RESOURCE COST OVERVIEW

COST STATUS COST DISTRIBUTION


Cost status for work resources. How costs are spread out amongst different resource types.

₹ 1,20,000.00

₹ 1,00,000.00

₹ 80,000.00

₹ 60,000.00

₹ 40,000.00

₹ 20,000.00

₹ 0.00 ₹ 2,06,082.24
P Q R S T U V

Actual Cost Remaining Cost Baseline Cost Type: Work

COST DETAILS
Cost details for all work resources.

Name Actual Work Actual Cost Standard Rate

P 336 hrs ₹ 33,600.00 ₹ 800.00/day

Q 0 hrs ₹ 0.00 ₹ 400.00/wk

R 0 hrs ₹ 0.00 ₹ 235.50/mon

S 0 hrs ₹ 0.00 ₹ 1,470.80/mon

T 0 hrs ₹ 0.00 ₹ 9,000.00/mon

U 0 hrs ₹ 0.00 ₹ 88,235.50/mon

V 0 hrs ₹ 0.00 ₹ 80,000.00/wk