Cost Savings: Reduce electricity expenses by ($....) annually for the organization hosting the solar installation.
Project Manager Project Title Rooftop solar system installation (100kW)
Project Sponsor Project Number PR 005 Financials Budget to complete this project is $50,000 Milestones Schedule Milestone Target Completion Date Actual Date System Design (BoQ) 02-Jan Contract 20-Jan PO confirm 01-Feb Material delivery 03-Mar Installation 30-Mar Testing and Commissioning 01-May Handover to customer 03-Apr Project Risk & Issues Material delivery Budget Logistics issues Project timeline Technical issues Customer Complaint Safety Resources Internal Resources Approval Persons Days Name Sign Project Manager 1 34 Sponsor Team Members 6 33 Engineering Manager Safety Officer 1 33 QA & QC Labour 20 20 Customer