Professional Documents
Culture Documents
Question 1
• As ammonia is regularly used in the business, its relevant cost will be the current price.
• Unit cost last month = R4 500/ 1 800kgs = R2.50 per kg.
• The current price after an 8% price hike = R2.50 x 1.08 = R2.70 per kg.
• The relevant cost ammonia for the special order = 3 500kgs x R2.70 = R9 450.
• Phosphoric acid is not regularly used in the business, the current inventories need not to be
replaced if used or sold. The relevant cost of phosphoric acid is therefore its net realisable
value if it were sold.
• The relevant cost phosphoric acid for the special order = 3 000kgs x (R2.75 – R0.50) = R6 750.
(Opportunity cost)
Skilled labour
• As skilled labour is in short supply, its relevant cost will be actual cost of labour hours
required for the special order plus the opportunity cost of labour diverted from the
production of ammonium nitrate.
• The actual cost of labour = (900/60) 15 Hours x R180 = R2 700.
• The opportunity cost of labour can be calculated in two ways:
Method 1
• No. of hours required for a 50kg bag of ammonium nitrate = R36.00/R180 = 0.20 hours
• The contribution per 50kgs of ammonium nitrate = (R335 – R88 – R36 – R40) = R171
• The contribution per skilled labour hour (extra price of skilled labour) = R171/0.2 = R855
(contribution lost)
• Opportunity cost of skilled labour for the special order = (900/60)15 hours x R855 = R12
825.
Or
Method 2:
Comments:
c) Ethics
Code of professional conduct being breached
Dishonesty and trust issues
Quote the relevant code issue on the auditing CPC handbook
Any other valid points
Question 3 - Solution
R
Material A 1 000 kgs @ R2 – R300 1 700
(Note 1) 1 000 kgs @ R10 10 000
———
11 700
Material B (note 2) 1 000 kgs @R15 15 000
Material C (note 3) 500 kgs – opportunity cost 8 000
Material D (note 4) 50 litres @ R50 (2 500)
Skilled labour (note 5) 1 000 hrs @ R25 25 000
Semiskilled labour (note 6) 500 hrs @ R22.50 11 250
Unskilled labour (note 7) 500 hrs @ R12 (opportunity cost) 6 000
———
Minimum tender price = total of relevant cash flows 74 450
———
NOTES
1. There are 1,000 kgs in stock and these will not be replaced. These would otherwise be sold
at a net gain of R1 700. This gain is therefore foregone as a result of using this material in the
contract. The other 1,000 kgs are out of stock and therefore the relevant cost is the current
purchase price of R10 per kg.
2. The material is in stock but will be replaced and therefore the relevant cost is the current
purchase price of R15 per kg.
3. The material is in stock and there are two options if this material is not used for the contract:
4. The material is in stock and will not be replaced. The cost of disposing of 50 litres will be
saved (@ R50/litre, i.e. R2 500). Saving this cost is a relevant benefit.
5. The incremental cost of paying for the labour needed.
6. 1 500 spare hours have already been paid for as the workforce are on annual contracts. The
additional cash flow is therefore the extra 500 hours that are needed at time-and-a-half.
7. For each hour diverted from their normal jobs contribution of R2 will be foregone. This
together with the cost of paying the workers to do the project amounts to a relevant cost of
R12 per kg. They would not be hired at R20 per hour as this is more expensive.
8. Fixed overheads can be ignored as they are not incremental.
9. Costs of preparing the tender are all sunk costs and hence must be ignored.
10. Profit element should be ignored since a minimum contract price is being calculated.