Professional Documents
Culture Documents
Cynthia Wang
Construction Management and Property Program
UNSW
1
Types Of Project Constraints
Technical or Logic Constraints
Physical Constraints
Activities that cannot occur in parallel or are affected by
contractual or environmental conditions.
Resource Constraints
Importance of Resources
Project network times are not a schedule until resources have been
assigned.
Cost estimates are not a budget until they have been time-phased.
3
Project Resources
It is important to see if
Comprise The idea here is resource assignments
people, Some resources are to identify
consumed (e.g. can be
equipment, resource smoothed/levelled
materials and materials and quantities
consumables); through changing
consumables, required for each activity sequences or
buildings and others are applied activity in each
(HR, equipment). rescheduling the entire
facilities. project phase. project in order to
prevent over-allocation.
4
Resource Estimation
There are five basic methods for resource
estimation:
1. Parametric estimation
2. Analogous estimation
3. Historical data
4. Expert judgment
5. Three-point estimating
5
Estimating Method & Method Statement
6
Parametric Estimation
Total resource usage for execution of a given activity in terms of man-
hours (for each trade/specialisation) is estimated by using productivity
rates and appropriate job-management factors.
8
Method Statement of Bulk excavation
Quantity = 9,000 m3;
Productivity Rates = one person one hour can
excavate 100 m3= 0.01 Person Hours/m3;
Total person hours required = 90
A Previous Example Of
Typical Crew Size = 1.5, therefore 90/1.5 = 60hrs Parametric Estimation
Assume 8 hours / day, then the work can be done
in
60 / (8 hours/day) = 7.5 days or 8 days
9
Analogous Estimating
10
Historical Data
Many companies compile historical data.
Also, there are many published productivity data handbooks and online databanks.
This method is useful for very specialised activities and when operators are trained to
perform tasks to set methods.
11
Expert Judgement
Engagement of experts for scheduling may be necessary, particularly when:
• A new technology is involved.
• A new project/business is undertaken with no prior experience.
• Proprietary technology or design is involved.
• Complicated operations, e.g. offshore projects
• Project is executed in hostile environments
• Safety reviews are involved.
• Local knowledge is essential.
A time-constrained project
- Completed by imposed time (time is fixed)
- If required, resources can be added to ensure the project is completed by a specific
date
- resource usage should be no more than is necessary and sufficient.
A resource-constrained project.
- Assumes the level of resources available cannot be exceeded
- If the resources are inadequate, it will be acceptable to delay the project, but as little as
possible.
14
Resource Allocation/Optimization
1- Resource smoothing (Time- Constraint Project)
- A technique that adjusts the activities of a schedule model such that the
requirements for resources on the project do not exceed certain predefined
resource limits.
- The project’s critical path is not changed and the completion date may not be
delayed.
- Consequently Activities may only be delayed within their free and total float.
15
Resource Allocation/Optimization
2- Resource levelling (Resource-Constraint Project)
- A technique in which start and finish dates are adjusted based on resource constraints with
the goal of balancing the demand for resources with the available supply.
- Can be used when shared or critically required resources are available only at certain times
or in limited quantities, or are overallocated, such as when a resource has been assigned
to two or more activities during the same time period.
- Can often cause the original critical path to change.
- Available float is used for levelling resources first, but you may need to go beyond this.
- Consequently, the critical path through the project schedule may change and/or extended.
16
Resource Smoothing- Example
Max. 3
Backhoes
available
Delay
Fence and
wails (use
the slack)
If Irrigation is delayed.
17
Copyright ©UNSW Sydney 2017