020 is 4.0 GW, capacity is either already connected to the
therefore leaving a total of 12 GW (of the 34 GW transmission system or will be by 2020 and
that is contracted with a signed connection there is enough generation with consents to
agreement and completion date before 2020) to provide the additional 2 GW in this scenario.
be connected to the transmission system by this
point. By the end of the period the Gone Green Accelerated Growth shows the level of offshore
scenario shows an offshore wind generating generation capacity at 2020 is 24 GW which is
capacity of 37 GW. 7 GW higher than the level shown in the Gone
Green scenario, meaning that a further 20 GW on
There is a large amount of capacity that is in the top of current levels will need to connect to the
scoping phase of project development which, transmission system by 2020 if this scenario were
based on historical observations, indicates that to be met.
there is the possibly that some of these generation
projects will not progress to completion. It is The following maps were published by The Crown
worth noting that the amount of generation Estate of the offshore system, showing firstly in
in the contracted background is not yet fully Figure 2.6.3 the projects that are operational and
commensurate with the total potential indicated under construction and secondly in Figure 2.6.4
through the Crown Estates leasing rounds. the offshore projects that are under development.
Page 36
Electricity Ten Year Statement
November 2012
Figure 2.6.3:
Offshore projects in operation or under construction
Source:
The Crown Estate
Page 37
2.6 continued
Renewables
Figure 2.6.4:
Offshore projects under development
Source:
The Crown Estate
Page 38
Electricity Ten Year Statement
November 2012
Figure 2.6.5:
Onshore wind contracted Vs scenarios
16
14
12
10
GW
8
6
4
2
0
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Offshore Wind Existing Offshore Wind Under Construction Offshore Wind Consented
Offshore Wind Awaiting Consent Offshore Wind Scoping SP GG AG
Page 39
2.6 continued
Renewables
Figure 2.6.6:
Marine contracted Vs scenarios
4
2
GW
0
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Marine Existing Marine Under Construction Marine Consented
Marine Awaiting Consent Marine Scoping SP GG AG
Figure 2.6.6 shows the current contracted position In Slow Progression, marine is assumed to
for marine (wave and tidal generation) against the develop very slowly due to high costs, with
requirement for marine generation under each of minimal deployment by 2030.
the three scenarios over the period to 2032.
In Accelerated Growth, there is a stronger build
In the Gone Green scenario the level of marine up of marine capacity, mainly post 2030.
generation capacity required in 2020, if the
scenario is to be met, is 20 MW. The current Apart from the 7 MW of existing or under
level of marine generation capacity that is construction capacity all marine generation is
either existing or under construction is 7 MW, currently in the scoping phase.
therefore leaving a total of 13 MW (of the 2 GW
that is contracted with a signed connection
agreement and completion date before 2020) to
be connected to the transmission system by this
Page 40
Electricity Ten Year Statement
November 2012
Figure 2.6.7:
Biomass contracted Vs scenarios
4
2
GW
0
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Biomass Existing Biomass Under Construction Biomass Consented
Biomass Awaiting Consent Biomass Scoping SP GG AG
Therefore, the graph shows under the contracted In Accelerated Growth there is strong growth in
background there is currently only just enough biomass with a total capacity of around 3.5 GW
generation with a signed connection agreement reached of which 1.5 GW is conversions.
to meet the level of biomass generation for the
Gone Green scenario and not enough to meet
Accelerated Growth.
Page 41
2.7
Interconnectors
Page 42
Electricity Ten Year Statement
November 2012
2.8
Non-GB generation
Page 43
2.9
Embedded generation
Figure 2.9.1:
Slow progression embedded generation
10
6
GW
0
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
This section describes the embedded generation total. In Scottish Power’s transmission area
capacity mix for each of the scenarios as the (South Scotland) this threshold falls to 30 MW
analysis so far in this chapter has focused only and in Scottish Hydro Electric’s transmission
on transmission connected generation capacity. area (North Scotland) it is 10 MW.
A definition of what we class as ‘embedded
generation’ can be found in section 2.4.1. In
the assessment of transmission demand, this 2.9.1
embedded generation is treated as ‘negative
demand’ as outlined in section 2.3.
Slow Progression
Figure 2.9.1 shows the embedded generation
Renewable technologies are more likely to be
capacity mix for Slow Progression out to 2032.
connected to the distribution grid than fossil and
As can be seen from the graph the levels
nuclear generation as they are not sufficiently
of embedded generation remain fairly static
scalable in many locations to make a transmission
throughout the period with a net increase of only
connection economically viable. In England and
0.90 GW over the whole period reflecting the
Wales, embedded generation will generally consist
underlying principles of this scenario.
of projects that are under 100 MW capacity in
Page 44
Electricity Ten Year Statement
November 2012
Figure 2.9.2:
Gone green embedded generation
20
18
16
14
12
10
GW
8
6
4
2
0
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Wind Hydro CHP Biomass Marine
Page 45
2.9 continued
Embedded generation
Figure 2.9.3:
Accelerated growth embedded generation
30
25
20
15
GW
10
0
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
Page 46
Electricity Ten Year Statement
November 2012
Page 47
Chapter three
Network capability and
future requirements
Electricity Ten Year Statement
November 2012
3.1
Introduction
The boundary assessment sections include This chapter also outlines our proposed Network
a summary of the generation that affects the Development Policy (NDP) which defines how
boundary and an identification of the potential we will assess the need to progress wider
reinforcements required under each of the transmission system reinforcements to meet the
scenarios. This forms the bulk of this chapter. requirements of our customers in an economic
and efficient manner. Please note that this is
In addition to the boundary assessment, this a National Grid Policy and applies to the
chapter also discusses the potential development onshore electricity transmission system in
of an integrated offshore network and the impact England & Wales.
of increased levels of interconnection.
Page 49
3.2
Background
Historically the NETS has developed and adapted With the expected growth in nuclear power and
to significant change, notably the adoption by wind as primary sources of energy, generation
generators of new preferred energy sources, is expected to move increasingly towards the
along with major structural changes and ongoing periphery of the system and more significantly
regulatory development. This context of evolution towards the north of the system including
and adaptation is expected to continue and even Scotland. This gives rise to increased power
accelerate in future years with increased levels of transfers and associated reinforcements
volatility and uncertainty. This chapter discusses which in turn present substantial consent
the consequential impact on transmission system and technology challenges.
requirements and our proposals for dealing with
this future. The development of the NETS is largely driven
by generation development, which in the UK
Power station sites are largely determined by is governed by market forces. This has led to
the location of their required fuel. In integrated significantly increased volumes of developments
utilities, generation and transmission may be proposed to meet the environmental targets, a
planned together and the issues arising are number of which remain uncertain. The NETSO
those of developing economic and technically and Transmission Owners (TOs) deal with this
viable solutions for transferring power from uncertainty by considering a number of future
remote locations. As described in Chapter 2 scenarios, as described in Chapter 2, from which
there is significant uncertainty surrounding the a range of indicative reinforcements emerge
development of generation. To manage this and upon which an assessment of appropriate
challenge we have developed a flexible approach reinforcement options and associated risks may
in developing future transmission capacity which be made.
allows us to respond to future requirements, whilst
minimising the risk of asset stranding. When planning future transmission capacity any
major transmission change can take many years
Transmission connected generation is distributed, to plan, construct and commission. Between
with large groups of generation clustered around the conception and delivery of a transmission
fuel sources such as coal mines, oil and gas scheme, changes in background assumptions
terminals, transport corridors and sea access. can occur which may affect both the need and
These generators are supported by good requirements of the scheme. By employing
electrical access to the large demand centres strategic planning the risks associated with
typically found in highly populated areas, such background uncertainty are reduced.
as London, Birmingham, Edinburgh, Manchester
and Glasgow.
Page 50
Electricity Ten Year Statement
November 2012
3.3
Co-ordinating the overall
transmission network
Page 51
3.4
Design criteria for the NETS
The National Electricity Transmission System are not compromised. Conversely, variations
(NETS) is designed in accordance with the requiring additional transmission investment
requirements of the Security and Quality of Supply beyond the minimum required by the SQSS are
Standard (SQSS). The standard sets out the also possible if an acceptable economic case can
minimum requirements for both planning and be made.
operating the NETS so that a satisfactory level
of safety, reliability and power quality is
maintained. Thus any modification to the
transmission system, for example new generation
3.4.1
connections, external connections and/or Generation, Demand and
changes to demand must satisfy the requirements
of the SQSS. The SQSS is applicable to all GB
Interconnectors
transmission licensees including National Grid,
In the case of generator connections, demand
Offshore Transmission Owners (OFTOs) and the
connections and interconnectors the standard
Scottish Transmission Owners.
requires that following prescribed faults and loss
of circuits, loss of power infeed should be limited
When applying this standard we utilise the
and unacceptable conditions avoided.
scenarios as described in Chapter 2 in order
to assess the performance of the NETS. Under
In the case of an individual generator or power
these conditions and for defined secured events,
station, loss of infeed is dependent upon factors
for example faults and subsequent loss of
such as generating unit size and the station
transmission equipment, the standard specifies
connection arrangements. Loss of infeed may
limits to the loss of power infeed from generating
often be determined by inspection; however
stations and loss of supply capacity at grid supply
the risk of unacceptable conditions must be
points. In addition, following such secured events
determined by detailed analysis. This requires the
no unacceptable conditions should occur. These
calculation of circuit flows, voltages and generator
conditions include: overloading of any primary
stability risk following faults and loss of circuits.
transmission equipment, unacceptable voltage
The results of such calculations are presented
conditions and system instability as defined in
later in this chapter.
the SQSS.
These results identify critical circuits which can
The security standard allows for connection
limit the transfer from an area. This process
design variations which in some cases may fall
uses the concept of a boundary separating
below the minimum required by application of
the area from the main system and crossing
the deterministic rules contained within these
the connecting circuits. These circuits are then
standards. This may typically occur when
tripped individually (N-1) and in pairs (N-2) and the
facilitating the connection of a particular type of
transfer capabilities of remaining boundary circuits
equipment and may result in reduced transmission
is determined.
investment. Nevertheless this will be acceptable if
system security and the safety of other customers
Page 52
Electricity Ten Year Statement
November 2012
Where more than one generating station or source Figure 3.4.1 shows how the different design
of power infeed is connected, a similar process is strategies affect the design of an illustrative 4 GW
adopted. In such cases additional boundaries may offshore wind farm development. The network
be drawn in order to consider the export from the design is developed to be delivered in a staged
whole group. The number of boundaries required approach to ensure timely investment and minimal
will depend on the topology of the network. stranding risk.
Page 53
3.4 continued
Design criteria for the NETS
HVDC systems, particularly the modem VSC restricting power flow along the offshore HVDC
designs, allow direct active control of the circuits power flow in the AC onshore system
power passing from one end to the other of may be directed away from areas of electrical
the DC circuits. When combined with offshore constraint. This active power control is a distinct
interconnection and parallel operation with advantage over the more traditionally passive
the onshore system, the opportunity arises to AC circuits.
benefit the onshore power flows. By boosting or
Figure 3.4.1:
Offshore transmission design strategy configurations
Page 54
Electricity Ten Year Statement
November 2012
Co-ordinated designs have been developed not as attractive for co-ordination and are
for the large offshore wind farm projects where assumed to mostly remain of radial design. There
benefit can be identified. The primary areas is still the potential to connect smaller offshore
where co-ordination has been proposed are the wind farms in a co-ordinated manner, such
Crown Estate Round 3 zones of the Firth of Forth, as those off the North West Coast of England
Dogger Bank, Hornsea, East Anglia and the Irish and the West Coast of Scotland. Where such
Sea. These areas offer the distinct possibility of opportunities are identified, they will be included in
parallel co-ordination with the onshore system any evaluation as appropriate.
due to their size and location, since links between
zones compare well with links to shore in terms of The co-ordination of the Round 3 zones mentioned
length and estimated cost. The smaller and more above could conceptually look like Figure 3.4.2
isolated projects along the South Coast, Scotland and provide transmission boundary support to a
and from earlier connection rounds are generally number of major system boundaries as shown.
Figure 3.4.2:
Offshore Coordination
Firth of Forth East Coast
Irish Sea
Page 55
3.4 continued
Design criteria for the NETS
As part of the process of developing and To demonstrate the potential benefits of offshore 1 www.nationalgrid.
com/uk/Electricity/
implementing the connection of any offshore wind farm co-ordination, the offshore to onshore OffshoreTransmission/
generation, each offshore connection will be cables installed as generators connect are OffshoreApproach/
Page 56
Electricity Ten Year Statement
November 2012
To manage this situation, we need to balance the The NDP sets out how we will make decisions
risks of investing too early in wider transmission about the choice and timing of wider transmission
reinforcements, which include the risk of inefficient network reinforcements such that the network
financing costs and an increased stranding continues to be planned in an economic and
risk, with the risks of investing too late, which efficient manner. This will involve making use of
include inefficient congestion costs. To this the available information to balance the risks of
end, following discussions between Ofgem and inefficient financing costs, stranding and inefficient
our stakeholders, the Network Development congestion costs.
Policy (NDP) is being developed to address
these challenges. As required by NDP, a summary of the inputs
and outputs of this process are published in
this document.
Page 57
3.4 continued
Design criteria for the NETS
Figure 3.4.3:
Boundary map (England, Wales, Scotland and offshore)
Page 58
Electricity Ten Year Statement
November 2012
Table 3.4.1:
Mapping of geographic areas to boundaries
Impacted Boundaries
NW1
NW2
NW3
NW4
EC1
EC3
EC5
EC6
EC7
SC1
Open Zone
B7a
B10
B11
B12
B14
B15
B16
B17
B1
B2
B3
B4
B5
B6
B7
B8
B9
Above B1 X X X X X X X X X X X
B1 – B2 X X X X X X X X X X
Within B3 X X X X X X X X X
B2 – B4 X X X X X X X X
B4 – B5 X X X X X X X
B5 – B6 X X X X X X
B6 – B7 X X X X X X
B7 – B7a X X X X
B7a – B8 X X X X X X
B8 – B9 X X X X
B9 – B10 X X
Above B11 X X X X
Below B12 X X X X X
Within B13 X X
Within B14 X X X X X
Within B15 X X X X X
Within B16 X X X X X X
Within B17 X X X X X
Within NW1 X
NW1 – NW2 X
NW2 – NW3 X X X
NW3 – NW4 X X X
Within EC1 X X X
Within EC3 X X X X
Within EC5 X X X X
Within EC6 X
Within EC7 X X
Below SC1 X X X X
Page 59
3.4 continued
Design criteria for the NETS
Figure 3.4.4:
Likely connection dates
Page 60
Electricity Ten Year Statement
November 2012
Page 61
3.4 continued
Design criteria for the NETS
The Security Criterion: The object of this In this approach scaling factors are applied
criterion is to ensure that demand can be to all classes of generation such that the
supplied securely, without undue reliance on generation meets peak demand. Based on this
either intermittent generators or imports from the Planned and Required Transfer values are
interconnectors. The background is set by: calculated in the usual way.
Determining, from a ranking order, the
conventional generation required to meet If a comparison with the Economy Criterion
120% of peak demand, based on the identifies additional reinforcements, a further CBA
generation capacity. should be performed in order to refine the timing
Scaling the output of these generators of a given investment. Further details can be
uniformly to meet demand (this means a found in the SQSS (Chapter 4, Appendix E).
scaling factor of 83%).
In networks where there is a significant volume
This selection and scaling of surplus generation of renewable generation it is expected that the
takes into account generation availability. Based application of the Economy Criteria will require
on this the Planned and Required Transfer values more transmission capacity than the Security
are calculated in the usual way. Criteria to ensure there is sufficient transmission
capacity. For some boundaries which may
This criterion determines the minimum be defined by areas which are predominantly
transmission capability required ensuring security demand driven, or which rely on conventional
of supply. This is then further assessed against the generators, the security background may produce
economic implications of a wide range of issues a higher boundary requirement.
such as safety, reliability and the value of loss of
load. Further explanation can be found later in this The Required Transfers presented in this chapter
chapter in section 3.8.6. are calculated for both criteria and the higher of
the two is plotted on the appropriate graphs for
The Economy Criterion: As increasing volumes future years.
of intermittent generation connect to the GB
system, the Security Criterion will become
increasingly unrepresentative of year-round
operating conditions.
Page 62
Electricity Ten Year Statement
November 2012
Page 63
3.4 continued
Design criteria for the NETS
Figure 3.4.5:
Example boundary graph
600
500
400
MW
300
200
100
0
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
Page 64
Electricity Ten Year Statement
November 2012
3.5
East Coast local boundaries
Page 65
3.5 continued
East Coast local boundaries
Figure EC1:
Geographical representation of East Coast Boundaries
Page 66
Electricity Ten Year Statement
November 2012
2.3
Axioms
3.5.3
Boundary EC1
Figure EC1.1:
Geographical and single line representation of boundary EC1
Generation Background
The Humber area enclosed by boundary EC1
is already a congested area of the transmission
system with 4 GW of CCGT generators
connected. Consideration is given to the
connection of up to 6 GW of new offshore wind
generation which will potentially outstrip any
potential closures. Currently there is 2 GW of
contracted offshore wind generation to connect
in this area.
Page 67
3.5 continued
East Coast local boundaries
Table EC1.1:
List of potential reinforcement projects in the EC1 boundary
Boundary Discussion and Opportunities links to meet increasing requirements. Table EC1.2
Figure EC1.2 below shows the required transfer. identifies the selected reinforcements, and their
The figure also shows the reinforcements selected timing, for each scenario.
and the benefit from the co-ordinated offshore
Figure EC1.2:
Generation background and capability for boundary EC1
12,000
10,000
8,000
6,000
MW
4,000
2,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Page 68
Electricity Ten Year Statement
November 2012
Table EC1.2:
Reinforcement date for each scenario
Scheme SP GG AG C
EC1-R01 – 2027 2024 –
OS Link-01 – 2027 2024 –
2028 2025
OS Link-02 – 2024 2023 –
2029 2025
2026
2028
2030
Currently, OHL thermal ratings are given for Under the Gone Green scenario the increase in
winter, spring/autumn and summer. These take capability seen in 2024 and 2029 is provided
into account the different ambient temperatures by the potential co-ordinated offshore link
across the year, so give fixed ratings for each OS Link-R02 as some of the offshore wind
season. There is currently a trial underway of connects. The required transfer across the
circuit monitoring – and potentially control – boundary starts to ramp up after 2026 due to
equipment in the Humber region, known as the the connection of further offshore wind farms.
Humber SmartZone. This equipment monitors From 2027, reinforcement EC1-R01 could
the temperature of OHLs and allows the use of provide sufficient capacity to satisfy the future
dynamic ratings, potentially increasing the scenario requirements. This reinforcement could
thermal rating available. This area has been be deferred a year later due to pure boundary
chosen for the trial due to the costal nature of requirements but the 2027 date is driven by
the area and the expectation of future high levels the substation build required to facilitate the
of wind generation. connection of further offshore wind. Under the
Accelerated Growth scenario reinforcement
EC1-R01 could be required from 2024. The order
of the reinforcements identified in Table EC1.2 is
subject to further evaluation.
Page 69
3.5 continued
East Coast local boundaries
3.5.4
Boundary EC3
Figure EC3.1:
Geographical and single line representation of boundary EC3
Page 70
Electricity Ten Year Statement
November 2012
Table EC3.1:
List of potential reinforcement projects in the EC3 boundary
Figure EC3.2:
Generation and capability for boundary EC3
7,500
6,500
5,500
4,500
3,500
MW
2,500
1,500
500
-500
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Page 71
3.5 continued
East Coast local boundaries
Boundary Discussion and Opportunities The current capability meets the present boundary 1 Reinforcement date
triggered by prior
Figure EC3.2 on page 71 shows the required requirement and continues to do so throughout requirement from boundary
boundary transfer from 2012 to 2032 under the the period under the Slow Progression and in the reference name
four scenarios as well the capability provided Contracted Backgrounds. The Gone Green
by the proposed reinforcements for the Gone scenario shows a modest increase in generation
Green scenario. The timing and selection of the until 2018. The sharp increases from 2019
reinforcements for all scenarios is detailed in are due to expected new CCGT connecting
Table EC3.2. within the boundary, and then the connection
of Round 3 offshore wind farms from 2024.
The existing capability of the EC3 boundary is
Table EC3.2: sufficient to sustain the generation levels under
Reinforcement date for each scenario the Gone Green scenario, with growth in the
required transfer in later years catered for by
Scheme SP GG AG C capability provided through coordinating the
EC5-R08 – – 2024 20201 offshore design, and as a result no additional
reinforcements are required until 2032.
OS Link-03 – 2029 2026 –
2027 Although the Accelerated Growth scenario shows
2028 rapid growth in required transfer after 2023, this
is met by scheme EC5-R08, which is triggered
for boundary EC5 before it is required for this
boundary. The same scheme is also triggered for
the Contracted Background by EC5.
Page 72
Electricity Ten Year Statement
November 2012
3.5.5
Boundary EC5
Figure EC5.1:
Geographical and single line representation of boundary EC5
The local boundary EC5 covers part of East Anglia Potential Reinforcements
including the substations of Norwich, Bramford Potential reinforcements for the period to 2032
and Sizewell. Crossing the boundary is a double are listed on page 74 in Table EC5.1. A number of
circuit between Norwich–Walpole and single reinforcements have been identified in order
circuits from Bramford to Pelham and Bramford to to increase this boundary’s capability.
Braintree. There is enough generation enclosed by
the boundary so that power is typically exported Boundary Discussion and Opportunities
out of the enclosed zone, predominantly along the Figure EC5.2 on page 75 shows the required
southern circuits. The maximum boundary transfer boundary transfer from 2012 to 2032 under the
capability is currently limited to 3.4 GW due to four scenarios as well the capability provided
thermal overload on the boundary circuits. by the potential reinforcements for the Gone
Green scenario. The timing and selection of the
Generation Background reinforcements for each scenario is detailed in
There is about 2.6 GW of generation connected Table EC5.2.
within this boundary, including nuclear, gas and
some offshore wind. The scenarios consider a full
range of potential offshore wind, nuclear and new
CCGT. Currently there is 8.3 GW of offshore wind
generation contracted to connect in this area.
Page 73
3.5 continued
East Coast local boundaries
This boundary has sufficient capability until 2027 generation. The increase in generation until 2022 is
under the Slow Progression scenario. But under mainly due to the addition of wind generation from
other scenarios and the Contracted Background, a the offshore wind farms off the Norfolk coast. The
number of reinforcements are required to facilitate increase in transfer in this boundary in later years is
the rapid increase in forecasted due to commissioning of nuclear generation within
this zone which occurs in all scenarios.
Page 74
Electricity Ten Year Statement
November 2012
Figure EC5.2:
Generation and capability for boundary EC5
14,000
12,000
10,000
8,000
MW
6,000
4,000
2,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Slow Progression Gone Green Accelerated Growth Contracted Background GG Capability
Page 75
3.5 continued
East Coast local boundaries
3.5.6
Boundary EC6
Figure EC6.1:
Geographical and single line representation of boundary EC6
Local boundary EC6 is located within boundary existing generation, the scenarios consider new
EC5 and is currently defined by four circuits nuclear and offshore wind generation.
from Sizewell to Bramford. The current transfer
capability is limited to 2.4 GW due to the circuit Potential Reinforcements
ratings and configuration that was designed The connection of significant new generation
to meet only the needs of the current nuclear within EC6 will require the reinforcements
generation at Sizewell. identified in Table EC6.1 below. The EC6-R02
Bramford reinforcement has also been included
Generation Background in this list, as without it the export from this
Presently there is 1.7 GW of installed generation boundary would be restricted by limited
capacity connected within EC6. In addition to the substation configuration capability.
Table EC6.1:
List of potential reinforcement projects in the EC6 boundary
Page 76
Electricity Ten Year Statement
November 2012
Boundary Discussion and Opportunities by the potential reinforcements for the Gone
Figure EC6.2 below shows the required Green scenario. The timing and selection of the
boundary transfer from 2012 to 2032 under the reinforcements for each scenario is detailed in
four scenarios as well the capability provided Table EC6.2.
Figure EC6.2:
Generation and capability for boundary EC6
7,000
6,000
5,000
4,000
MW
3,000
2,000
1,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Table EC6.2:
Reinforcement date for each scenario
Page 77
3.5 continued
East Coast local boundaries
3.5.7
Boundary EC7
Figure EC7.1:
Geographical and single line representation of boundary EC7
Boundary EC7 is a local boundary that biggest impact on this boundary. There is
encompasses the north east of England. One of currently 4 GW of offshore wind in the contracted
the principle Anglo-Scottish double circuits – the background within this boundary.
400kV Eccles–Stella West–Norton circuit – passes
through the region. At the southern end a second A future HVDC interconnector to Norway may
400kV circuit crosses the boundary. Within the also connect into the north-east coast and is
boundary is a ring of predominantly 275kV circuits currently contracted for connection in 2018 at
that serve local demand and carry any generation 1.4 GW capacity.
surplus in the area to the 400kV circuits. This area
is constrained by north-south power flows and is Potential Reinforcements
traditionally characterised The connection of new generation within EC7
as an exporting area, with the 400kV circuits will trigger the boundary reinforcements identified
at the southern end of the boundary liable to in Table EC7.1 on page 79. As much of the
limit transfers. transmission within the EC 7 boundary is of
275kV construction, it is of lower capability than
Generation Background the 400kV sections so large new connections
Current generation capacity within the boundary will require upgrading of the local 275kV part of
consists of 1.2 GW of nuclear generation and the system. Those local reinforcements that are
0.2 GW of other smaller thermal plant. New heavily dependent on the location of specific
offshore wind generation is likely to have the generation projects are not listed here.
Page 78
Electricity Ten Year Statement
November 2012
Table EC7.1:
List of potential reinforcement projects in the EC7 boundary
Figure EC7.2:
Generation background and capability for boundary EC7
8,000
7,000
6,000
5,000
4,000
3,000
MW
2,000
1,000
0
-1,000
-2,000
-3,000
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Page 79
3.5 continued
East Coast local boundaries
Scheme SP GG AG C
B7a-R03 – 2020 1
2018 1
20181
EC7-R01 2028 2025 2022 2019
OS Link-01 2025 2022 2019 2017
2027 2024 2021 2019
2027 2024
2028 2025
2027
2029
OS Link-03 – 2029 2026 –
2028
2028
Boundary Discussion and Opportunities for significant reinforcement, but the B7a-R03
Figure EC7.2 shows the required boundary Yorkshire lines reconductoring, triggered by B7a
transfer from 2012 to 2032 under the four and the Saltholme upgrade EC7-R01 will more
scenarios as well the capability provided by the than meet this requirement. If the existing nuclear
proposed reinforcements for the Gone Green power station closes then this will free additional
scenario. North to south power flows load boundary capacity.
the circuits to an extent that additional export
capability is difficult to realise. Suggested There is the potential for additional offshore
timing and selection of the reinforcements for HVDC links from Scotland to connect into this
all scenarios is detailed in Table EC7.2. region, potentially adding 4 GW or more of
cross-boundary through flow.
This region currently imports but the trend in
future years is for the region to move to export The Norwegian interconnector will place
as new offshore wind generation connects. an additional 1.4 GW of boundary capacity
The export capability is insufficient to meet the requirement when importing to GB but at the
predicted future required transfers for all the default scenario assumption of no interconnector
scenarios other than Slow Progression. For power flow, there is not additional stressing of
the Contracted background there is a need the boundary.
Page 80
Electricity Ten Year Statement
November 2012
3.6
North Wales local boundaries
Page 81
3.6 continued
North Wales local boundaries
Figure NW1:
Geographical representation of North Wales boundaries
Page 82
Electricity Ten Year Statement
November 2012
3.6.3
Boundary NW1
Figure NW1.1:
Geographical and single line representation of boundary NW1
Potential Reinforcements
A number of potential reinforcements have
been identified for the NW1 boundary to meet
the required power transfers. Table NW1.1 on
page 84 lists possible reinforcements that have
been identified for boundary NW1 including a
brief works description.
Page 83
3.6 continued
North Wales local boundaries
Table NW1.1:
List of potential reinforcement projects in the NW1 boundary
Boundary Discussion and Opportunities by the potential reinforcements for the Gone
Figure NW1.2 below shows the required Green scenario. The timing and selection of the
boundary transfer from 2012 to 2032 under the reinforcements for each scenario is detailed in
four scenarios as well the capability provided Table NW1.2.
Figure NW1.2:
Generation and capability for boundary NW1
8,000
7,000
6,000
5,000
MW
4,000
3,000
2,000
1,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Page 84
Electricity Ten Year Statement
November 2012
Ref SP GG AG C
NW1-R011 2025 2022 2021 2020
B8-R01 – 20221 20221 20191
OS-Link-05 – 2020 2019 2019
Page 85
3.6 continued
North Wales local boundaries
3.6.4
Boundary NW2
Figure NW2.1:
Geographical and single line representation of boundary NW2
This local boundary bisects the North Wales maximum capacity for the pump storage units.
mainland close to Anglesey and as shown in Across the scenarios a range of offshore wind
Figure NW2.1 above, crosses through the Pentir and new nuclear is considered in addition to the
to Deeside 400kV double circuit and Pentir to non-GB generation developments identified in
Trawsfynydd 400kV single circuit. The existing section 2.8. There is currently 3 GW of additional
boundary capability is 1.5 GW, limited by the offshore wind and 3.6 GW of new nuclear in the
single circuit connecting Pentir to Trawsfynydd. contracted background within this boundary.
Page 86
Electricity Ten Year Statement
November 2012
Table NW2.1:
List of potential reinforcement projects in the NW2 boundary
NW2-R01 Establish second Pentir– Reconductor existing 132 kV circuit for operation at
Trawsfynydd 400 kV New 400 kV Reconfiguration and extension of Pentir 400
Transmission Route kV substation Increase the capacity of the cable link
crossing the Glaslyn Estuary to be equivalent to the
overhead line
B8-R01 Wylfa–Pembroke HVDC Link 2 GW HVDC link from Wylfa/Irish Sea to Pembroke.
substation extension at Wylfa and Pembroke
NW3-R03 Pentir–Deeside Reconductor the Pentir–Deeside existing double
Reconductoring circuit with higher rated conductor
OS-Link-05 Lancashire–North Wales Offshore Integration between North Wales, Irish Sea
Offshore Integration offshore projects and Lancashire region
OS Link-04 Irish Integration Controllable interconnection between the Irish Wind
circuits connecting to Pentir and Pembroke
Page 87
3.6 continued
North Wales local boundaries
12,000
10,000
8,000
MW
6,000
4,000
2,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
The establishment of a second Pentir to the North Wales to South Wales group or vice
Trawsfynydd circuit (NW2-R01) increases the versa in the event of system faults. Transmission
capability. The earliest this reinforcement can be capability improvements from this are shown in
delivered is 2018 due to construction and outages the graph and Table NW2.2 (OS Link-04 and
planning availability. OS Link-05). The alternative, of connecting the
entire 3 GW generation to one group, would
Due to the volume of generation connecting require major onshore system reinforcements to
at sites in both North and South Wales this accommodate generation post-fault, most likely
creates the opportunity for new offshore routes a new transmission route across either North or
which allow generation to be transferred from South Wales.
Page 88
Electricity Ten Year Statement
November 2012
3.6.5
Boundary NW3
Figure NW3.1:
Geographical and single line representation of boundary NW3
Potential Reinforcements
Most of the potential reinforcements determined
for NW2 also provide capability for NW3. Table
NW3.1 on page 90 lists a brief works description.
Page 89
3.6 continued
North Wales local boundaries
Table NW3.1:
List of potential reinforcement projects in the NW3 boundary
Page 90
Electricity Ten Year Statement
November 2012
Figure NW3.2:
Generation and capability for boundary NW3
12,000
10,000
8,000
MW
6,000
4,000
2,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Slow Progression Gone Green Accelerated Growth Contracted Background GG Capability
Page 91
3.6 continued
North Wales local boundaries
3.6.6
Boundary NW4
Figure NW4.1:
Geographical and single line representation of boundary NW4
Page 92
Electricity Ten Year Statement
November 2012
Table NW4.1:
List of potential reinforcement projects in the NW4 boundary
Boundary Discussion and Opportunities by the potential reinforcements for the Gone
Figure NW4.2 below shows the required Green scenario. The timing and selection of the
boundary transfer from 2012 to 2032 under the reinforcements for each scenario is detailed in
four scenarios as well the capability provided Table NW4.2.
Figure NW4.2:
Generation and capability for boundary NW4
9,000
8,000
7,000
6,000
5,000
MW
4,000
3,000
2,000
1,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Page 93
3.6 continued
North Wales local boundaries
Ref SP GG AG C
B8-R01 – 2022 1
2022 2019
OS-Link-05 – 2020 1
2019 2019
OS Link-04 – 2028 2025 2018
Page 94
Electricity Ten Year Statement
November 2012
3.7
Wider boundaries
3.7.1
Boundary B1
Figure B1.1:
Geographical representation of boundary B1
The Boundary B1 runs from the Moray coast near generation connections north of the boundary
MacDuff to the West coast near Oban, separating are expected to massively increase the export
the north-west of Scotland from the southern requirements across the boundary as can be
and eastern regions. The area to the north-west seen in Figure B1.2.
of Boundary 1 is inclusive of the Western Isles,
Skye, Mull, Moray, Caithness, Beauly, and Orkney. Generation Background
The boundary crosses the 275kV double circuits In all of the generation scenarios, there is an
running eastwards from Beauly and the double increase in the power transfer through B1 due
circuit running southwards from Fort Augustus. to the large volume of renewable generation
The present B1 boundary capability is around connecting to the north of this boundary. This is
500 MW. primarily onshore wind and small scale hydro,
however, there is the prospect of significant
The existing transmission infrastructure in hydro, wave and tidal generation resources being
northwest Scotland is relatively sparse, formed connected in the longer term. The contracted
from 275 kV and 132 kV assets. Some of the generation behind B1 within the time horizon
large new generation projects are in places covered by this ETYS includes the renewable
remote from any form of strong transmission generation on the Western Isles, Orkney and
infrastructure so new infrastructure is required the Shetland Isles as well as a range of large
both for connection and to support power and small onshore wind developments. It is
export out of the area. New renewable also expected that some marine generation will
Page 95
3.7 continued
Wider boundaries
connect in this zone within the ETYS time period. Potential Reinforcements
Under all scenarios the total generation above Several reinforcement projects, as summarised
the B1 boundary increases. This large generation in Table B1.1, have been identified to cater for
increase is not likely to be offset by any closure the increasing power exports across boundary
of generation plants. B1. The Beauly to Denny reinforcement (B1-R01)
extends across boundaries B2 and B4 providing
additional capability for these as well as
Boundary B1.
Table B1.1:
List of existing and potential reinforcement projects for the B1 boundary
Page 96
Electricity Ten Year Statement
November 2012
Figure B1.2:
Required transfer and capability for boundary B1
6,000
5,000
4,000
MW
3,000
2,000
1,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Slow Progression Gone Green Accelerated Growth Contracted Background GG Capability
Page 97
3.7 continued
Wider boundaries
Page 98
Electricity Ten Year Statement
November 2012
Table B1.3:
List of reinforcement projects within the zone to the north of the B1 boundary
Page 99
3.7 continued
Wider boundaries
Page 100
Electricity Ten Year Statement
November 2012
3.7.2
Boundary B2
Figure B2.1:
Geographical representation of boundary B2
Page 101
3.7 continued
Wider boundaries
Table B2.1:
List of existing and potential reinforcement projects for the B2 boundary
Page 102
Electricity Ten Year Statement
November 2012
Figure B2.2:
Required transfer and capability for boundary B2
8,000
7,000
6,000
5,000
MW
4,000
3,000
2,000
1,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Slow Progression Gone Green Accelerated Growth Contracted Background GG Capability
Generation to the north of this boundary is Beyond this, additional reinforcement of the
increasing at a significant rate due to the high B2 boundary will be required for all generation
volume of contracted renewable generation scenarios. The proposed East Coast 400kV
seeking connection in this area. Consequently, upgrade (B2-R01) comprises an upgrade of one
the boundary transfers are also increasing at a of the existing 275kV east coast routes between
similar rate. Blackhillock and Kincardine, to 400kV using
existing infrastructure that is currently operated
The increase in the required transfer capability at 275kV but which is constructed at 400kV. This
for this boundary across all generation scenarios increases the B2 capability from around 2500 MW
indicates the need to reinforce the transmission to around 3400 MW by 2017.
system on both the West and East transmission
Page 103
3.7 continued
Wider boundaries
To facilitate further connection of large volumes of For the other scenarios it can be seen that
wind, a new Eastern HVDC link (B6-R03) between the predicted continual growth in generation
Peterhead, Torness and Hawthorn Pit in the north connections requires a very challenging
east of England, is also proposed in 2019 for programme of works to facilitate. A second new
all the scenarios except Slow Progression, Eastern HVDC link (B7-R03) could be delivered
where a later 2020 delivery date is more suitable. post 2020 if required to facilitate the growth in
This increases the B2 capability to around marine and wind generation. For the contracted
5500 MW. After 2022, there is little growth in the background, there is a far greater pace of wind
Slow Progression required transfer, predominantly farm connection in the early years, with the
due to a reduced amount of generation in the required transfer peaking around 2020 after
Round 3 and Scottish Territorial Waters wind which point it levels off at around 6 GW across
farm zones, and no assumed CCGT generation B2. The dates shown for required reinforcements
connecting in the later part of the period. represent the earliest possible delivery dates.
Accordingly, no further reinforcements are
required beyond the first HVDC link (B6-R03). There are a number of other reinforcement
projects to the north of the B2 boundary which
are necessary to secure the network and for the
connection of generation in this area.
Table B2.3:
List of reinforcement projects within the zone to the north of the B2 boundary
Page 104
Electricity Ten Year Statement
November 2012
3.7.3
Boundary B3
Figure B3.1:
Geographical and single line representation of boundary B3
Boundary B3 is a local boundary within the SHE constant although there is the potential for
Transmission system and encompasses Argyll and further generation in this area. The generation
the Kintyre peninsula. It cuts across the circuits comprises large and small scale hydro generation,
running to the south of the Sloy and Inverarnan onshore wind and small scale marine generation.
substations. The present boundary capability is Approximately half of the generation total is
350 MW. wind with a small volume of marine and hydro
accounting for the remainder.
Generation Background
The contracted generation within the B3 Potential Reinforcements
boundary increases from around 380 MW in One reinforcement project is presently proposed
2012 to around 510 MW in 2017. After 2017 the for the B3 boundary, as summarised in Table B3.1.
contracted generation remains approximately
Table B3.1:
List of potential reinforcement projects for the B3 boundary
Page 105
3.7 continued
Wider boundaries
Page 106
Electricity Ten Year Statement
November 2012
3.7.4
Boundary B4
Figure B4.1:
Geographical representation of boundary B4
Page 107
3.7 continued
Wider boundaries
Table B4.1:
List of potential reinforcement projects for the B4 boundary
Page 108
Electricity Ten Year Statement
November 2012
Figure B4.2:
Required transfer and capability for boundary B4
8,000
7,000
6,000
5,000
MW
4,000
3,000
2,000
1,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Slow Progression Gone Green Accelerated Growth Contracted Background GG Capability
Page 109
3.7 continued
Wider boundaries
The increase in the required transfer capability Beyond this the proposed Eastern HVDC link (B6-
over the ETYS period clearly indicates the need R03). After 2022, there is little growth in the Slow
to reinforce the transmission system across Progression required transfer, predominantly due
the B4 boundary. The current B4 capability to a reduced amount of generation in the Round
is insufficient to satisfy the boundary transfer 3 and Scottish Territorial Waters wind farm zones,
requirement for the first few years under the Gone and no assumed CCGT generation connecting in
Green and Contracted scenarios. This is due to the later part of the period. Accordingly, no further
generation being connected ahead of the required reinforcements are required.
reinforcement in accordance with the Connect
and Manage access framework. For the other scenarios the predicted ongoing
growth in generation requires a very challenging
The proposed Beauly to Denny reinforcement programme of works to facilitate connections. A
will increase the capacity of the B4 boundary second new Eastern HVDC link could be delivered
significantly from around 1800 MW to around post-2020 if required to provide the transmission
3000 MW in 2015. The East Coast 400kV capacity to support the growth in marine and wind
reinforcement will increase the B4 boundary generation. For the contracted background, there
capability from around 3000 MW to around is a far greater pace of wind farm connection in
3900 MW. the early years, with the required transfer peaking
around 2019 after which point it gently decreases,
Smaller incremental upgrades to the SHE primarily due to the high volume of contracted
Transmission network including the installation generation connections in England and Wales.
of phase shifting transformers at Blackhillock, The dates shown for reinforcements in this case
the reconfiguration of the Errochty 132kV busbar represent earliest possible delivery dates.
and the incremental works on the Tealing–
Westfield–Longannet circuits allow optimisation
of power flows though the network will provide
small but very cost effective increases in the
B4 boundary capability.
Page 110
Electricity Ten Year Statement
November 2012
3.7.5
Boundary B5
Figure B5.1:
Geographical representation of boundary B5
Page 111
3.7 continued
Wider boundaries
Table B5.1:
List of potential reinforcement projects of works for the B5 boundary
Boundary Discussion and Opportunities as well as the optimum reinforcements and their
Figure B5.2 below shows the required transfer timing for the Gone Green scenario. Beneath,
capabilities from 2012 to 2032 for the three Table B5.2 identifies the reinforcements selected
scenarios and the Contracted Background, for each scenario.
Figure B5.2:
Required transfer and capability for boundary B5
10,000
9,000
8,000
7,000
6,000
MW
5,000
4,000
3,000
2,000
1,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Page 112
Electricity Ten Year Statement
November 2012
Page 113
3.7 continued
Wider boundaries
3.7.6
Boundary B6
Figure B6.1:
Geographical representation of boundary B6
Page 114
Electricity Ten Year Statement
November 2012
Table B6.1:
List of potential reinforcement options and description of works for the B6 boundary
Page 115
3.7 continued
Wider boundaries
Figure B6.2:
Required transfer and capability for boundary B6
14,000
12,000
10,000
8,000
MW
6,000
4,000
2,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Page 116
Electricity Ten Year Statement
November 2012
3.7.7
Boundary B7
Figure B7.1:
Geographical representation of boundary B7
Generation Background
In all scenarios there is an increase in generation
output over the period considered, as the
boundary is influenced by everything north of
Teesside. In addition to that identified in the
B6 section there is a further 4 GW of offshore
wind, 3 GW of new nuclear and 1.4 GW of new
interconnector capacity contracted to connect.
Page 117
3.7 continued
Wider boundaries
Table B7.1:
List of potential reinforcement projects in the EC1 boundary
Page 118
Electricity Ten Year Statement
November 2012
Figure B7.2:
Required transfer and capability for boundary B7
18,000
16,000
14,000
12,000
10,000
MW
8,000
6,000
4,000
2,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Slow Progression Gone Green Accelerated Growth Contracted Background GG Capability
Page 119
3.7 continued
Wider boundaries
Page 120
Electricity Ten Year Statement
November 2012
3.7.8
Boundary B7a
Figure B7a.1:
Geographical representation of boundary B7a
Boundary B7a runs parallel with boundary most significant changes to generation in this
B7, sharing the same path in the east, region predominantly occurs after 2020, with
but encompassing Heysham, Hutton and the connection of 1.75 GW of offshore wind.
Penwortham in the west. The boundary intersects Anticipated closures of existing generation may
two double 400kV circuits in the east and a 400kV result in little overall change in the generation
double circuit and a 275kV double circuit south surplus within this region.
of Penwortham in the west. The region between
Boundary B7 and B7a includes more generation Potential Reinforcements
than demand, further increasing the transfers Potential reinforcements for the period to 2032 are
from north to south. The boundary capability is listed in Table B7a.1 on page 122. This boundary
currently 4.8 GW, limited by thermal ratings. is primarily limited by thermal ratings, so the
reinforcements focus on uprating existing lines,
Generation Background or constructing new ones.
The generation background for B7a is dominated
by the generation north of B7. Within the
region between B7 and B7a, a number of
approximately 100–200 MW sized offshore
wind farms are already connected with further
similar developments expected in the next few
years. This is partially offset by the anticipated
closure of some existing generation. The
Page 121
3.7 continued
Wider boundaries
Table B7a.1:
List of potential reinforcement projects in the B7a boundary
Page 122
Electricity Ten Year Statement
November 2012
Figure B7a.2:
Required transfer and capability for boundary B7a
20,000
18,000
16,000
14,000
12,000
MW
10,000
8,000
6,000
4,000
2,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Slow Progression Gone Green Accelerated Growth Contracted Background GG Capability
Page 123
3.7 continued
Wider boundaries
Table B7a.2:
Selection and timing of reinforcements
Ref SP GG AG C
B7a-R01 2014 2014 2014 2014
B6-R02 2016 2016 2016 2016
B7a-R02 – 2019 2018 2018
B7a-R03 – 2020 2018 2018
B6-R03 2026 2019 2019 2019
B6-R05 – 2021 2019 2019
B7-R03 – 2025 2022 2020
B7-R04 – – 2025 2023
OS Link-01 2025 2022 2019 2017
2027 2024 2021 2019
2027 2024
2028 2025
2027
2029
OS Link-03 – 2029 2026
2028
2030
OS link-05 – 2020 2019 –
2021
2023
Page 124
Electricity Ten Year Statement
November 2012
3.7.9
Boundary B8
Figure B8.1:
Geographical representation of boundary B8
Page 125
3.7 continued
Wider boundaries
Table B8.1:
List of potential reinforcement projects in the B8 boundary
Boundary Discussion and Opportunities as shown in Figure B8.2 with the exception of
Boundary B8 has traditionally been heavily loaded Slow Progression which increases slowly in the
at the time of winter peak due to high north to next few years then remains steady beyond 2020.
south power flows. Several offshore wind farms
are expected to connect north of B8. These Reactive energy support in the areas with long
new connections drive the trend of significant heavily loaded circuits is the key to sustain the
increases in required transfers for all scenarios, high level of power transfer across the boundary.
Page 126
Electricity Ten Year Statement
November 2012
Changes in the capacity and geographic Figure B8.2 below shows the required transfer
locations of the generation in the Midlands could capabilities from 2012 to 2032 for the four
lead to variations in the B8 boundary capability different scenarios, as well as the optimum
throughout the years of analysis. reinforcements and their timing for the Gone
Green scenario. Beneath, Table B8.2 identifies
the reinforcements selected for each scenario.
Figure B8.2:
Required transfer and capability for boundary B8
20,000
18,000
16,000
14,000
MW
12,000
10,000
8,000
6,000
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
The existing infrastructure will sustain the extra route for the power to flow south. The HVDC
additional transfer requirements up to 2020 link will provide shared benefits across several
except for in the Contracted Background, despite wider boundaries.
changes in the generation background leading
to a capability decrease. Onshore reinforcement In addition to B8-R01, offshore integration in
will be required for the Contracted Background the East Coast and Wales (OS Link-02, OS
around 2018. B8-R01 will be required in all Link-03, and OS Link-04) will provide transfer
scenarios with the exception of Slow Progression capability to B8 and reduce the requirement for
to satisfy the transfer requirement by creating an onshore reinforcements. Together with onshore
Page 127
3.7 continued
Wider boundaries
Table B8.2:
Selection and timing of reinforcements
Ref SP GG AG C
B8-R01 – 2022 2022 2019
B8-R02 2031 2029 2024 2018
B11-R01 – – 2025 1
–
B17-R02 20311 20291 20241 20181
EC1-R01 – 20271 20241 –
EC5-R08 – – 2024 1
20201
EC5-R04 – 20251 20211 20181
OS Link-02 – 20241 2023 –
20251
OS Link-03 – 20291 2026 –
2028
20301
OS Link-04 – 20251 20251 20181
Page 128
Electricity Ten Year Statement
November 2012
3.7.10
Boundary B9
Figure B9.1:
Geographical representation of boundary B9
Page 129
3.7 continued
Wider boundaries
Table B9.1:
List of potential reinforcement projects in the B9 boundary
Page 130
Electricity Ten Year Statement
November 2012
Figure B9.2:
Required transfer and capability for boundary B9
18,000
16,000
14,000
12,000
10,000
MW
8,000
6,000
4,000
2,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Slow Progression Gone Green Accelerated Growth Contracted Background GG Capability
1 Reinforcement date There is sufficient capacity across this boundary Table B9.3:
triggered by prior
requirement from boundary
to meet requirements of all the scenarios until Selection and timing of reinforcements
in the reference name 2024. The boundary benefits from many projects
that are required by the East Coast, North Wales
Ref SP GG AG C
and B8, B11 boundaries, including offshore
reinforcements (B8-R01, OS Link-02, OS Link-03, B8-R01 – 2022 1
2022 1
20191
OS Link-04) and onshore reinforcements (B8-R02, B8-R02 20311 20291 2024 20181
B11-R01, B17-R02, EC5-R08, EC5-R06). Table
B9.2 shows the year the reinforcements of B9 B11-R01 – – 20251 –
are required, and the available date of potential B17-R02 2031 1
2029 1
2024 1
20181
co-ordinated offshore links.
EC5-R08 – – 20241 20201
EC5-R04 – 20251 20211 20181
OS Link-02 – 20241 2023 –
20251
OS Link-03 – 20291 2026 –
2028
20301
OS Link-04 – 20251 20251 20181
Page 131
3.7 continued
Wider boundaries
3.7.11
Boundary B10
Figure B10.1:
Geographical representation of boundary B10
Generation Background
The existing generation within this boundary is
mostly thermal, as well as the nuclear generator
at Hinkley Point. There is over 5 GW of renewable
generation and 3.3 GW of new nuclear generation
capacity contracted to connect within this boundary.
Page 132
Electricity Ten Year Statement
November 2012
Figure B10.2:
Required transfer and capability for boundary B10
8,000
7,000
6,000
5,000
MW
4,000
3,000
2,000
1,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Page 133
3.7 continued
Wider boundaries
Ref SP GG AG C
B13-R01 2024 1
2021 1
2020 1
20171
Page 134
Electricity Ten Year Statement
November 2012
3.7.12
Boundary B11
Figure B11.1:
Geographical map of boundary B11
Page 135
3.7 continued
Wider boundaries
Table B11.1:
List of potential reinforcement projects in the B11 boundary
Page 136
Electricity Ten Year Statement
November 2012
Figure B11.2:
Required transfer and capability for boundary B11
20,000
18,000
16,000
14,000
MW
12,000
10,000
8,000
6,000
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Slow Progression Gone Green Accelerated Growth Contracted Background GG Capability
1 Reinforcement date
triggered by prior Boundary Discussion and Opportunities Table B11.2:
requirement from boundary Figure B11.2 above shows the required transfer Selection and timing of reinforcements
in the reference name
capabilities from 2012 to 2032 for three scenarios
and the contracted background, as well as
Ref SP GG AG CB
the optimum reinforcements and their timing
for the Gone Green scenario. Table B11.2 B6-R01 2015 1
2015 1
2015 1
20151
identifies the reinforcements selected B7-R01 20141 20141 20141 20141
for each scenario.
B6-R02 20161 20161 20161 20161
EC1-R01 20271 2024 –
B11-R01 – 2025 –
OS Link-02 – 2024 1
2023 –
2026
OS Link-03 – 20291 2026 –
2028
20301
Page 137
3.7 continued
Wider boundaries
Page 138
Electricity Ten Year Statement
November 2012
3.7.13
Boundary B12
Figure B12.1:
Geographical representation of boundary B12
Page 139
3.7 continued
Wider boundaries
Table B12.1:
List of potential reinforcement projects in the B12 boundary
Figure B12.2:
Required transfer and capability for boundary B12
10,000
9,000
8,000
7,000
6,000
5,000
MW
4,000
3,000
2,000
1,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Page 140
Electricity Ten Year Statement
November 2012
Ref SP GG AG C
B8-R01 – 2022 1
2022 1
20191
B14(e)-R02 – 20211 20171 20171
OS Link-04 – 20251 20251 20181
Page 141
3.7 continued
Wider boundaries
3.7.14
Boundary B13
Figure B13.1:
Geographical and single line representation of boundary B13
Page 142
Electricity Ten Year Statement
November 2012
Boundary Discussion and Opportunities by the proposed reinforcements for the Gone
Figure B13.2 below shows the variation in B13 Green scenario. The timing and selection of the
boundary requirements from 2012 to 2032 reinforcements for each scenario is detailed in
under the three scenarios and the contracted Table B13.2
background, as well as the capability provided
Figure B13.2:
Required transfer and capability for boundary B13
5,000
4,000
3,000
2,000
1,000
0
MW
-1,000
-2,000
-3,000
-4,000
-5,000
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Slow Progression Gone Green Accelerated Growth Contracted Background GG Capability B13E
GG Capability B13I
Page 143
3.7 continued
Wider boundaries
Table B13.2:
Selection and timing of reinforcements
Ref SP GG AG C
B13-R01 2024 2021 2020 2017
Page 144
Electricity Ten Year Statement
November 2012
3.7.15
Boundary SC1
Figure SC 1.1:
Geographical representation of boundary SC1
This boundary as shown in Figure SC1.1 runs This import is reduced by the potential connection
parallel to the south coast of England between of new generation. Within this area, there is an
the Severn and Thames Estuaries, crossing three opportunity for up to 5.7 GW of offshore wind
major double circuits: Canterbury North–Cleve connections in the contracted background.
Hill in the East, Hinkley point–Taunton in the West
and Bramley–Fleet in the centre. The subsystem The scenarios consider a full range of potential
enclosed is historically an importing area of the offshore wind and interconnector generation.
system. Future scenarios include new wind farms
and new HVDC interconnection to Europe, which Potential Reinforcements
gives rise to the risk of significant variation in the Potential reinforcements for the period to 2032
transfer levels. are listed on page 146 in Table SC1.1.
Generation Background
Installed generation broadly matches demand but
a reduced contribution from older plant plus the
potential for exports to France via the 2 GW IFA
interconnector may result in an import into the
region. The potential for further interconnection
capacity could impact on the required transfers
and may increase imports into the region.
Page 145
3.7 continued
Wider boundaries
Table SC1.1:
List of potential reinforcement projects in the SC1 boundary
Boundary Discussion and Opportunities reinforcements is also illustrated for the Gone
Figure SC.1.2 illustrates the range of possible Green scenario. Table SC1.2 identifies the
Required Transfers arising in the scenarios and selected reinforcements, and their timing,
the Contracted Background. The boundary for each scenario.
capability including contribution from additional
Figure SC1.2:
Required transfer and capability for boundary SC1
10,000
9,000
8,000
7,000
6,000
5,000
MW
4,000
3,000
2,000
1,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Page 146
Electricity Ten Year Statement
November 2012
Table SC1.2:
Selection and timing of reinforcements
Ref SP GG AG C
SC1-R01 2018 2018 2018 2018
SC1-R02 2018 2018 2028 2018
SC1-R03 2018 2018 2018 2018
Page 147
3.7 continued
Wider boundaries
3.7.16
Boundary B14
Figure B14.1:
Geographical and single line representation of boundary B14
Generation Background
There is currently little generation in the
London area with demand mainly met by
generation outside the boundary. Major new
generation projects are not expected within the
boundary across any of the scenarios. As this
a predominantly demand driven boundary the
demand growth is the dominant factor in the
boundary’s requirements.
Page 148
Electricity Ten Year Statement
November 2012
Table B14.1:
List of potential reinforcement projects in the B14 boundary
Boundary Discussion and Opportunities for Gone Green including any increase from
Figure B14.2 on page 150 shows the required reinforcements selected to meet increasing
transfer for Boundary B14 from 2012 to 2032 requirements. Table B14.2 identifies
for the three scenarios and the Contracted the selected reinforcements, and their timing,
Background, as well as the boundary capability for each scenario.
Page 149
3.7 continued
Wider boundaries
Figure B14.2:
Generation Background and capability for boundary B14
14,000
13,000
12,000
11,000
MW
10,000
9,000
8,000
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Page 150
Electricity Ten Year Statement
November 2012
Table B14(e).1:
List of potential reinforcement projects in the B14(e) boundary
Page 151
3.7 continued
Wider boundaries
Figure B14(e).2:
Required transfer and capability for boundary B14(e)
13,000
12,500
12,000
11,500
11,000
10,500
MW
10,000
9,500
9,000
8,500
8,000
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Boundary Discussion and Opportunities B14(e).2, although this will be subject to robust
With the HVDC links to Europe exporting, there cost benefit analysis (NDP) to determine the most
is additional transfer necessary into the South cost efficient date for building the reinforcements.
East, which results in larger through-flow across The calculated boundary transfer exceeds the
London, causing a fall in the boundary B14(e) capability from 2012 if the interconnectors are
capability, limited by both voltage and thermal fully exporting to Europe. However the earliest
compliance issues. possible year for delivering the identified
B14(e)-R01 reinforcement is 2016. For the
The set of reinforcements listed in Table B14(e).2 Accelerated Growth scenario, B14 remains
provide sufficient boundary capability to facilitate non compliant, under interconnector exporting
the suggested European interconnection and conditions, from 2028 onwards despite delivery
allow unrestricted access to the European Energy of all the suggested reinforcements. This situation
Market. The benefits of these reinforcements will need to be re-evaluated in the future as
for the Gone Green scenario are illustrated in the status of generation, demand and
Figure B14(e).2. The timing of reinforcements interconnection becomes clearer.
within the different scenarios is shown in Table
Page 152
Electricity Ten Year Statement
November 2012
Table B14(e).2:
Selection and timing of reinforcements
Ref SP GG AG C
B14(e)-R01 2016 2016 2016 2016
B14(e)-R02 – 2021 2017 2017
B14(e)-R03 – 2021 2017 2017
B14(e)-R04 – 2028 2025 2021
B14(e)-R05 – 2027 2023 2019
B14(e)-R06 – 2024 2019 2018
B14(e)-R07 – 2031 2026 –
B14(e)-R08 – 2031 2026 –
Page 153
3.7 continued
Wider boundaries
3.7.18
Boundary B15
Figure B15.1:
Geographical and single line representation of boundary B15
Generation Background
Current generation within the boundary totals
around 9 GW. The overall generation levels within
the boundary initially decrease across all scenarios
due to closures offsetting any new generation
connections. A range of thermal and new nuclear
generation connections are considered across
the scenarios.
Potential Reinforcements
Potential reinforcements for the period to 2032
are listed on page 155 in Table B15.1.
Page 154
Electricity Ten Year Statement
November 2012
Table B15.1:
List of potential reinforcement projects in the B15 boundary
Figure B15.2:
Required transfer and capability for boundary B15
10,000
9,000
8,000
7,000
MW
6,000
5,000
4,000
3,000
2,000
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Page 155
3.7 continued
Wider boundaries
Ref SP GG AG C
B14(e)-R01 2016 1
2016 1
2016 1
20161
Page 156
Electricity Ten Year Statement
November 2012
3.7.19
Boundary B16
Figure B16.1:
Geographical map of boundary B16
B16 follows the path of B11 in the west, while Generation Background
in the east it also encompasses the areas The significant changes described in previous
of Nottinghamshire and Lincolnshire, thus boundary commentaries (B1–B7, EC1 and
incorporating additional generation from these EC7) also apply to this boundary and the net
regions. The boundary crosses the four double effect is shown in Figure B16.2. A range of
circuits running south from Nottinghamshire new generation connections and closures are
(West Burton / Cottam), instead of the two circuit considered across the scenarios including
pairs south of Keadby. Similarly to B11, B16 is offshore wind and thermal generation.
considered a boundary that carries power from
north to south. B16 is currently limited to Potential Reinforcements
a maximum transfer of just over 15 GW. Table B16.1 lists the options of reinforcements
which will improve the B16 boundary capability
to meet the potential increases in transfer
requirements in the period to 2032.
Page 157
3.7 continued
Wider boundaries
Table B16.1:
List of potential reinforcement projects in the B16 boundary
Page 158
Electricity Ten Year Statement
November 2012
Figure B16.2:
Required transfer and capability for boundary B16
25,000
20,000
15,000
MW
10,000
5,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Slow Progression Gone Green Accelerated Growth Contracted Background GG Capability
1 Reinforcement date Table B16.2: Boundary B16 has a high transfer capability which
triggered by prior
requirement from boundary
Selection and timing of reinforcements will sustain the development of new generation in
in the reference name the north of the boundary. The drop in capability
shown on Figure B16.2 in 2015 is due to
Ref SP GG AG CB
generation background changes, shifting power
B6-R01 2015 1
2015 1
2015 1
20151 flow patterns in this area.
B6-R02 20161 20161 20161 20161
The transfer requirements of B16 increase steadily
B7-R01 20141 20141 20141 20141 in the early years due to the expected closure of
B11-R01 – – 20251 – generation south of the boundary. The transfer
requirements then decrease across all three
EC5-R08 – – 2024 1
20201
scenarios and the Contracted Background due to
EC5-R04 – 20251 20211 20181 generation closures in Yorkshire and the Humber
OS Link-02 – 20241 2023 – region and generation development to the south
20251 of the boundary in Wales and the West Midlands.
OS Link-03 – 20291 2026 –
2028
2030
Page 159
3.7 continued
Wider boundaries
Page 160
Electricity Ten Year Statement
November 2012
3.7.20
Boundary B17
Figure B17.1:
Geographical and single line representation of boundary B17
Page 161
3.7 continued
Wider boundaries
Table B17.1:
List of potential reinforcement projects in the B17 boundary
Boundary Discussion and Opportunities including any increase from network changes.
Figure B17.2 below shows the required transfer Table B17.2 identifies the network reinforcements
for Boundary B17 from 2012 to 2032 for the affecting this boundary, and their timing, for
three scenarios and the Contracted Background, each scenario.
as well as the Gone Green boundary capability,
Figure B17.2:
Required transfer and capability for boundary B17
12,000
10,000
8,000
MW
6,000
4,000
2,000
0
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
Page 162
Electricity Ten Year Statement
November 2012
Ref SP GG AG C
B17-R01 2031 2029 2024 2018
B8-R01 – 2022 1
2022 1
20191
B17-R02 2031 2029 2024 2018
Page 163
3.8
Proposed National Grid Network
Development Policy (NDP) process
Page 164
Electricity Ten Year Statement
November 2012
Page 165
3.8 continued
Proposed National Grid Network
Development Policy (NDP) process
Table 3.8.1:
Potential transmission solutions
Page 166
Electricity Ten Year Statement
November 2012
The range of solutions identified will be sufficiently enhancement) will be calculated and recorded for
wide and include both small-scale reinforcements the purposes of the application of the Network
with short lead-times as well as larger-scale Development Policy.
alternative reinforcements which are likely to have
longer lead-times. The NDP does not cover all schemes presented
earlier in this chapter as no immediate decision is
In developing this range of solutions, the required for schemes further than ten years before
Replacement Priority of existing transmission they are required.
assets and alignment with asset replacement
programmes will be considered. If an asset is to The factors shown in Table 3.8.2 on page 168
be replaced in the relevant timescales, then the will be identified for each transmission solution to
marginal cost associated with rating enhancement provide a consistent basis on which to perform
(rather than the full cost of replacement and cost benefit analysis at the next stage.
Page 167
3.8 continued
Proposed National Grid Network
Development Policy (NDP) process
Cost The forecast total cost for delivering the project, split to reflect the pre-
construction and construction phases. The risk of over-/under-spend (for
example, due to uncertainty associated with the levels of undergrounding
required) will also be quantified to improve the consideration of solutions;
a marginally higher mean expected cost may be preferred if the risk of
over-spend is significantly reduced2
The progress of the transmission solution through the development and
delivery process. The stages are as follows:
Scoping Identification of broad need case and
consideration of number of design and
reinforcement options to solve boundary
constraint issues
Pre-construction
It is possible that alternative solutions will be these developments alongside any updates to
identified during each year and that the next known transmission solutions, the scenarios or
iteration of the NDP process will need to consider commercial assumptions.
Page 168
Electricity Ten Year Statement
November 2012
Page 169
3.8 continued
Proposed National Grid Network
Development Policy (NDP) process
Figure 3.8.1:
ELSI inputs, assumptions and outputs
Assumptions:
Physical constraints
Existing network / boundary
capabilities
Forecast constraint prices
Future Energy
Scenarios
Suite of
ELSI transmission
analysis strategies with
lifetime costs
Transmission solutions
(boundary capability
and construction cost)
The full lifetime cost analysis includes forecast Lifetime cost analysis will be undertaken
transmission investment costs, constraint costs against various different transmission strategies
(based on the prices observed in the Balancing (combinations and timings of transmission
Mechanism) and the cost of transmission losses. solutions) until the lowest costs are found for
This analysis is consistent with the recent paper each of the scenarios and sensitivities. The first
by the Joint Regulators Group (JRG) “Discounting stage of this process involves the application
for CBAs involving private investment, but public of engineering judgement to combinations and
benefit”. The cost of transmission reinforcements timings of transmission solutions based on
is annuitised at the post-tax weighted average the capability deficits calculated through the
cost of capital. This is then added to the application of the security standards and the
constraint and losses costs in each year, and the capabilities delivered by each of the transmission
totals are discounted at the Treasury’s social time solutions. The results from this first stage allow
preference rate. finer adjustments in choice and timing to be made
to finalise the selected strategy.
ELSI uses the more detailed energy scenarios to
complete this analysis out to 2030. Then, in order
to estimate full lifetime costs, the values from
2030 are duplicated to give 45 years of data.
Page 170
Electricity Ten Year Statement
November 2012
Page 171
3.8 continued
Proposed National Grid Network
Development Policy (NDP) process
Table 3.8.4:
Example ‘least regret’ analysis
This is illustrated in Table 3.8.4 above, where If the economic implications of these
option 1 is selected as the preferred solution for considerations outweigh the cost of reinforcement
the following year. to meet the security criterion, then investment
in the transmission strategy is required to
The analysis process will be further developed to ensure we continue to build an economic
include an increased number of decision points and efficient network.
(i.e. instead of assuming that all information is
revealed in a year, we will seek to include decision If the cost of reinforcement to meet the security
points further into the future when it is likely that criterion outweighs the economic implications,
more information has been revealed). a derogation will be sought from Ofgem to not
reinforce and diverge from the security standards.
Test selected transmission strategy against
security criterion Stopping or delaying a transmission strategy
Once a transmission solution or strategy has As time progresses, it is possible that a
been selected with a least regret delivery date, transmission strategy selected in a prior year
it is necessary to consider whether this decision will no longer be the least regret option identified
is robust against the security criterion contained in the current year. In this event, the transmission
in the security standards. If the criterion is not strategy will be reviewed in detail to understand
met, we will consider the economic implications the committed cost to date and cost of
of a wider range of issues including (but not cancellation. If the project is so far progressed
limited to): that the cost of cancellation is greater than the
safety and reliability cost to complete (for example, if pre-existing plant
value of lost load and loss of load probability has been removed and scrapped and new plant
(to the extent that this is not already included would be required regardless of the re-forecast
in the ELSI treatment, i.e. ideal curtailment of network benefit), the transmission strategy would
demand and immediate restoration) be allowed to complete.
cost of reduced security on the system
operational cost of constraints to complete
the solution.
Page 172
Electricity Ten Year Statement
November 2012
Figure 3.8.2:
Stopping or delaying a transmission strategy
Otherwise, if the decision is marginal and sensitive In the case of physical reinforcements
to a discrete assumption change, options to slow (construction projects), any committed
or delay completion of the transmission strategy spend on plant will be assessed for possible
and hence reduce potential regret will be sought. re-deployment on other construction projects.
These options can then be considered as part of For example, overhead line conductor (especially
the least regret analysis, and one of these might if it has not been cut to section lengths) can
then become the selected transmission strategy. be diverted to other projects at minimal marginal
cost. This activity will form part of the cost of
If it is clear that a transmission strategy is no cancellation analysis.
longer preferred under all revised scenarios and
that the cost of cancellation is less than the cost
to complete, work would be suspended and
any associated, sanctioned projects would be
deferred or closed.
Page 173
3.8 continued
Proposed National Grid Network
Development Policy (NDP) process
Figure 3.8.3:
Annual timetable
3.8.7 3.8.8
Annual timetable NDP outputs by region
The blocks shown in blue are the elements Following an NDP review of the England and
of the process which are mainly internal to Wales transmission solutions, the following
National Grid. The light purple blocks are external sections show a summary of the initial NDP
publications within which feedback is sought findings by region. In addition, we have included
from stakeholders. As part of the development a fully worked example for the Northern England
of the UK Future Energy Scenarios, there is a region in the Appendices.
stakeholder engagement process.
For all regions, the identification of future
transmission capability requirements is provided
in the earlier sections of this chapter.
Page 174
Electricity Ten Year Statement
November 2012
Page 175
3.8 continued
Proposed National Grid Network
Development Policy (NDP) process
Northern England
Identification of transmission solutions
Page 176
Electricity Ten Year Statement
November 2012
Table 3.8.5:
Northern England transmission solutions
Page 177
3.8 continued
Proposed National Grid Network
Development Policy (NDP) process
Table 3.8.6:
Lowest cost strategies for each scenario
Scenario Strategy
Transmission solution Completion date
Slow Progression Nothing N/A
Gone Green Eastern HVDC Link 1 2019
Mersey Ring 2017
Accelerated Growth Eastern HVDC Link 1 2018
The Gone Green scenario drives higher year- The current-year options that have been
round transfers than the Accelerated Growth considered are:
scenario across boundary B7a between 2018 complete Eastern link pre-construction
and 2024. This means that the Mersey Ring start Mersey ring construction
reinforcement is required under the Gone complete Eastern link pre-construction and
Green scenario, but not the Accelerated start Mersey ring construction
Growth scenario. do nothing.
Page 178
Electricity Ten Year Statement
November 2012
Table 3.8.7:
Northern England reinforcement options and regrets
Outputs
The Eastern link pre-construction is to be taken
forward in 2013/14.
Page 179
3.8 continued
Proposed National Grid Network
Development Policy (NDP) process
Table 3.8.8:
North Wales transmission solutions (Investment options)
Page 180
Electricity Ten Year Statement
November 2012
Table 3.8.9:
Lowest cost strategies for each scenario
Scenario Strategy
Transmission solution Completion date
Slow Progression 2nd Pentir–Trawsfynydd circuit 2021
Gone Green 2nd Pentir–Trawsfynydd circuit 2018
2nd Wylfa–Pentir route 2022
Wylfa-Pembroke HVDC link 2024
Accelerated Growth 2nd Pentir–Trawsfynydd circuit 2018
2nd Wylfa–Pentir route 2021
Wylfa-Pembroke HVDC link 2024
Local Contracted Sensitivity 2nd Pentir–Trawsfynydd circuit 2018
2nd Wylfa–Pentir route 2020
Wylfa–Pembroke HVDC link 2020
No New Generation in region None N/A
Page 181
3.8 continued
Proposed National Grid Network
Development Policy (NDP) process
Table 3.8.10:
Current year options and regrets
Regrets(£m)
The worst regrets for each of the options are The 2nd Wylfa–Pentir project is required for
shown. The preferred option is to progress with 2020 under the local contracted sensitivity and
the 2nd Pentir–Trawsfynydd option for the there is significant lead-time risk for new overhead
current year. lines that require planning consents. Provided
the cost commitment is small, it is therefore
Table NDP.10 shows a number of regrets that are prudent to progress with the development of
very low, for example, the regret associated with the project to ensure that customers are not
committing to Pentir–Trawsfynydd second circuit unduly exposed to the risk of high constraints
against the Slow Progression scenario is only if the customer connections materialise within
£0.6m. This represents three years of financing contracted timescales.
costs for the first year of committed spend on the
project (£9.3m). This spend will occur three years Outputs
earlier than necessary if we choose this option The construction of the 2nd Pentir–Trawsfynydd is
and the Slow Progression scenario outturns. to be taken forward in 2013/14.
Page 182
Electricity Ten Year Statement
November 2012
Page 183
3.8 continued
Proposed National Grid Network
Development Policy (NDP) process
Table 3.8.11:
East Coast transmission solutions
Page 184
Electricity Ten Year Statement
November 2012
Table 3.8.12:
Lowest cost strategies for each scenario
Scenario Strategy
Transmission solution Completion date
Slow Progression Nothing N/A
Gone Green Bramford–Twinstead 2020
Braintree–Rayleigh reconductoring 2020
Rayleigh–Coryton–Tilbury reconductoring 2020
Walpole QBs 2021
Accelerated Growth Bramford–Twinstead 2021
Braintree–Rayleigh reconductoring 2021
Elstree–Waltham Cross–Tilbury 275 to 400kV 2022
upgrade
Rayleigh–Coryton–Tilbury reconductoring 2018
Walpole QBs 2021
Kemsley–Littlebrook–Rowdown 2022
Tilbury–Kingsnorth–Northfleet East reconductoring 2022
Local Contracted Sensitivity Bramford–Twinstead 2018
Braintree–Rayleigh reconductoring 2018
Elstree–Waltham Cross–Tilbury 275 to 400kV 2019
upgrade
Rayleigh–Coryton–Tilbury reconductoring 2018
Walpole QBs 2018
Kemsley–Littlebrook–Rowdown 2020
Tilbury–Kingsnorth–Northfleet East reconductoring 2020
No New Generation Nothing N/A
Sensitivity
Page 185
3.8 continued
Proposed National Grid Network
Development Policy (NDP) process
Development of current year options year to achieve the minimum cost strategy for the
The table on page 185 shows that the minimum local contracted sensitivity.
cost strategies for each of the scenarios are
different, and therefore there is a risk of regret. The current-year options that have been
considered are:
The lowest cost strategy for Slow Progression commit to a further one year spend for
is to do nothing further in the area. The lowest Bramford–Twinstead (delivery 2018)
cost strategy for the local contracted sensitivity commit to a further one year spend for Elstree–
requires both the Bramford–Twinstead and the Waltham Cross–Tilbury (delivery 2019)
Elstree–Waltham Cross–Tilbury 275 to 400kV commit to a further one year spend for
upgrade to be considered in the current year. Bramford–Twinstead (2018) and Elstree–
Waltham Cross–Tilbury (2019)
The pre-construction element of the Bramford– do nothing further.
Twinstead and the Elstree–Waltham
Cross–Tilbury 275 to 400kV upgrade projects Selection of preferred option
has already been completed. The construction The options and regrets against each of the
elements have a lead-time of six and seven years scenarios and sensitivities are shown in Table
respectively and therefore have to be initiated this 3.8.13 below.
Table 3.8.13:
East Coast reinforcement options and regrets
Page 186
Electricity Ten Year Statement
November 2012
Outputs
Further spend on the Bramford–Twinstead project
will be committed in 2013/14.
Page 187
3.8 continued
Proposed National Grid Network
Development Policy (NDP) process
Table 3.8.14:
South West and South Coast transmission solutions
Page 188
Electricity Ten Year Statement
November 2012
Table 3.8.15:
Lowest cost strategies for each scenario
Scenario Strategy
Transmission solution Completion date
Slow Progression Hinkley Point–Seabank 2026
Reactive compensation at Canterbury substation 2021
Gone Green Hinkley Point–Seabank 2021
Reactive compensation at Canterbury substation 2020
Dungeness–Sellindge–Canterbury reconductoring 2021
Accelerated Growth Hinkley Point–Seabank 2020
Reactive compensation at Canterbury substation 2020
Dungeness–Sellindge–Canterbury reconductoring 2021
Local Contracted Sensitivity Hinkley Point–Seabank 2019
Reactive compensation at Canterbury substation 2019
Dungeness–Sellindge–Canterbury reconductoring 2019
No New Generation None N/A
Sensitivity
Selection of transmission The South Coast MSCs and SVCs are needed
solution and timing in all scenarios between 2019 and 2021. Due to
Calculation of operational costs optimisation and alignment of works, these MSCs
for transmission solutions are due to be delivered in stages up to 2019. The
Cost benefit analysis was completed with various decision will be reviewed annually and the best
different strategies (combinations and timings of economic balance sought after considering the
transmission solutions) until the lowest cost was outage alignment and year of requirement.
found for each of the scenarios.
Page 189
3.8 continued
Proposed National Grid Network
Development Policy (NDP) process
Development of current year options For the South West, the current-year options that
The table on page 189 shows that the minimum have been considered are:
cost strategies for each of the scenarios are commit to the next year of spend for Hinkley
different, and therefore there is a risk of regret. Point–Seabank for delivery by 2019
progress with pre-construction for Bramley–
The pre-construction element of the Dungeness– Melksham for delivery in 2018
Sellindge–Canterbury project has already been commit to the next year of spend for
completed. The construction element has a lead- Hinkley Point–Seabank and progress with
time of four years, and the earliest date this is pre-construction for Bramley–Melksham for
required for any scenario is 2019/20. The scheme delivery in 2018
can therefore be delayed with no regret. do nothing.
Table 3.8.16:
Current year options and regrets
Page 190
Electricity Ten Year Statement
November 2012
Outputs
The Hinkley Point–Seabank project is to be taken
forward in 2013/14.
Page 191
3.8 continued
Proposed National Grid Network
Development Policy (NDP) process
London
Identification of transmission solutions
Table 3.8.17:
London transmission solutions
Page 192
Electricity Ten Year Statement
November 2012
Table 3.8.18:
Lowest cost strategies for each scenario
Scenario Strategy
Transmission solution Completion date
Slow Progression Hack–Tott–Walx 275 to 400kV upgrade 2017
Sundon–Cowley and Elstree Turn-in 2021
Gone Green Hack–Tott–Walx 275 to 400kV upgrade 2017
Sundon–Cowley and Elstree Turn-in 2019
Accelerated Growth Hack–Tott–Walx 275 to 400kV upgrade 2017
Sundon–Cowley and Elstree Turn-in 2019
Page 193
3.9
Development consents
The illustrative transmission systems contained The Act sets out mandatory pre-application 1 www.legislation.gov.uk/
ukpga/2008/29/contents
in this document do not consider specific procedures which includes notification, 2 www.communities.gov.
requirements for consent or planning permission. consultation and publicity requirements. NGET uk/localgovernment/
decentralisation/localismbill/
However, such planning permissions will be a is committed to meeting and if appropriate www.services.parliament.uk/
key factor in the actual physical development exceeding the requirements of the Planning Act bills/2010-11/localism.html
3 www.infrastructure.
of NETS. The following section provides a high 2008. NGET will engage and consult affected independent.gov.uk/
level overview of the key aspects of the planning parties in the development of its projects, legislation-and-advice/
national-policy-statements/
process which will be applicable for connecting an demonstrating how local communities’ and 4 www.nationalgrid.com/
offshore generation projects to the NETS. other stakeholders’ views have been taken into NR/rdonlyres/21448661-
909B-428D-86F0-
consideration. Our commitments in this regard 2C4B9554C30E/39991/
are described in more detail in our Stakeholder SCADocument6_2_
Final_24_2_13.pdf
Community & Amenity Policy4 which also outlines
3.9.1. how we seek to meet our statutory responsibilities
5 www.nationalgrid.com/uk/
LandandDevelopment/SC/
Page 194
Electricity Ten Year Statement
November 2012
1 www.legislation.gov.uk/
ukpga/2009/23/contents 3.9.2. Marine Licensing
The new legislation introduced changes to the
Marine Planning
2 www.defra.gov.uk/
environment/marine/ system for marine consenting and licensing
protect/planning/
3 www.archive.defra.gov. and has moved from a system where multiple
uk/environment/marine/ The Marine and Coastal Access Act 20091 and consents were required under multiple Acts to
documents/ourseas-
2009update.pdf
the Marine (Scotland) Act 20108 establishes a more streamlined approach where a single
4 www.marinemanagement. the legislative basis for the marine planning ‘marine licence’ is required.8
org.uk
5 www.scotland.gov.uk/
and licensing process in the UK. The Acts aim
About/People/Directorates/ to provide an integrated approach that brings In the past multiple licensing regimes and
marinescotland
6 http://wales.gov.
together marine management decisions and authorities regulated marine development, and
uk/?lang=en allows for joined-up decision making. The new included consent under the Coast Protection
7 www.doeni.gov.uk
8 www.marinemanagement.
marine planning framework and marine licensing Act 19499 (CPA consent) and a licence under
org.uk/licensing/index.htm system came into force in April 2011. the Food and Environment Protection Act 198510
9 www.legislation.gov.uk/
ukpga/Geo6/12-13-14/74 (FEPA licence).
10 www.legislation.gov.uk/
Marine Planning
ukpga/1985/48
11 www.legislation.gov.uk/
An overarching UK Marine Policy Statement Since April 2011 the requirements contained in
ukpga/2009/23/contents (March 2011)2 provides a framework for preparing CPA consents and FEPA licences have been
12 www.communities.
gov.uk/publications/
marine plans and taking decisions affecting the brought together into a single marine licence
planningandbuilding/ marine environment. The Marine Policy Statement for which the MMO, Welsh Government,
dcosimpactassessment
supports the UK’s high level marine objectives3 Marine Scotland and the Department of the
and will be implemented through marine plans in Environment for Northern Ireland act as licensing
England, Scotland, Wales and Northern Ireland. authorities. These bodies determine marine
licence applications for offshore generation
For marine planning purposes UK waters will be development projects. In England and Wales the
divided into ‘inshore’ regions (0–12 nautical miles Planning Inspectorate will determine applications
from the shore) and ‘offshore’ regions (12–200 for offshore generation development projects
nautical miles from the shore). Marine plans will greater than 100 MW in size. Any associated
be developed for each marine region. Plans are infrastructure including cabling, collector stations
anticipated to have a life of approximately 20 and converter stations would required consent
years and will be kept under regular review during under the Marine and Coastal Access Act
their lifetime. 200911 but the developer may choose for this
to be consented by the Planning Inspectorate
The Marine Management Organisation (MMO)4, as ‘associated development’ and a marine
Marine Scotland5 Welsh Government6 and the licence will be issued as part of the Development
Department of the Environment for Northern Consent Order (DCO)12 in consultation with
Ireland7 are responsible for the marine planning the marine bodies.
systems in their authority areas.
Table 3.9.1 provides an indicative timeline for
the offshore planning process for an offshore
generation (larger than 100 MW of installed
generation capacity) project connecting to
the electricity network.
Page 195
3.9 continued
Development consents
Table 3.9.1:
Indicative timeline for the offshore planning process for offshore generation (greater than 100
MW of installed generation capacity) Connecting to or using the National Electricity Transmission
System in Great Britain
Page 196
Electricity Ten Year Statement
November 2012
3.10
Technologies
Table 3.10.1:
HVDC technology advancements
1 www.nationalgrid.com The relevant transmission technologies, outlined in April 2011.1 Although voltage/power ratings
/NR/rdonlyres/
444EB282-E38C-41DE-
in Appendix E, have been further reviewed in are in excess of those presently installed, these
8282-6F83F93C17D0/ consultation with the main European manufacture are achievable through incremental development
46591/ODISTechnology
Workshop13thApril2011
suppliers. The reviewed technology including the rather than requiring a fundamental step change.
_FinalVersion.pdf advancements below has been applied when
developing the suggest transmission changes. Series reactive compensation is now firmly in the
development phase for insertion in Anglo-Scottish
Technology Advancements circuits. This will be the first deployment of
The ongoing development of HVDC equipment capacitive series compensation on the NETS.
technologies, such as subsea cables and
converter stations, means that energy transfer A new 400KV transmission pylon design is
capability is continuously improving. For example, being developed by National Grid and Danish
it is now feasible to develop an offshore converter architects Brystrup following a successful design
station with a capacity in the region of 1000 MW. competition. The new design aims to help satisfy
Within the next few years it is anticipated that the future engineering needs whilst being aesthetically
technology will have progressed to the extent that pleasing and environmentally friendly. A preferred
2000 MW capacity is achievable, as outlined in T-pylon design is currently being prepared ready
Table 3.10.1. for a prototype to be produced and tested. It is
hoped that the T-pylon design will be ready for
In principle, there are no anticipated technical deployment within the next four to five years.
barriers to deploying the proposed connection
designs as discussed and agreed at the
Technology Workshop, facilitated by NGET,
Page 197
3.11
Potential Development of
Integrated Offshore Network
Dogger Bank Zone the EC3 or EC1 region, however, whatever option
OffshoreTransmission/
OffshoreApproach/
Page 198
Electricity Ten Year Statement
November 2012
developed incrementally alongside the generators, Both of these Round 3 generating zones are
thus minimising redundancy risk, whilst facilitating close to the coast line and the indicative capacity
future development. for each zone is small enough that the use of
AC technology is expected to be the most cost
effective solution to connect the offshore zones to
the onshore network, with connections to existing
3.11.4 substations likely to be the most straightforward.
East Anglia Zone The low level of existing generation in the area
coupled with local demand requirements results
The Round 3 East Anglia Zone as seen in Figure in smaller impacts on load flows and only minor
2.13 has the potential for 7.2 GW of offshore wind local reinforcements are expected to be required
generation capacity. Connection contracts are in to facilitate these connections. Due to the large
place for the full 7.2 GW with staged connection geographic split of the two offshore zones and the
dates from 2016 to 2021 to connection points pattern of predicted network flows on the south
within East Anglia. The connection points are coast circuits, it is unlikely that any offshore links
contained within the EC5 and EC6 boundaries between zones will be cost effective options to
with the transmission requirements shown in meet network reinforcement requirements.
Figures EC5.2 and EC6.2. By offshore co-
ordination within the East Anglia offshore zone Although, there are offshore contracted
increased supply security will be attainable. With a connections from outside the zone which are
co-ordinated connection with Hornsea or Dogger due to connect in a similar region onshore, these
Bank additional boundary capability will be further connections will use DC technologies due
provided across the B8 and B9 boundaries. to distance from the coast line and it is unlikely
The offshore zone could also be considered that integrating with the other zones will be
for co-ordination with Belgium or Netherlands economic as it will require combining AC and
projects to provide additional interconnection DC technologies.
capacity between the countries.
3.11.6
3.11.5 Bristol Channel Zone
South Coast Zone
Figure 2.13 highlights a single Round 3 zone in
Figure 2.13 shows two Round 3 zones off the the Bristol Channel area, Atlantic Array, and there
south coast and south-west peninsula of England, is potential for some 1.5 GW of offshore wind
Rampion just south of Brighton and Navitus Bay generation in total from this zone.
to the south-west of the Isle of Wight, and there
is potential for some 1.5–1.9 GW of offshore wind This Round 3 generating zones is close to the
generation in total from these two zones. As the coast line and the indicative capacity for the zone
affected boundaries B10 and SC1 are generally is small enough that the use of AC technology is
net importers, it is anticipated that this generation expected to be the most cost effective solution
can be accommodated within the zone as the to connect the offshore zones to the onshore
generation will tend to balance the local demand. network. Although the furthest extent of the
Page 199
3.11 continued
Potential Development of
Integrated Offshore Network
zone may be close to the limit of a practical The majority of this zone is within 50 km of the
AC circuit connection, the collector network shore of Anglesey so the use of AC technology
within the zone is unlikely to be such that DC is considered appropriate for these near shore
technologies will be necessary. Potential onshore parts. The northern parts can be over 60 km
connection points cover both the South Wales from the shore, reaching the practical limit of AC
peninsula and the south-west coast. Examining cabling, and would most likely require and HVDC
boundary requirements for B12 and B13 reveals connection. This northern section is comparatively
that connection to the south-west coast is as close to the Lancashire coast as the North
preferable as B13 is generally a net importer and Wales coast so it is a practical proposition to
the generation will help to balance local demand connect to a substation in Lancashire in order
with a beneficial effect on the required boundary to separate the zone across different onshore
capacity. The South Wales coastal circuits near connection points to help distribute the power
Cardiff and Swansea are predominantly 275kV infeed from the wind generation reducing
and provide little support for additional generation the loading impact at the connection sites.
without replacement or upgrading to 400kV. Consideration of the transfer requirements for
Adding additional generation to these circuits the North Wales boundaries NW1, NW2, NW3
will increase the B12 transfer requirement. and NW4 also reveals that alternative connection
points away from Anglesey help to reduce
There is an opportunity to integrate this zone with pressure on these boundaries and mitigate the
potential generation proposed in Irish territories immediate need for onshore reinforcement.
(onshore and offshore). Such connections would
inevitably require DC technologies due to the An integrated design with additional
distances involved, the capacities will be such interconnections within the zone could give
that there will be little headroom for integration additional benefits by reducing the number
and the programmes are not expected to align. of connections to shore and providing circuit
The possibility of a tidal barrage exists in this area, diversity to the offshore generation. Further it
of anticipated capacity 5–10 GW, depending on will introduce some additional transfer capability
exact location. Should such a barrage project across the B7a boundary, either mitigating
proceed it is likely that extensive reinforcement or deferring the need for additional onshore
and upgrade would be required to both the north reinforcements. The use of HVDC technology
and south of the channel. This possibility has only within this boundary link will allow greater control
been considered at a high level to date. of power flows which will provide increased ability
to take power from the North Wales area which is
traditionally a region of high generation export.
3.11.7 There is currently great interest in connecting
Irish Sea Zone significant levels of wind generation from outside
the zone, either from Irish territorial waters or
There is a single Round 3 zone in the Irish Sea from the Irish mainland itself. The distances
area, off the north coast of Wales, from which involved will require the use of HVDC technology
there is potential for some 4.2 GW of offshore and the indicative capacities will require multiple
wind generation in total. links to the onshore network, most likely to
Page 200
Electricity Ten Year Statement
November 2012
North Wales, South Wales and possibly beyond. the opportunity for within zone interconnection
There are a range of potential network design in order to offset the number of offshore to
solutions, depending on the rate of growth onshore links, with selected oversizing of some
and timing of the generation. A co-ordinated of these links when compared to the likely radial
solution will allow incremental development, thus alternative design.
minimising redundancy risk whilst facilitating
future development which can be incorporated For the Firth of Forth zone it is proposed to
as further offshore generation is developed. investigate additional connections offshore to
Further, by integrating at the source of these links the network in the north-east of England. For the
outside the zone, it is expected that network Moray Firth zone, additional interconnection in
transfer benefits can be achieved having the this manner will bridge the northernmost section
benefit of mitigating the onshore reinforcements of the network and provide an efficient method of
that would be required if each connection point connecting the links to the more remote Orkney
were analysed in isolation. The network solution and Shetland developments. It is expected that
will continue to be explored as the interest and these arrangements will mitigate an extensive
opportunity for such connections increases upgrade or reinforcement of significant parts of
alongside the evolving commercial and the Scottish network and the Scotland to England
regulatory clarity. onshore circuits.
Page 201
3.12
European interconnection
Increased interconnectivity between European c. NSN (2018) – 1400 MW interconnector 1 A wholly owned subsidiary
of National Grid Plc.
Member States will play an essential role in between Norway and GB jointly owned
facilitating competition by developing the by NGIL and the Norwegian transmission
European electricity market and the transition company Statnett
to a low carbon electricity sector by efficiently d. Northconnect (2021) – 1400 MW
integrating various types of renewable generation, interconnector between Norway and GB
particularly offshore wind. jointly owned by five partners: Agder Energi,
E-CO, Lyse, Scottish and Southern Energy
Current and planned interconnection and Vattenfall AB
1. There are four existing interconnectors
between GB and other markets: 3. There are further projects which have applied
a. IFA (1986) – 2000 MW interconnector for PCI status (projects of common interest)
between France and GB jointly owned by under the Commission’s energy infrastructure
National Grid Interconnector Limited (NGIL)1 package, and other projects that are already
and the French transmission company in the public domain. These are set out in the
Réseau de Transport d’Electricité (RTE) table below, but we recognise that there may
b. M oyle (2002) – 450 MW interconnector be others of which we are currently not aware,
from Scotland to Northern Ireland, 80 MW so this list is not exhaustive
into Scotland owned by Northern Ireland
Energy Holdings and operated by the 4. Ofgem are currently developing a new
System Operator for Northern Ireland (SONI) regulatory regime for interconnectors and
c. B ritNed (2011) – 1000 MW interconnector we welcome applications from both these
between the Netherlands and GB jointly ‘cap and floor’ regulated and exempt third
owned by NGIL and the Dutch transmission party projects.
company TenneT
d. E WIC (2012) – 500 MW interconnector from
Ireland to GB owned by the Irish System
Operator, EirGrid
Page 202
Electricity Ten Year Statement
November 2012
Table 3.12.1
Page 203
3.13
Areas of future interest
Figure 3.13.1:
Potential areas for new boundaries (note the boundaries drawn are indicative of the areas
of interest and further work will be required to refine their exact shape)
Page 204
Electricity Ten Year Statement
November 2012
The boundaries currently assessed reflect In the South East of England, the volume of
previously identified areas of the transmission proposed interconnection to continental Europe
system likely to be stressed in the future. will present challenges in terms of the high
Assumptions around future generation and potential variability of flows through this region
demand patterns continue to evolve and as such from fully exporting, fully importing and cross
the potential effects on the transmission system European transfers. Some of these stresses have
will also change. Therefore the boundaries studied been identified already as they affect B14 as
are continually subject to review. There are shown in the B14(e) sensitivity discussion, but
currently two additional areas of the transmission there could also be effects outside of London.
system identified that are potentially areas of high
stress in the future. Interest has been expressed These areas are identified on Figure 3.13.1.
for additional new connections in South Wales The boundaries drawn are indicative of the regions
which will require some further analysis to of interest, and do not represent actual proposals
investigate together with the interactions with for boundaries. Further work to refine the circuits
North Wales and the South West Peninsula. of interest will be undertaken, and if necessary,
additional boundaries will be considered in the
2013 ETYS.
Page 205
Chapter four
System operation
Electricity Ten Year Statement
November 2012
4.1
Introduction
Page 207
4.1 continued
Introduction
We have consulted extensively with stakeholders important challenge is the increase in the number 1 Operating the Electricity
Networks in 2020
to identify how the design and operation of the of embedded generators which impact on the www.nationalgrid.com/
electricity transmission system will develop (e.g. transmission demand profile (both minimum and NR/rdonlyres/DF928C19-
9210-4629-AB78-
Operating the Network in 2020 consultations1, maximum demand), flows on the transmission BBAA7AD8B89D/
RIIO ‘Talking Networks’ consultations and system and system performance issues such as 47178/Operatingin2020_
finalversion0806_final.pdf
engagement). Our focus has been on enabling an voltage, fault level and inertia. Potential increases 2 The contracted
orderly transition that facilitates the achievement in the penetration of electric vehicles, electricity background is not
analysed in this section as
of climate change targets, and provides a solid storage and a range of demand side management we are considering system
foundation for the further change required in the programmes may also change the demand profile issues rather than local
connection issues.
period out to 2050. and impact on system operation.
The key change to the network is the transition These challenges are likely to be at their most
from a generation mix dominated by fossil extreme during periods of high wind generation
fuel synchronous generation, to a generation output and low demand, as the level of installed
mix which includes far more low carbon and wind capacity on the system may be even higher
intermittent asynchronous generation and than the demand during low demand periods. The
interconnectors. The level of change in the graphs below show the level of wind production at
generation capacity mix is dependent on a 70% of installed capacity in spot years out to 2030
number of factors which are covered by our range compared with summer minimum demand levels,
of scenarios described in Chapter 22. Another in the three main scenarios.
Figure 4.1.1:
Slow progression wind production
25,000
20,000
15,000
MW
10,000
5,000
0
2017/18 2020/21 2023/24 2027/28 2030/31
Page 208
Electricity Ten Year Statement
November 2012
Figure 4.1.2:
Gone green wind production
30,000
25,000
20,000
15,000
MW
10,000
5,000
0
2017/18 2020/21 2023/24 2027/28 2030/31
Figure 4.1.3:
Accelerated growth wind production
35,000
30,000
25,000
20,000
MW
15,000
10,000
5,000
0
2017/18 2020/21 2023/24 2027/28 2030/31
Page 209
4.1 continued
Introduction
In Slow Progression the level of wind output is The next section discusses the issues and
likely to be below the minimum level of demand. challenges for the operation of the system in
In Gone Green and Accelerated Growth there are the context of the different scenarios. Various
occasions beyond 2020 when the level of wind technical issues are described and analysed in
output may exceed the minimum level of demand. detail. In the final section some potential mitigating
With an assumption that nuclear power provides measures are considered. The aim is to ensure
a level of ‘baseload’ generation, then occasions the system is operated in the most secure and
when the power output of wind and nuclear efficient way whilst maximising the use of the
in combination may exceed the minimum demand network capacity under a range of scenarios.
may occur earlier than identified above, and The chapter concludes by identifying what
more frequently. opportunities exist to assist in meeting these
challenges.
This outlines one of the key potential challenges
facing us and in addition there are a number of Despite the challenges that the changes to the
other issues considered over the course of this network will present, we have identified a range
chapter. These are generally common issues that of potential solutions on how we will need to
are applicable to all three scenarios. This chapter adapt the way we operate to ensure continued
discusses these issues in detail and highlights the successful management of the power system.
resulting impact on the network:
system inertia and fault level changes The issues and challenges briefly described above
voltage and Reactive Power management will be discussed throughout this chapter under
intermittent generation and interconnector the following headings:
volatility requiring additional reserves and system operability
causing power flow volatility both in magnitude system design and operating challenges; and
and direction opportunities.
high wind speed shut down.
Page 210
Electricity Ten Year Statement
November 2012
4.2
System operability
Figure 4.2.1:
Classification of power system stability
Our principal role as system operator is to networks and have also been the foundation
maintain a safe, secure, compliant, and economic for our National Electricity Transmission System
system. This section discusses the technical Operator (NETSO) policies.
aspects of system operability and the impact of
each element on the operation of the system. The National Electricity Transmission System
Security and Quality of Supply Standard (NETS
In the context of security of supply, maintaining SQSS) accounts for all aspects of system stability,
a stable power system is the main focus. The at the design and operation stage, by specifying
importance of the stability of a power system is to the system performance requirements. These
ensure the ability of the system to remain operable stability challenges are very familiar to us.
and synchronised during various disturbances (e.g. For instance, as an island power system with
loss of generation, loss of circuit after a fault in the no AC link to other large power systems, it
transmission line). For power systems worldwide, is important to maintain a balance between
traditionally dominated by large central generators, frequency stability, the size of the largest potential
this varied power system stability task has been loss of infeed to the system, the costs of de-
classified into segments described in Figure 4.2.1. loading plant, and providing frequency control
services. The connection between the generators
The figure above illustrates the day-to-day stability in England and Wales and those in Scotland
challenges applicable to almost any large power requires appropriate Power System Stabiliser
system. The three main classes consist of rotor (PSS) at these stations and possibly Power
angle, frequency, and voltage stability. These have Oscillation Damping (POD) facilities in future
been the focus in designing appropriately robust HVDC interconnectors.
Page 211
4.2 continued
System operability
Page 212
Electricity Ten Year Statement
November 2012
4.3
System design and
operation challenges
Figure 4.3.1:
System frequency limits and concept of RoCoF
50.2
50
49.8
Rate of Change of Frequency (RoCoF=df/dt)
Frequency (Hz)
49.6
49.2
Infrequent Infeed Loss Limit (49.2 Hz)
49
48.8
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49
Time (s)
Inertia and Rate of Change of System inertia will reduce as a result of increasing
Frequency (RoCoF) the penetration of asynchronous generators which
A synchronous generating unit (mainly large steam have no or very little natural inertia compared to
or gas turbine generating plant) operating in the large synchronous generators (due to the absence
electrical power system will deliver its stored of a large rotating mass in the generator). Under
energy (in the rotating mass of the shaft of the all three scenarios, the reduction in system inertia
turbine) to the system on falling system frequency. is visible. The degree of reduction is dependent on
This inertia response will help to slow down the how much asynchronous plant is connected, and
initial fast drop of the system frequency and hence the generation output of this plant, which in turn
a reduction of “Rate of Change of Frequency determines how much synchronous plant is left
(RoCoF)” and is measured in Hertz per second running at any time.
(Hz/s). Interconnectors and converter interfaced
generating plant
Page 213
4.3 continued
System design and
operation challenges
Reduction of system inertia may have two effects b. The impact on statutory frequency limit: Apart
on the frequency management: from the rapid change in the frequency, there
is also a risk that the statutory frequency
a. The impact on the Rate of Change of limit is violated. The restoration of balance
Frequency (RoCoF): After a loss of generation, between supply and demand through the
the frequency will start to drop rapidly. With current primary response sources may take
falling inertia the RoCoF increases. This may a few seconds, and hence the frequency can
pose a challenge for a system operator as fall significantly before the primary response
embedded generators may also trip if RoCoF arrests the fall.
exceeds the setting of the Loss of Mains
(LOM) protection which utilises the RoCoF. The following charts show the change in total
LOM is used to protect against the risks of the system inertia (calculated in GVA.s) for the
generator continuing to run as part of a non- scenarios, at different years and during low
viable isolated system. demand periods:
Figure 4.3.2:
System inertia changes for Slow Progression at 70% wind power output (H= System Inertia)
300
250
200
250-300
H(GVAs )
150
200-250
100
150-200
50
100-150
0
50-100
2012-2013
2014-2015
2016-2017
0-50
Year
2018-2019
2020-2021
2022-2023
De m and
2024-2025
30GW
2026-2027
28GW
26GW
2028-2029
24GW
22GW
2030-2031
20GW
Page 214
Electricity Ten Year Statement
November 2012
Figure 4.3.3:
System inertia changes for Gone Green at 70% wind power output (H= System Inertia)
300
250
200
250-300
H(GVAs )
150
200-250
100
150-200
50
100-150
0 50-100
2012-2013
2014-2015
0-50
2016-2017
2018-2019
Year
2020-2021
2022-2023
De m and
2024-2025
30GW
2026-2027
28GW
26GW
2028-2029
24GW
2030-2031
22GW
20GW
Figure 4.3.4:
System inertia changes for Accelerated Growth at 70% wind power output (H= System Inertia)
300
250
200
250-300
H(GVAs )
150 200-250
100 150-200
50 100-150
0 50-100
2012-2013
2014-2015
0-50
2016-2017
2018-2019
Year
2020-2021
2022-2023
De m and
2024-2025
30GW
2026-2027
28GW
26GW
2028-2029
24GW
22GW
2030-2031 20GW
Page 215
4.3 continued
System design and
operation challenges
In the early years, the three scenarios have a very Methods that address the issues identified
similar generation capacity mix and as a result above include:
the overall system inertia is almost the same, but
varies slightly due to demand differences. With Low Load Operation of Synchronous
respect to system inertia the deviations in the Generators – Synchronous generators
scenarios are significant post-2020. connected to the system but at low load operation
mode may still provide inertia to the system. This
The impact of the low overall system inertia is a is usually not an optimal operating point for the
substantially higher risk in frequency management generators in terms of unit cost (£/MWh), but may
unless mitigating actions are taken. Wind and still be required for securely operating the system
PV generally contribute little or no inertia of their in the absence of other more feasible solutions.
own and this can become critical during low
demand conditions (summer minimum demand Fast Frequency Response – System inertia
scenario). Considering the rate of installation is provided by the rotating mass of directly
of deeply embedded solar PV (1 GW has been connected generators (i.e. not decoupled through
installed during 2011), the minimum demand power electronics such as solar PV and some
seen at the transmission level may reduce even wind turbines). The initial RoCoF depends on
more. This means, the number of hours that the the size of infeed loss (causing a mismatch
system inertia may be low will increase, and this between generation and demand), and the level
may expose the system to more risk in terms of of system inertia.
frequency management.
Alternative solutions to manage the initial RoCoF
Potential Mitigating Measures issue may include providing additional inertia
There are two key challenges with regard to from new technologies such as flywheels.
frequency management. One is to control the However, this technology is still at a very early
RoCoF, and the other is to limit the frequency stage of development. The alternative to having
deviation after a loss of infeed. It is important mechanical inertia to manage RoCoF issue would
that the measures proposed are economic and be to provide fast acting power injection (typically
support the move towards the environmental within 200ms), or the use of demand side
targets, therefore, limiting the largest infeed to a response to mitigate the demand / generation
lower value, or constraining the generators to limit imbalance. Therefore, the concepts Fast
RoCoF are not the most economic options . Frequency Response, and/or synthetic inertia in
the context of frequency management have been
introduced which may be provided from:
Page 216
Electricity Ten Year Statement
November 2012
The fault level of a system provides a good The fault level results presented in this section
indication of the strength of the network which are estimated for the spot years 2012, 2017
in turn, reflects on its ability to remain stable and 2022 and are based on the generation mix
following disturbances. A system with a high in each of the different scenarios.
fault level is therefore less prone to instabilities
and power quality issues (such as large voltage A demand of approximately 30 GW,
steps, flicker and harmonics) when compared corresponding to a modest summer demand
to a weaker system having a lower fault level. level, was used to despatch the required level of
generation under the assumption that the output
It is desirable that fault levels are not excessively from renewable plants (wind and wave) was
high from a protection and asset life perspective scaled to 70% of their capacities. The assessment
but at the same time are not too low from a has considered different regional areas, rather
system strength point of view. Therefore the than a specific busbar on the network to better
right balance in fault levels needs to exist to show the trend in fault level reduction. The results
ensure that both the asset life and system shown in this section illustrate the percentage
strength are not compromised. changes in fault level from the 2012 base case.
Page 217
4.3 continued
System design and
operation challenges
Figure 4.3.5:
Fault level variation for the Slow Progression Scenario (covering the lower range of demand)
100%
75%
% Difference from 2012 levels
50%
25%
2012
Level
-25%
-50%
-75%
-100%
South North North East Northern Wales SW London SE Midlands
Scotland Scotland England England England England
2012 2017 2022
The chart above illustrates the trend in fault units, there may be an improvement in network
levels from 2012 to 2022 under the Slow strength in the Midlands region and the South
Progression scenario. East region. For the northern and southern parts
of Scotland, there is a slight increase in fault levels
By the year 2017, the study shows that in the due to small increase in synchronous generation
North and South of Scotland regions, Wales and in northern Scotland.
South West region, and North East of England
region, there is a small reduction in the minimum By the year 2022, for the North East of England,
fault level. This is due to the replacement of Midlands and South East regions, the fault
synchronous generators by asynchronous levels remain almost constant as the levels of
generators which have less contribution during synchronous generation do not change between
faults. The reduction in network strength for the 2017 and 2022. The substantial drop in the Wales
Northern region of England is more pronounced and South West region is due to the replacement
(25% reduction). This is mainly due to the of about 3 GW of synchronous generation in this
synchronous generators in the North being region by asynchronous generation spread across
replaced in the merit dispatch order by new CCGT the system.
units in other regions. Due to these new CCGT
Page 218
Electricity Ten Year Statement
November 2012
Figure 4.3.6:
Fault level variation for the Gone Green Scenario (covering the lower range of demand)
100%
75%
% Difference from 2012 levels
50%
25%
2012
Level
-25%
-50%
-75%
-100%
South North North East Northern Wales SW London SE Midlands
Scotland Scotland England England England England
2012 2017 2022
The chart above illustrates the trend in fault of England. This reduction in impedance along
levels from 2012 to 2022 under the Gone with the increase in synchronous generation in
Green scenario. the North East of England causes a greater fault
in-feed, therefore explaining the slight rise in fault
The study shows that for the Scottish regions levels in the Scottish areas. In Northern England,
and the North East of England region, there Wales and the Midlands, the drop in fault levels
is an increase in fault levels of about 2% and is due to a large amount of synchronous
17% respectively. For the latter area, the higher generation falling outside the merit dispatch
fault levels are mainly due to an increase in order due to an increase in the penetration of
synchronous generation. asynchronous plants.
Although there is a small reduction of By the year 2022, about 60% of synchronous
synchronous generation in Scotland from 2012 generation would be preceded by asynchronous
to 2017 (about 125 MW), the fault levels increase plants in the merit order when compared to the
because of network changes such as the effect of 2017 levels. The largest reduction in synchronous
series compensation. In the network model used, generation occurs in the Wales and South West
the reinforcements essentially reduce the electrical and South East regions. This explains the drastic
distance between Scotland and the North East decrease in fault levels in these regions.
Page 219
4.3 continued
System design and
operation challenges
Figure 4.3.7:
Fault level variation for the Accelerated Growth Scenario (covering the lower range of demand)
100%
75%
% Difference from 2012 levels
50%
25%
2012
Level
-25%
-50%
-75%
-100%
South North North East Northern Wales SW London SE Midlands
Scotland Scotland England England England England
2012 2017 2022
The chart above illustrates the trend in fault from their 2017 values. This is because the
levels from 2012 to 2022 under the Accelerated level of synchronous generation is expected to
Growth scenario. drop by about 70% to prioritise generation from
asynchronous sources.
The trend in the 2017 fault levels in the
Accelerated Growth scenario is very similar to that The connection of new nuclear units compensates
in the Gone Green scenario with the exception for the other synchronous generators which
of the Wales and South West region and the become out of merit in the Wales and South
Midlands region. Under the Accelerated Growth West area. For a 30 GW level of demand, new
scenario, the level of synchronous generation nuclear units are dispatched in the merit order and
drops at a faster rate in Wales and South West therefore cause the fault level to rise in the Wales
thereby causing a more prominent reduction in fault and South West region.
levels. when compared to the Gone Green scenario.
The results demonstrate that there is a direct link
With the exception of Wales and South West between the level of synchronous generation and
in 2022, all areas face a reduction in fault levels the fault levels on the system.
Page 220
Electricity Ten Year Statement
November 2012
There are other factors which will affect the High volt situations under low demand conditions
minimum fault level in a region of the system and are now increasing due to several factors including:
as a result, the findings presented in this section development of underground cables in the
can only be used as a guideline to reflect the distribution and transmission grid
general trend expected in minimum fault levels. lack of generation support in specific
The results also represent a snapshot of how areas; and
fault levels may vary on the basis of a 30 GW reduction in reactive demand.
demand and asynchronous plants scaled to 70%.
At an even lower demand e.g. 20 GW with a This issue is worse overnight, when the demand
higher penetration of renewables e.g. 100%, the for electricity is lower, and therefore the charging
minimum fault levels will reduce even further. current produced by lightly loaded circuits
increases the voltage on the system. This is most
The reduction in system strength may have some severe in cable dominant areas. The reactive
consequences which are described below: power consumption of the load also has an
impact on the voltage profile. The following figure
Voltage and Reactive Power Management illustrates the historic trend of reactive power
Reactive power to support and stabilise system demand during minimum demand periods.
voltage is currently provided locally using
reactive power compensation equipment, and
by generators set to voltage control. This allows
better control over the voltage on the grid, one
of the key system stability factors. Inadequate
reactive power may result in low voltage, an
increase in network losses, and voltage instability.
Excessive reactive power on the network causes
the voltage to rise.
Page 221
4.3 continued
System design and
operation challenges
Figure 4.3.8:
Average active and reactive power demand (average of 3 lowest each year)
25,000 0.50
20,000 0.40
15,000 0.30
Q/P Ratio
MW
10,000 0.20
5,000 0.10
0 0.00
2005/06 2006/07 2007/08 2008/09 2009/10 20010/11 2011/12
Page 222
Electricity Ten Year Statement
November 2012
Figure 4.3.9:
Q/P ratio over a 24hr period in summer minimum demand periods
0.36
0.34
0.32
R educ ing
0.30
0.28
Q/P Ratio
0.26
0.24
0.22
0.20
0.18
06:00
07:00
08:00
00:00
01:00
02:00
03:00
04:00
05:00
09:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
2008 2009 2010 2011 Time
Under all future scenarios large numbers of coal management. Therefore, we are investigating
plants installed in the centre of the network are the exact cause of the high voltage observed
decommissioned. Simultaneously, large offshore overnight by working with distribution companies.
wind farms connected to the periphery of the The solutions to address this issue currently being
system can only provide localised reactive power considered include investment in reactive power
support (at the point of connection) to the grid. compensation devices, and managing the output
The new Combined Cycle Gas Turbine (CCGT) of generators local to the affected regions.
generators requiring cooling water are also
located closer to the shore and the periphery Protection Sensitivities to Low Fault Level
of the system. This may result in having strong Protection devices will be affected because
reactive power control capability around the as under the low fault level case, the speed
network extremities through the connection of of response to eliminate the fault is reduced.
these generators, but a lack of such capability in Furthermore with increasing penetration of
the central parts of the system. asynchronous generation and interconnectors
there may be cases when the load current and the
The consequences of this are complex and fault current become close to each other, implying
may result in reduced boundary transfer that the detection of faults will become more
capability, system stability issues, including challenging.
inter-area oscillation, and problems with voltage
Page 223
4.3 continued
System design and
operation challenges
Quality of Supply Issues – The reduction in fault Potential Mitigating Measures to tackle low
levels weakens the overall strength of the network system strength issues
which in turn can gives rise to quality of supply
issues such as large voltage steps, harmonics Use of FACTS Devices – The Flexible AC
and flicker. Transmission System (FACTS) devices such as
Static Var Compensator (SVC) are used in the
HVDC Commutation Failure – Voltage network in various locations for better voltage
disturbance is one of the key reasons for control and maintaining system stability. There
commutation failure on HVDC Links. Voltage is however scope for the system-wide control
disturbances are generally caused by system of such devices to improve powerflow control
faults or switching events. These events are between different boundaries, manage voltage
unpredictable and therefore the system must in certain areas, and enhance system stability.
be robust enough to survive them or be able Advanced control systems may also allow the
to recover from them successfully. In a system devices to contribute to some complex power
with low fault levels, the severity of such voltage system stability challenges such as low frequency
disturbance may be such that it does not allow oscillation.
the minimum extinction angle required by the
Thyristor to perform block/de-blocking in a Line Synchronous Compensators – A synchronous
Commutated Current (LCC) HVDC system. generator spinning at synchronous speed
Therefore, the probability of commutation failures connected to the system contributes to system
in LCC-based HVDC is greater for weak networks. strength for voltage control, and provides fault
current contribution due to its inductive nature.
In the design of the HVDC projects, and in order A synchronous compensator retains some of the
to identify the appropriate technology, we give properties of a synchronous generator but without
consideration to fault level variations over the requiring the whole power plant to operate.
lifetime of the project. It may be beneficial for the new generators to
be designed in such a way that they can be
declutched from the turbine (main mechanical
driver) to operate as a synchronous compensator.
Further consideration needs to be given regarding
the conversion feasibility for older generators.
Page 224
Electricity Ten Year Statement
November 2012
Page 225
4.3 continued
System design and
operation challenges
Figure 4.3.11:
Comparison of powerflows and dependency to wind output for Slow Progression
scenario in 2022
Page 226
Electricity Ten Year Statement
November 2012
Figure 4.3.12:
Comparison of powerflows and dependency to wind output for Gone Green scenario in 2022
Page 227
4.3 continued
System design and
operation challenges
Figure 4.3.12:
Comparison of powerflows and dependency to wind output for Accelerated Growth
scenario in 2022
Page 228
Electricity Ten Year Statement
November 2012
Depending on the level of wind on the system in System balancing ensures that:
different scenarios, the power flows across the at any given time, the balance between
system are very sensitive to both wind output generation and demand including network
and location. The magnitude of change in the losses, is maintained
flow to and from an area for Slow Progression there is enough generation and demand side
is noticeable mainly over Anglo-Scottish reserve (also termed ‘margin’) that can be
interconnectors due to dependency of powerflow dispatched rapidly; usually between 10–30
in this power corridor to the level of wind power seconds to cater for the level of generation/
generation in Scotland. For other areas, there is demand imbalance specified in the SQSS
significant change in the powerflow magnitude the transmission network can securely transfer
when considering the variations in regional wind the power from one region of the country
power output. In Gone Green, the challenges with to another.
regard to change in the magnitude of powerflow
to and from an area is more severe as the level The key indicator for system balancing is the
of installed wind power generation is higher system frequency which in a balanced system will
in many areas. For Accelerated Growth, the be equal to the nominal frequency (namely 50.0
powerflow direction could become south to north Hz in the GB power system). Another important
considering the variations in regional wind power aspect is the cost of balancing the system. Any
output. The change in powerflow direction for unplanned change in demand/generation in the
other areas is also noticeable due to the change in balancing market, or constraint on economic
wind power output in different cases. power transfers, may result in significant balancing
costs incurred by the system operator.
Page 229
4.3 continued
System design and
operation challenges
Figure 4.3.13:
British market in January 2030 with 2000 weather
500
Electricity Price (£/MWh)
400
300
200
100
0
-100
Electricity Price
50
Generation (GW)
40
30
20
10
0
Intermittent Generation
70
60
Generation (GW)
50
40
30
20
10
0
01 Jan
04 Jan
07 Jan
10 Jan
13 Jan
16 Jan
19 Jan
22 Jan
25 Jan
28 Jan
31 Jan
Figure 4.3.13 can only be an approximate imported and none exported. This illustration is
forecast, but it does illustrate that unless wind at the highest demand of winter and these issues
is curtailed, all other generation technologies will become more pronounced when demand
including nuclear have to reduce or even shut is lower. Further analysis shows that there may
down completely. Here the assumption is no be events (around 10 times per year) that wind
external power exchanges, i.e. no further wind output exceeds the demand.
Page 230
Electricity Ten Year Statement
November 2012
Figure 4.3.14:
Wind turbine power output curve
1.2
CALM GENTLE FRESH STRONG NEAR GALE SEVERE STORM VIOLENT
BREEZE BREEZE BREEZE GALE GALE STORM
1.0
Active Power (per unit)
0.8
Maximum Power High Wind Speed
RATED WIND SPEED
CUT IN WIND SPEED
0.0
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
Wind Speed (m/s)
Page 231
4.4
Opportunities
Page 232
Electricity Ten Year Statement
November 2012
4.4.2 4.4.3
Parallel Operation of AC Dynamic Thermal Rating
and DC Systems National Grid and many other transmission
utilities apply a constant seasonal thermal rating
The fundamental process that occurs in a HVDC
for overhead lines. This rating is a conservative
system is the conversion of electrical current
value, which in turn is likely to be lower than
from AC to DC (rectifier) at the transmitting end
the actual thermal rating which varies with
and from DC to AC (inverter) at the receiving
the weather conditions. The thermal rating is
end. The rectifier and inverter can be either a
calculated based on the thermodynamic balance
Thyristor-based LCC or an Insulated-Gate Bipolar
between the heat generated inside the conductor
Transistor (IGBT) based voltage sources converter
and the heat lost by the conductor through
(VSC). Both LCC-HVDC and VSC HVDC employ
radiation and convection. The transmission
switching commutation in order to perform
capacity of overhead transmission lines is often
conversion and they are currently in operation
constrained by temperature limitations on the
in the Network. The control of powerflows on a
conductors. One strategy connected with smart
HVDC link is possible whereas in an AC system,
energy transmission is to calculate present and
the power will flow depending on the route’s
future transmission capacities of the lines based
impedance. Powerflow control capability on
on actual weather conditions and forecasts,
the HVDC links, and additional features such
supplemented by real time measurements
as power reversal (rapid power reversal is only
rather than relying on a static and conservative
available in VSC-based HVDCs), ramp-up and
fixed value. An increased transmission capacity
ramp-down capability provide great opportunities
can then be enabled for time scales where a
in both the design and operation of the system.
reliable weather forecast is available or where
measurements such as conductor tension
Many power system stability issues such as
measurements have been fitted. These
voltage and rotor angle stability may be managed
techniques can also be applied to further enhance
better by the parallel operation of the AC and DC
short-term ratings, taking into account the actual
systems and by considering dynamic response
loading of the previous period.
characteristics of HVDC systems.
Page 233
4.4 continued
Opportunities
4.4.4 4.4.5
Interconnectors Improved Demand Side
Interconnector capacity is forecast to increase
Management (DSM)
in all scenarios. The additional interconnectors,
Various Demand Side Response services
which improve access to other European power
may be provided by demand customers.
systems, may add complexity to the transmission
For real power this can be provided at all levels
network in terms of powerflows. Managing the
– from large industrial consumers, commercial
powerflow on the interconnectors, and the impact
consumers and domestic consumers. These
of simultaneous import/export on the onshore grid,
services can be automated by using movements
are some of the challenges related to additional
in system frequency as the controlling quantity
interconnector capacity.
or they may be switched via a remote signal,
e.g. by an aggregator. For reactive power and
Despite these challenges, from a system design
voltage management, co-ordinated demand
and operation point of view, the interconnectors
side management with distribution systems can
may provide some additional services to enhance
enhance the voltage control capability in the
the grid’s stability – in the short term by sharing
system. Some of these services are currently
reserve with the rest of Europe, and in the longer
being provided at a limited scale but DSM may
term by enhancing system stability through
be able to expand to incorporate the advent of
providing fast frequency response, dynamic
electric vehicles and heat pumps (particularly in
reactive power support (VSC-HVDC links at zero
the period post-2020.
transfer may provide reactive power for voltage
management), and power oscillation damping.
Page 234
Electricity Ten Year Statement
November 2012
4.4.6
Energy Storage
The storage of energy available to be converted
into electrical energy is possible in various forms
such as batteries, pumped storage, and in lesser
known or used forms such as Compressed Air
Energy Storage (CAES) and flywheels. Energy
storage technology could play a significant role
in the operation of the transmission networks by
improving the utilisation of renewable generation,
the provision of flexible balancing services, and
tackling some of the system design and operation
issues, particularly with regard to inertia and fast
frequency response.
Page 235
Chapter five
Way forward
Electricity Ten Year Statement
November 2012
5.1
Introduction
transmission.etys@nationalgrid.com
Page 237
5.2
Continuous development
Our aim going forwards is to ensure that we adopt It is intended that the ETYS annual review
the following principles to enable the ETYS to process will ultimately facilitate the continuous
continue to add value in the future: development of the Statement and encourage
participation from interested parties with the
seek to identify and understand the views and view of enhancing future versions of the ETYS
opinions of all our stakeholders in accordance with our licence provisions.
provide opportunities for engagement all the
through the process
endeavour to enable constructive debate
to take place, creating open and two-way
communication processes
base the engagement around assumptions,
drivers and outputs upon which stakeholders
can make an informed decision
provide feedback on how views expressed
have been considered and the outcomes of
any engagement process.
Page 238
Electricity Ten Year Statement
November 2012
5.3
Stakeholder engagement
The ETYS will be the subject of an annual review In addition to the development of the ETYS
process, facilitated by National Grid, and involving document we are keen to canvass views on
all customers who use this publication. The our Network Development Policy approach
purpose of this review is to ensure the aims of to identifying future network reinforcements.
the document continue to be met and the ETYS It should be noted that the NDP only applies to
evolves alongside industry developments. Some the development of the network in England and
of the areas to consider are: Wales, but any views on the approach to network
development in Scotland are of course welcome.
Does the ETYS meet the stated aims of:
– illustrating the future development of the
transmission system in a co-ordinated and
efficient way?
– providing information to assist customers in
identifying opportunities to connect to the
transmission network?
Are there any areas where the ETYS can be
improved to meet these aims?
Page 239
5.4
Timetable for 2013 engagement
Figure 5.4.1:
ETYS engagement timeline 2013
Page 240
Electricity Ten Year Statement
November 2012
Notes
Disclaimer
The information contained within the Electricity Ten Year Statement document company shall be under any liability for any error or misstatement or opinion
(“the Document”) is disclosed voluntarily and without charge. The Document on which the recipient of this Document relies or seeks to rely other than
replaces the Seven Year Statement (SYS) and the Offshore Development fraudulent misstatement or fraudulent misrepresentation and does not accept any
Information Statement (ODIS) and is published in accordance with the relevant responsibility for any use which is made of the information or Document which or
Licence conditions. (to the extent permitted by law) for any damages or losses incurred.
National Grid would wish to emphasise that the information must be considered Copyright National Grid 2012, all rights reserved. No part of the Document or this
as illustrative only and no warranty can be or is made as to the accuracy and site may by reproduced in any material form (including photocopying and restoring
completeness of the information contained within the Document. Neither National in any medium or electronic means and whether or not transiently or incidentally)
Grid Electricity Transmission, National Grid Gas nor the other companies within without the written permission of National Grid except in accordance with the
the National Grid group, nor the directors, nor the employees of any such provisions of the Copyright, Designs and Patents Act 1988.
Page 242
Electricity Ten Year Statement
November 2012
National Grid plc
National Grid House,
Warwick Technology Park,
Gallows Hill, Warwick.
CV34 6DA United Kingdom
Registered in England and Wales
No. 4031152
www.nationalgrid.com