You are on page 1of 4

For Use With PAM 2018

SCHEDULE OF DAYWORK RATES ANNEX “A”

Pursuant to Clause 11.6 (d) (i) of the Conditions of Contract for the main Works, the Architect
may sanction work on a daywork basis if the work cannot be properly measured and valued in
accordance with Clause 11.6(a), (b) or (c). The Tenderer shall fill in the Daywork Rates
hereunder which he would charge for work carried out on a daywork basis.

The Daywork Labour Rates shall be the actual all-in rate of the Contractor’s labour cost
including transportation, food and lodging (if any), all statutory charges or levies payable,
provident fund, insurances, use of all ordinary and standing plant (plant already on site),
tools, standing scaffolding, supervision, overheads and profit. The time of chargehands
(working with their hands) shall be brought to account, but the time of foremen and walking
overseers will be regarded as included in the cost of supervision in his all-in Daywork Labour Rates
and will not be considered for payment under a separate Daywork rate, nor will rates be paid at a
grade higher than that considered necessary by the Architect for the class of work involved. The
cost for power-driven tools should not be included in the labour rates but charges for hand tools
shall be deemed to be included.

Where special mechanical plant is required for use on Daywork, the Architect’s approval must be
obtained and the cost to be paid to the Contractor must be agreed before commencement of
work. Only such plant that the Architect has accepted as special mechanical plant before
commencement of work will be considered for payment as special plant on daywork basis.

The Daywork Plant and Equipment Rates shall be the actual all-in rate of the Contractor’s
common plant and equipment cost including fuel and consumable stores, maintenance, servicing,
repairs, spare parts and lubricant, transportation from and to store/yard, all statutory charges, taxes
and insurances and all other costs, expenses and charges in connection including the cost of
drivers, banksmen, attendants and operators, overheads and profit.

Only time on work actually done will be allowed. A “Day” is considered to be a normal working day
of 8 hours. Fractions of a day will be paid for “pro-rata”.

RL Bersepadu Sdn Bhd ANN/A/1


1055 AMKOR
For Use With PAM 2018
ANNEX “A” - SCHEDULE OF DAYWORK RATES (Cont’d.)

Daywork Labour Rates Per 8 Hour Day (RM)

Concretor ………130.00……….

Steel Bar Bender and Fixer ………130.00……….

Bricklayer ………130.00……….

Drainlayer ………130.00……….

Waterproofer ………130.00……….

Pavior ………130.00……….

Tiler ………130.00……….

Mason ………130.00……….

Roofer ………130.00……….

Carpenter ………130.00……….

Joiner ………130.00……….

Steel Erector ………130.00……….

Welder ………130.00……….

Fitter ………130.00……….

Plasterer ………130.00……….

Plumber ………130.00……….

Glazier ………130.00……….

Painter ………130.00……….

Fence Maker ………130.00……….

Road Maker ………130.00……….

Pneumatic Tool Operator ………140.00……….

Labourer (Male – Semi-skilled Artisan’s mate) ………110.00……….

Labourer (Male – Unskilled) ………90.00……….

Labourer (Female) ………75.00……….

RL Bersepadu Sdn Bhd ANN/A/2


1055 AMKOR
For Use With PAM 2018
ANNEX “A” - SCHEDULE OF DAYWORK RATES (Cont’d.)

Daywork Plant and Equipment Rates Per 8 Hour Day (RM)

Motor lorry not exceeding 3 tons capacity ………500.00……….

Motor lorry exceeding 3 tons capacity ………650.00……….

Excavator not exceeding 14 cu. ft. capacity ………900.00……….

Excavator exceeding 14 cu. ft. capacity ……1,200.00……….

Combined shovel and backhoe (CASE or equivalent) ………600.00……….

Backpusher ………530.00……….

Bulldozer not exceeding 50 HP ………650.00……….

Bulldozer exceeding 50HP but not exceeding 100HP ………750.00……….

Grader ………760.00……….

Steel wheeled road roller with total operating weight not exceeding 8
tons ………780.00……….

Steel wheeled road roller with total operating weight exceeding 8 tons
but not exceeding 10 tons (driven roll exerting a rolling force of not less
than 3.5 tons/metre of roll width) ………950.00……….

Pneumatic tyred roller with 9 wheels of 1.0 of 2.0 tons per wheel ……1,100.00……….

Mobile crane not exceeding 5 tons lifting capacity ………800.00……….

Mobile crane exceeding 5 tons lifting capacity (__20__Tons) ………900.00……….

Concrete mixer not exceeding 14/10 capacity ……….90.00……….

Concrete mixer exceeding 14/10 capacity ………150.00……….

Air Compressor not exceeding 210cu.ft. capacity including


one pneumatic tool ………200.00……….

Each additional pneumatic tool ………85.00……….

Mechanical concrete vibrator ………130.00……….

Power driven pump, outlet diameter not exceeding 3in. including all
piping ………90.00……….

RL Bersepadu Sdn Bhd ANN/A/3


1055 AMKOR
For Use With PAM 2018
ANNEX “A” - SCHEDULE OF DAYWORK RATES (Cont’d.)

Daywork Plant and Equipment Rates (Cont’d.) Per 8 Hour Day (RM)

Power driven pump, outlet diameter exceeding 3in. including all piping ………110.00……….

Generator set not exceeding 50 KVA at 50 Hz ………180.00……….

Generator set exceeding 50 KVA but not exceeding 150 KVA at 50 Hz ………400.00……….

Generator set exceeding 150 KVA but not exceeding 250 KVA at
50 Hz ………650.00……….

Generator set exceeding 250 KVA at 50 Hz ………900.00……….

Oxy-Acetylene cutting set ………200.00……….

Electric welding set 300 amp ………250.00……….

Cherry pickers ………550.00……….

Scissor lift ………450.00……….

Set of standard scaffolding comprising 1 pair main frame, 2 pairs cross ………250.00……….
braces and 4 Nos. joint pins

SIGNATURE OF TENDERER: …………………………………………………………………………...

NAME OF TENDERER: …………………………………………………………………………………..

ADDRESS: …………………………………………………………………………………………………

DATE: ……………………………………………………………………………………………………….

SIGNATURE OF WITNESS: …………………………………………………………………...………...

NAME OF WITNESS: ……………………………………………………………………………………..

ADDRESS: …………………………………………………………………………………………………

DATE: ……………………………………………………………………………………………………….

RL Bersepadu Sdn Bhd ANN/A/4


1055 AMKOR

You might also like