Professional Documents
Culture Documents
SUGGESTED SOLUTIONS
SOLUTION TO MULTIPLE CHOICE QUESTIONS
10.1 (e) 10.6 (b)
10.2 (c) 10.7 (d)
10.3 (d) 10.8 (e)
10.4 (c) 10.9 (a)
10.5 (b) 10.10 (a)
10.1
Standard costing enables a benchmark to be set against which actual costs, revenues and
volumes can be measured. This assists in management by exception, that is, it easily
identifies situations where actual results differ from what was expected. By identifying a
standard, budgets can be prepared and control is made easier because the variance from the
plan is easily determined.
10.2
A variance is a deviation in actual performance when measured against the standard
expected. While it is always anticipated that there will be some deviation from standard,
variance analysis permits a tolerance level to be established. This means, for example, that if
a 5% deviation (above or below standard) is considered to be acceptable, variances in excess
of the tolerance levels can be identified. There may be legitimate reasons for such deviations,
but it nevertheless brings it to the attention of the responsible manager, who will request an
explanation. If the variance is as a result of a situation which requires correction, then action
can be taken timeously.
10.3
The two most significant variables when setting standards for materials are the standard price
and the standard quantity of the materials used per item of production. In addition, attention
must be paid to the quality of the materials, as lower quality material may be less costly, but
larger quantities may be required. The three critical variables are therefore the price, the
quantity and the quality of the materials. Other factors which must be considered are the
availability and the supplier from which it will be sourced. There must be confidence that a
specific material will always be able to be sourced, so alternative and contingency plans must
be on hand. In the event of materials being sourced from outside the country, consideration
must be given to exchange rates and lead times for delivery.
10.4
Direct material standards are set based on price, quantity and quality of materials required.
Consideration must be given to wastage which is inevitable in the use of all materials. This
must be included the standard material requirements in order to ensure that the standard is
realistic under normal working conditions
Direct labour standards are set based on the wage which must be paid and the average time
required for production of each unit. The wage should be market related and must comply with
any minimum wage legislation. Consideration needs to be given to possible down time as a
result of machine malfunctions and other possible stoppages in the normal course of
production.
10.5
An ideal standard is based on perfect conditions and no consideration of any defects or
malfunctions. This is not practical in real life situations, so due consideration is given to these
issues when setting practical standards.
10.7
Direct costing treats overhead costs as an expense for the period under review. Stated
differently, all overhead costs are written off as an expense for the period, regardless of how
many units were produced or sold. No allocation of overheads is included in the cost of the
units, which is determined only on the basis of the direct (variable) costs.
As a result, when direct costing is used, the only overhead variance is the overhead spending
variance, that is the difference between budgeted overheads and actual overheads incurred
during the period.
When absorption (full) costing is used, a portion of the overheads is budgeted into the cost of
each unit of production, based on the budgeted production volume. When there is a difference
between budgeted and actual volume, it follows that overheads will either have been under
absorbed or over absorbed by the production output. The overhead volume variance (volume
of over/under production x standard overhead allocation) must be determined in order to
reconcile the Rand difference between budgeted and actual production cost.
10.8
All resources used can conveniently and intuitively be divided into the quantity of the resource
used and the price paid. In most cases there are different people responsible for each and
dividing the variance in this way enables the person responsible to offer the reasons for such
variances.
10.9
Whenever the actual volume of units produced or sold is above or below the budgeted volume
of units, it follows that many other cost and revenue items will also be affected. In fact, the
only item which should not be affected is fixed costs. In order to make the variances more
useful, it also follows that the budget against which actual performance is measured should be
"flexed" in order to see what the budget would have been, had it budgeted for the actual
production. Variances are then comparable and provide useful information.
LUCID LTD
MASTER BUDGET
500,000 600,000 750,000
Sales 17,500,000 21,000,000 26,250,000
Cost of Sales 15,960,000 18,792,000 23,040,000
Materials 10,800,000 12,960,000 16,200,000
Labour 3,360,000 4,032,000 5,040,000
Prime Cost 14,160,000 16,992,000 21,240,000
Overheads 1,800,000 1,800,000 1,800,000
Net Profit 1,540,000 2,208,000 3,210,000
Cost per unit R 31.92 R 31.32 R 30.72
Profit/Sales 8.8% 10.5% 12.2%
Markup 9.6% 11.7% 13.9%
(c) The cost per unit declines as production increases, because the fixed costs are spread across
a grater number of units.
VARANCE VARANCE
MASTER FLEXIBLE ACTUAL
FLEXIBLE TO MASTER TO
BUDGET BUDGET RESULTS
ACTUAL ACTUAL
LUCID LIMITED
BUDGET VARIANCE REPORT
Budgeted Net profit 1,540,000
Sales Variance -204,400
Volume Variance 1,135,600
Price Variance -1,340,000
Material Variance 3,072,000
Volume Variance 4,212,000
Price Variance -1,140,000
Labour Variance 182,400
Volume Variance 470,400
Price Variance -288,000
Overhead Spending Variance -135,000
Actual Net Profit 4,455,000
(d)
BASIC VARIANCES
Master Budget Profit 2,000
Sales Volume -400
Sales Price 240
Cost -305
Actual Profit 1,535
(e)
RHINO DOORS CC
VARANCE
VARANCE
MASTER FLEXIBLE ACTUAL MASTER
FLEXIBLE
BUDGET BUDGET RESULTS TO
TO ACTUAL
ACTUAL
500 550 550 0 50
Sales 425,000 467,500 473,000 5,500 48,000
Cost of Sales 379,800 417,780 396,000 21,780 -16,200
Materials 54,000 59,400 55,000 4,400 -1,000
Labour 315,000 346,500 330,000 16,500 -15,000
Prime Cost 369,000 405,900 385,000 20,900 -16,000
Overheads 10,800 11,880 11,000 880 -200
BASIC VARIANCES
Master Budget Profit 45,200
Sales Volume 4,520
Sales Price 5500
Cost 21,780
Actual Profit 77,000
VARANCE VARANCE
MASTER FLEXIBLE ACTUAL
FLEXIBLE MASTER
BUDGET BUDGET RESULTS
TO ACTUAL TO ACTUAL