Professional Documents
Culture Documents
PTG 18.57.02
November 2019
Internal
© 2019 PETROLIAM NASIONAL BERHAD (PETRONAS)
All rights reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form
or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright
owner. PETRONAS Technical Standards are Company’s internal standards and meant for authorized users only.
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 2 of 145
FOREWORD
PETRONAS Technical Guidelines (PTG) has been developed based on the accumulated knowledge,
experience, Lessons Learnt and Best Practices of the PETRONAS group supplementing PETRONAS
Technical Standards (PTS), National and International standards where appropriate. The key objective of
PTG is to guide the implementation of technical practices across the PETRONAS group.
Compliance to PTG should be adhered to across the Group. The PTG shall remain confidential within the
PETRONAS Group and shall not be issued to Contractors / Manufacturers / Suppliers. Issuance of PTG to
third parties shall be subjected to G-TA approval.
In issuing and making the PTG available, PETRONAS is not making any warranty on the accuracy or
completeness of the information contained in PTG. The end-users shall ensure the accuracy and
completeness of the PTG used for the intended application.
PETRONAS is the sole copyright holder of PTG. No part of this document may be reproduced, stored in a
retrieval system or transmitted in any form or by any means (electronic, mechanical, recording or
otherwise) or be disclosed by users to any company or person whomsoever, without the prior written
consent of PETRONAS.
The PTG shall be used exclusively for the authorised purpose. The users shall arrange for PTG to be kept
in safe custody and shall ensure its secrecy is maintained and provide satisfactory information to
PETRONAS that this requirement is met.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 3 of 145
Table of Contents
1.0 INTRODUCTION ..................................................................................................... 8
1.1 SCOPE .................................................................................................................................... 8
1.2 SPECIFIC DEFINITION ............................................................................................................. 9
1.3 SUMMARY OF CHANGES ..................................................................................................... 14
2.0 GENERAL INSTRUCTION TO MASTER OF MARINE VESSEL (CIMMV) ....................... 15
2.1 MARINE VESSEL’S SCOPE OF WORK .................................................................................... 15
2.2 PETRONAS MARINE BASES .................................................................................................. 16
2.3 APPLICABLE LAWS, REGULATIONS AND PETRONAS REQUIREMENTS ................................ 16
2.4 COMPLIANCE TO SAFETY PRACTICES .................................................................................. 16
2.5 CHARTS, NAVIGATIONS Publications and Information ....................................................... 17
2.6 VHF AND SSB RADIO COMMUNICATIONS .......................................................................... 17
2.7 HSSE INSTRUCTION FOR MASTER AND CREW .................................................................... 18
2.8 INCIDENT AND ACCIDENT REPORTING ............................................................................... 19
2.9 EMERGENCY DRILLS ............................................................................................................ 20
2.10 REQUIREMENT FOR VESSEL IN PORT .............................................................................. 21
2.11 DEPARTURE PORT REPORTING ....................................................................................... 22
2.12 SAFETY INSTRUCTION FOR VESSEL AT SEA ..................................................................... 22
2.13 REQUIREMENT FOR VESSEL AT OFFSHORE INSTALLATION. ........................................... 23
2.14 FIRE FIGHTING AT OFFSHORE INSTALLATION ................................................................. 28
2.15 DAILY REPORTING ........................................................................................................... 28
2.16 CARGO HANDLING AT INSTALLATION ............................................................................. 29
2.17 HOT WORK RESTRICTION ................................................................................................ 29
2.18 CARGO OPERATION......................................................................................................... 30
2.19 CARRIAGE OF EXPLOSIVE ................................................................................................ 30
2.20 CARRIAGE OF OIL BASE MUD (OBM) AND BASE OIL (BO) ............................................... 31
2.21 FREEZER OR CHILLER CONTAINERS ................................................................................. 32
2.22 CARRIAGE OF PASSENGERS ............................................................................................. 32
2.23 LIFTING/SLINGING OPERATIONS ..................................................................................... 34
3.0 INSPECTION OF OFFSHORE SUPPORT VESSEL (OSV) .............................................. 36
3.1 INTRODUCTION ................................................................................................................... 36
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 4 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 5 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 6 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 7 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 8 of 145
1.0 INTRODUCTION
This PETRONAS Technical Guideline (PTG) provides guidance on the safety requirements
necessary for all Offshore Marine activities conducted at PETRONAS and JV’s (with operational
control) facilities and installations. It should be used in conjunction with local procedures,
guidelines, regulations and statutory requirements. Where more stringent statutes or regulations
are applied, they shall take precedence over this PTG.
1.1 SCOPE
This PTG covers:
i. Common Offshore marine activities of personnel & goods transferring, fuel & freshwater
bunkering, towing, anchor handling, mooring for barges (e.g. Pipe Laying Barge, Derrick Barge,
Transportation Barge, Accommodation Barge).
ii. Role of Offshore support vessels in providing emergency support to any offshore facilities.
iii. Usage of Offshore support vessels in upstream and downstream activities.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 9 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 10 of 145
No Term Definition
10 Fast Recue Craft (FRC) Semi rigid / rubber fast rescue craft/boat with
outboard engine.
11 Field Support Vessel (FSV) All types of Offshore Support Vehicles (OSV) which
provide services to PETRONAS and are assigned to
the platform or offshore facilities as standby
function. Barges, workboats and drilling rigs are
excluded.
12 General Purpose (GP) GP is small in nature compared to other vessels, with
a gross registered tonnage of less than 500 tons. It is
mainly used to transport minimal numbers of
personnel and materials during inter-field transfer
within offshore facilities.
13 GRT Gross Registered Tonnage represents the total
internal volume of a vessel, with some exemptions
for non-productive spaces such as crew quarters.
14 Landing Craft Tank (LCT) LCT is a flat-bottomed seagoing ship with lowerable
front ramp and is designed with a shallow draft. The
primary function for these vessels is the
transportation of goods and to supply offshore
facilities.
15 Logistics Supply base Generally is referred to as Logistics Management
business that oversees on the operation and
planning of Marine, Aviation, and Land
transportation and supply base.
16 Master The person in command of a vessel. The person who
is in charge of the vessel solely responsible for the
safety of the crew and the vessel at all times. While
onboard, he/she is the ship-owner representative
and accountable for safe manoeuvering and
operation of the vessel.
17 Near Coastal Voyages Vessel plying within limits of the countries as
determined by the Marine Department, Ministry of
Transport Malaysia.
18 Offshore Support Vessel (OSV) Any type of vessel (propelled or not propelled) that
may be used to support activities at offshore
facilities.
19 Oil Record Book This record is a valuable means of providing proof
that the ship has complied with the anti-pollution
regulations. It applies to all OSV of 400 GRT and
above.
20 Platform Supply Vessel PSV / SSV / Milk Run Vessel is a vessel specifically
(PSV)/Straight Supply Vessel designed to supply offshore platforms/facilities and
(SSV)/Milk Run Vessel accomplish a variety of tasks. The primary function
for most of these vessels is the transportation of
goods and personnel to and from offshore facilities
or other offshore structures.
21 Port Side Left-hand Side
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 11 of 145
No Term Definition
No Abbreviation Description
1 AB Able Seaman
2 ABS American Bureau of Shipping
3 AHT Anchor Handling Tugs
4 AHT/S Anchor Handling Tugs / Supply
5 AHTS Anchor Handling Tug Supply Vessel
6 AHV Anchor Handling Vessel
7 BO Base Oil
8 BDR Bunker Delivery Receipt
9 BDT Bunker Delivery Ticket
10 BMS Barge Management System
11 CIMMV Charter Instructions to Master of Marine Vessel
12 COC Certificate of Competency
13 COLLREGS Collision Regulation - Refer to International Rules of
Prevention of Collision at Sea
14 COQ Certificate of Quality
15 CSR Company Site Representative
16 CV Curriculum Vitae
17 DGPS Differential Global Positioning System
18 DNV Det Norske Veritas
19 DP Dynamic Positioning
20 DPA Designated Person Ashore
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 12 of 145
No Abbreviation Description
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 13 of 145
No Abbreviation Description
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 14 of 145
No Abbreviation Description
95 SW Southwest
96 SWL Safe working load
97 TA Technical Authority
98 TBE Total Bid Evaluation
99 Tp The period associated with the peak in the wave
energy spectrum
100 Tz Average Period of the waves (zero-crossing periods)
within the measuring period
101 UKOOA United Kingdom Offshore Operators Association
102 UMS Unattended Machinery Space
103 VHF Very High Frequency
104 ZeTo Zero Tolerance
Table 2: Specific Abbreviations
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 15 of 145
This document does not provide detailed instructions to operate a particular vessel as such
instructions are a ship operator’s / owner’s responsibility. It is intended to provide the master
with information expected in the industry by PETRONAS and JV’s.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 16 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 17 of 145
2.4.5 Housekeeping
Due attention should be given to housekeeping so that the vessel is maintained in a clean, tidy
and hygienic condition. This includes maintaining the cargo deck area is clear and clean for the
carriage of cargo.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 18 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 19 of 145
2.8.1 Vessel Incident Notification Flow (within 500m Zone) For Malaysia Domestic Operations
Figure 1. Incident Notification Flow (within 500m zone for Malaysia Domestic Operation)
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 20 of 145
2.8.2 Vessel Incident Notification Flow (Outside 500m Zone) For Malaysia Domestic Operations
Figure 2. Incident Notification Flow (Outside 500m zone for Malaysia Domestic Operation)
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 21 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 22 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 23 of 145
While on a voyage, the minimum distant to pass an offshore platform is 500 metres. In any event,
if the vessel requires passing or approaching the 500 metres zone, the master to observe the
following requirement.
i. To make contact with the offshore installation (rig, barge or platform) and request permission
to enter or passing through.
ii. To observe any navigational warning broadcasted by any of the floating vessels.
iii. To navigate away from any anchor marker buoys for the workboat/barge at anchor on 4 or 8
point moorings. Cautiously observe the anchor’s buoys that may be extending out for more
than 500 metres away from the barge.
iv. The Master is to seek advice including obtaining an anchor pattern from the person in
charge.
v. To avoid crossing of any anchor wire closer than 50 metres.
vi. Get advice on any activities such as diving and ROV activities within the area that could pose
a threat to navigation.
vii. Navigate with extreme caution.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 24 of 145
ii. The vessel to confirm, by functional tests, the satisfactory operation of the followings:
a) All propulsion and manoeuvring control equipment,
b) Internal and external communications equipment,
c) Cargo handling equipment.
iii. Minimum criteria for consideration prior to entering the 500 m zone:
a) Checklist for Vessel
i. Weather conditions are suitable;
ii. All required propulsion, control and back-up systems are operational;
iii. Master and crew are sufficiently rested;
iv. Deck crew are briefed and correctly dressed;
v. Vessel’s program has been advised/agreed;
vi. Communications with the installation are working;
vii. Internal communications on the vessel are working;
viii. Bulk transfer procedures have been agreed;
ix. Full details of cargo discussed/agreed;
x. The notification has been given and received of any expected helicopter
movements.
b) Checklist on Installation
i. The required working zone alongside is clear of other vessels;
ii. All non-essential over side discharges in the working zone have been stopped;
iii. Standby Vessel has been briefed on the operation;
iv. Installation personnel are sufficiently rested;
v. Deck crew and crane operator are briefed;
vi. Weather limitations have been considered;
vii. Vessel’s program has been advised/agreed;
viii. Crane limitations have been advised to Master;
ix. Permission is given to offload during diving operations;
x. Bulk transfer procedures have been agreed;
xi. Full details of cargo discussed/agreed;
xii. Underwater/waterline obstructions which could cause a hazard to the vessel
notified.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 25 of 145
c) After completing the above, the vessel Master should formally request to enter the
installation’s 500 m zone. This request to be confirmed and the time entered into the
vessel’s logbook.
d) Any defect occurring after the checks to be immediately reported to the installation.
Continuity of operations should be subjected to agreement between the vessel Master
and installation OIM.
c) Position set-up
i. This is the process whereby the vessel master determine how adequately the vessel
is managing to hold position before starting the final approach. This should be done
far enough away so that, if something goes wrong, the vessel crew have enough
time to take corrective action.
ii. It can take some time to acquire a stable position and if applicable allow a DP model
to build up (up to 30mins).
iii. Position set-up to take place well away from the installation (to avoid collision with
the installation if equipment failure occurs during set up checks)
1½ x vessel length for drift-off operations
2½ x vessel length for drift-on operations
iv. During this time the vessel personnel are to satisfy themselves that:
DP references and sensors are stable, if applicable.
Vessel motion is within operational limits.
Vessel machinery operation within limits i.e. power utilization not greater than
45%.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 26 of 145
i. In most cases, it is preferable for all vessel to lie on the lee side of any installation during cargo
handling. However, this may not always be possible, for a variety of reasons.
ii. Where working on weather side is not possible, the Master is to set his own weather
limitations based on his own judgment, experience and through his knowledge on the vessel’s
handling characteristics. He should also make reference to Marine MOPO. This will involve a
risk assessment being carried out by the Master prior to any agreement to come alongside.
iii. Factors to be considered during such a risk assessment should include:
a) Experience of Master
b) The prevailing wind speed and direction.
c) The sea height and its effect on the vessel’s station-keeping.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 27 of 145
In the event of any conflict of requirements between vessel and installation, the final decision on
whether to position the vessel on the weather side rests with the vessel’s Master.
2.13.6 Manoeuvring
There shall be at least one additional competent crew to assist the Master during the process of
manoeuvring to berth or un-berth, anchor handling or any other critical operation in which the
situation is deemed necessary.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 28 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 29 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 30 of 145
2.18.2 Lightings
During hours of darkness, sufficient lighting should be provided at the access ways and at all work
locations to ensure the operation can be carried out safely
2.19.1 Notification
PETRONAS to notify the Master on the schedule and time for when the vessel is required to load
explosives.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 31 of 145
2.20 CARRIAGE OF OIL BASE MUD (OBM) AND BASE OIL (BO)
ii. Similarly, for backload, the rig’s Mud Technician or Engineer should inspect the tanks with
the vessel’s Officer.
a) If any of the inspection party consider the tanks are unfit to store OBM/BO, the Master
to inform Logistics Supply base person in charge immediately.
b) If all parties are in concurrence that the tanks are fit, then all parties are to sign the Tank
Fitness Certificate.
i. For OBM/BO loaded or back loaded, the Master is to obtain a sample from the vessel’s tanks
and deliver to PETRONAS person in charge for retention. The supplier or rig should collect
their own sample.
ii. The Master to stop the operation if any contamination is detected during loading or
discharging. A joint investigation to be carried out between the Supplier and the vessel
responsible officer to establish the cause. Master to inform the findings to PETRONAS person
in charge.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 32 of 145
ii. Unweighted Mud (OBM without Barites) requires circulation to prevent separation of oil and
water into different phases. Four (4) hours of is recommended for every eight (8) hours: and
at least two hours circulation before discharge.
iii. Base Oil does not require any circulation but is highly sensitive to water contamination.
2.21.2 Inspection
The freezer or chiller containers, during transit, are to be inspected at least twice a day and the
temperature to be recorded in the vessel’s daily log.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 33 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 34 of 145
g) Use swing rope once the other person has safely transferred on the boat landing and
away from the point of the landing area.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 35 of 145
v. Acknowledgement or Affirmative
All instructions and messages transmitted over the radio are to be acknowledged and
confirmed by repeating. To prevent misunderstanding, words with difficult pronunciation
are to be spelt-out using the phonetic guidelines as in the International Code of Signals.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 36 of 145
Certain limitation, substandard items, non-conformances may be visible during the inspection and
the master/contract holder should take proactive or preventive measures to manage the issues
to prevent the unfortunate incident. Non-conformance will lead to exposure of risk and danger
to human life, damage to property, environment and reputation.
This section should be used for the purpose of conducting the following inspections:
i. Pre-Hire Inspection
ii. Offshore Installation Manager / Company Site Representative Inspections
iii. Quarterly Self Inspection by Vessel Master
iv. For inspections in the above items, the following should use this guideline and checklist
provided in Appendix 2.
3.2 OBJECTIVE
This section is written to:
i. Identify any shortcomings of the operational requirements of the vessel.
ii. Assist or guide the Master in identifying high-risk areas.
iii. Improve the operation of the vessel by providing an accurate assessment for the safety and
operational suitability.
Any findings can be identified within the vessel’s documentation, tools, equipment, work method
and other related areas of concern. The inspection guideline is a supervisory procedure and a
checklist is provided to assist in identifying any non-conformance including substandard
conditions. The guideline is not intended to override any other requirements subjected by
Maritime Law and regulations by local port authority (in respective countries). This guideline
intended for Malaysia water operations.
3.3 SCOPE
This section is designed for the use of PETRONAS both Domestic and International operations.
This is to ensure any chartered vessel working for and on behalf of PETRONAS offshore facilities
or platforms are responsible for their own-HSE, contractual requirement and the smooth
operation of the vessel.
This requirement should cover for vessel hired/chartered by PETRONAS. For vessel
hired/chartered by PETRONAS contractor, they should also adopt the same practices.
Contract Holder should enforce this requirement on long and medium-term chartered vessels.
The short term charter which is serving the PETRONAS for less than 3 months may not be required
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 37 of 145
to conduct the quarterly self-inspection other than pre-hire inspection which will be done at least
once prior to the contract period.
3.4.1 Application
i. All OSV intended to be utilized are to be inspected before hiring.
ii. The inspection should be jointly conducted by Marine HSE, Logistics Supply base and End
User.
iii. Pre Hire Inspection comprises of risk assessment and assurance processes for “fit for
purpose” that may include but not limited to:
a) Validity/status of Crew OSP, OVID and Tour of Duty
b) Crew Qualification and experiences.
c) Life-Saving Equipment and Fire Fighting Appliances status and readiness
d) Navigation Safety
e) Machinery condition and status
f) General Condition of vessel
g) AAE status
iv. Briefing of PETRONAS Marine Guidelines is to be conducted at the time of inspection.
v. Closure of observation is to be monitored by attending contract holder representative.
vi. Inspection report sample as per Appendix 1.
vii. On completion of the inspection, the inspector is to provide a list of the inspection
findings in the form of written observations or discuss the inspection findings with the
Master or the Master's authorized deputy before leaving the vessel.
viii. The inspector should consider requesting that equipment be run and tested to confirm
that it is in operational order and that officers and crew are familiar with its operation,
but should ensure that such requests do not cause delay or interfere with the safety and
normal operation of the vessel.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 38 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 39 of 145
iv. All previous finding items to be reviewed and update the status accordingly.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 40 of 145
4.1 SCOPE
This requirement is applicable to all OSV’s chartered by PETRONAS as a Field Support Vessel (FSV).
International operations should adopt this requirement giving special considerations on specific
local legislation in addition to international convention/protocol ratified by the country.
The objective of this document defines as follows:
i. The requirement for Field Support Vessel (FSV) to be available at all offshore manned,
unmanned platform and facilities; -
ii. Roles and Responsibilities of FSV as Field Support Vessel (FSV); and
iii. Required minimum vessel technical specifications.
FSV should be present within the vicinity of manned offshore platform/facilities and to comply
with the requirement of response time as stated under section 4.5 of this document.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 41 of 145
FSV may not leave its station without the permission of the respective OIM/CSR. The time of
taking over and being relieved of stand-by duty should be noted in the official logbook and the
vessels last appointed as stand-by should remain in that capacity until officially relieved of the
duty.
At unmanned platform/facilities, the requirement for standby FSV is when there are people
working on platform/facilities.
FSV on duty should have adequate clear deck space for any foreseeable emergency and to cope
with the duties as laid down. Adequate clear deck space would normally mean that not more than
one-third of the deck space is taken up with cargo or material and that there is access for the full
length of the deck. Both port and starboard rescue zones shall be kept clear.
The vessel’s crew to be fully conversant in all aspects of the roles and responsibilities of FSV as
stated in section 4.2 of this document.
It is the Master's duty to hold regular drills and exercises to ensure that the crews are fully
prepared to render assistance in a competent and efficient manner by participating in planned
offshore platform/facilities drills in addition to relevant regulatory requirement.
Training to be conducted onboard or ashore with the crews to ensure that they are familiar with
any special equipment that is supplied for use in working condition.
There should be a continuous communications link on a dedicated channel between the FSV and
the control/operations room on the platform/facilities. The FSV bridge should be manned 24
hours a day.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 42 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 43 of 145
5.1 OBJECTIVE
The objective of this section is to identify the limiting criteria, balance safety and operational
requirements while determining the safest way forward at marginal weather.
Wind speed is the average speed of the wind over a 10-minute period at a height of 10 metres
above the surface. As a guide, double the wind speed in knots to convert to kilometres per hour;
for example, 20 knots is approximately 40 km/h.
Gusts are increases in wind speed lasting for just a few seconds. The speeds are typically 30 to 40
per cent higher than the average wind speed, but stronger gusts are likely in the vicinity of
showers, thunderstorms and frontal systems.
A squall is an abrupt and large increase in wind speed that usually only lasts for minutes then
diminishes rather suddenly.
Swell waves are the regular longer period waves generated by distant weather systems.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 44 of 145
An ocean current is a seasonal directed movement of seawater generated by forces acting upon
this mean flow, such as breaking waves, wind, temperature and salinity differences, while tides
are caused by the gravitational pull of the Sun and Moon.
Wind-driven current hence is termed residual currents. Some other non-cyclic factors for current
include turbidity and landslide. They are intense in velocity and are not predictable but can be
monitored if the suspected potential area is known.
5.2.4 Current Speed
Current speed is measured based on the time average. For the operational purpose, the time base
for ocean current data is 10-minute average up to 1-hour average.
5.2.5 Tropical storms (TS)
Below are the statistics of tropical storms generated by North West (NW) Pacific Ocean over a
nominal one-year period. However, it is difficult to predict the correct number of tropical storms
activity that would happen in the year.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 45 of 145
NE Pacific &
Beaufort N Atlantic NW Pacific NW Pacific N Indian Ocean SW Indian Ocean Australia & S Pacific
10-minute sustained winds
scale UN (NHC) / US US (JTWC) Japan (JMA) India (IMD) France (MF) Aust (BOM) / Fiji (FMS)
(CPHC)
Zone of Disturbed
0–7 <28 knots (32 mph; 52 km/h) Depression
Weather
Tropical Depression Tropical Depression Tropical Disturbance
28–29 knots (32–33 mph; 52–
7 Tropical Depression Tropical Disturbance Tropical Depression
54 km/h)
Deep Depression Tropical Low
30–33 knots (35–38 mph; 56–
8 Tropical Depression
61 km/h)
34–47 knots (39–54 mph; 63– Moderate Tropical Category 1
9–10 Tropical Storm Tropical Storm Tropical Storm Cyclonic Storm
87 km/h) Storm tropical cyclone
48–55 knots (55–63 mph; 89–
11
102 km/h) Category 2
Severe Tropical Storm Severe Cyclonic Storm Severe Tropical Storm
56–63 knots (64–72 mph; tropical cyclone
104–117 km/h)
Category 1 hurricane
64–72 knots (74–83 mph;
119–133 km/h)
73–83 knots (84–96 mph; Very Severe Category 3 severe
Category 2 hurricane Tropical Cyclone
135–154 km/h) Cyclonic Storm tropical cyclone
84–85 knots (97–98 mph;
Typhoon
156–157 km/h) Category 3 major
86–98 knots (99–113 mph; hurricane
12+
159–181 km/h) Category 4 severe
Typhoon
99–107 knots (114–123 mph; Extremely Severe Intense Tropical tropical cyclone
183–198 km/h) Cyclonic Storm Cyclone
108–113 knots (124–130 mph; Category 4 major
200–209 km/h) hurricane
114–119 knots (131–137 mph; Category 5 severe
211–220 km/h) Very Intense Tropical tropical cyclone
Super Typhoon Super Cyclonic Storm
>120 knots (140 mph; Category 5 major Cyclone
220 km/h) hurricane
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 46 of 145
5.3 SQUALL
Squall is a line of a thunderstorm that can span hundreds of kilometres. It forms from the merging
of small groups of thunderstorms into a long line of thunderstorms. However, unlike
thunderstorms, squalls are longer lived.
Squall causes a sudden increase in wind speed in the magnitude of greater than 16 knots and gust
that can last for one minute. In Malaysian waters, squalls can be destructive as the peak can go
up to 60 knots. Another special feature of a squall is the sudden change in wind direction. The
squall is usually oriented perpendicular to the main wind flow.
Squall is difficult to predict as it usually takes 4 to 6 hours to form, which is roughly a similar time
frame to forecast.
Recommendation for working beyond the trigger condition requires additional consideration and
approval from management to proceed as some of the solutions will incur additional cost and
additional HSE requirement such as Permit to Work, Job Hazard Assessment and other relevant
HSE mitigations.
These trigger tables are developed by the project team together with the shipowners
representatives during a workshop and does not overwrite the Marine Manual of Permitted
Operations (Marine MOPO) or more stringent site specific MOPO. Please refer to Appendix 1 for
Marine MOPO.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 47 of 145
Seismic acquisition is a data-dependent operation where the vessel is towing multi-streamers and
acoustic sources. The typical capability of a seismic acquisition vessel runs at a surface current of
4 knots on average. Even though adverse weather may not be the main trigger to halt work on a
seismic acquisition vessel, it is important that the safety of crew members is not compromised.
2 Significant Wave
Height (Hs) 1. Check data quality. If exceed acceptable tolerance, stop the acquisition.
<2.5 m 2. No crew change via boat transfer.
3. Lifting precaution during streamer and gun source retrieval.
3 Surface Current
1. Check data quality. If bad, stop.
<2 knots
2. Check on the current direction that will influence the feathering angle
allowance of the seismic streamer cables.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 48 of 145
< 25 knots 2. Check data quality. If quality exceeds acceptable tolerance, stop surveying.
3. Check on wind direction and speed frequently.
4. Stop surveying, secure equipment and take shelter.
2 Significant Wave
Height (Hs) 1. Check data quality. If quality exceeds acceptable tolerance, stop surveying.
At 2.5 m
2. No drop core sampling activity. Refer to IMCA M 187, lifting operations
guideline.
3 Surface Current
<2 knots 1. Check data quality. If exceed acceptable tolerance, stop surveying.
2. Check on current direction and speed frequently.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 49 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 50 of 145
< 25 knots 2. Check consistency with platform design if load exceed the loads that the soft
mooring is designed for.
3. To ensure barge station keeping, maintain BMS positioning system.
4. Secure loose items.
5. No crew and materials transfer beyond 25 knots.
6. No lifting activities to take place if the vessel rolls more than 3 degrees Port to
Starboard or vice versa.
3 Roll & Pitch No lifting and anchor handling activities to take place if the wind reaches more than
At 3 degrees 25 knots.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 51 of 145
For heavy lifting operations during unfavourable weather condition, it is the responsibility of the
Chief Officer to supervise at all times. If the CSR with the advice from the barge master is in
agreement that the work can safely continue, specific PTW and JHA to be produced.
2 Significant Wave 1. Refer to (Towing, Mooring and Anchor Handling Guideline – Section 9) & (CIMMV
Height (Hs) – Section 3 and MOPO – APPENDIX 1).
<2.5 m 2. No personnel transfer and materials transfer if sea swell height is higher than
2.5 metres.
3. No anchor handling activities should take place if sea swell height more of 2.5 s.
4. Maintain BMS (Barge Management System) positioning system to ensure barge
station keeping, if any.
5. Check real-time data from wave monitoring buoy/ weather station.
6. Secure loose items.
7. No berthing activities should take place if sea swell height is more than 2.5
metres.
8. No bulk cargo transfer should take place if the wind reaches more than 25 knots.
9. Refer site-specific Pull-out Procedure
10. If the weather becomes severe, and the master is of the view that it is not safe
to be at the location, the barge to redeploy anchor or release all for shelter.
11. Check mooring wire tension meter and record the reading every hour. If the
tension wire (weather side) meter reading is more than the permitted as per
barge SOP, prepare for emergency pull out and refer to Emergency Pull Out
procedures.
3 Roll & Pitch No lifting activities should take place if the vessel rolls more than 10 degrees Port to
10 degrees Starboard or vice versa. For a long duration event, stop work and prepare for
emergency pull out.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 52 of 145
Before all critical lifts, a 72 hours weather window to be confirmed from weather forecast reports.
Trigger Precaution HSE/Operationally:
1. Barge Superintendent to consult with CSR on suspension of operation
1 Wind
planning.
< 25 knots
2. Cease all operation if necessary.
2 Significant Wave
Height (Hs) <2.5 m 3. Connect static tow., if applicable
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 53 of 145
Table 11: Trigger table for Anchor Handling Tugs/ Supply Vessels (AHT/S)
5.4.9 Fast Crew Boat
The main consideration for fast crew boats is for the transferring of crews.
Trigger Precaution HSE/Operationally:
1 Wind
At 25 Knots/13m/s or 1. Remain outside the 500m zone to avoid collision with the platform or other
vessels.
more Or
2. No personnel on open deck area.
Significant Wave 3. Secure loose items.
Height (Hs)
4. During severe sea state, proceeds to shelter.
At 2.5 m or more
5. Refer to the Marine MOPO
In addition, it is extremely crucial that the HSE requirements are adhered to during this season.
The six mandatory HSE requirements during monsoon are as follow:
i. Strict compliance with ZeTo Rules.
ii. Stringent equipment inspection prior to marine spread mobilization.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 54 of 145
iii. No activities e.g., anchor handling, berthing, lifting, personnel transfer etc. to be carried
out if the wind speed is more than 25 knots and sea swell/ Hs above 2.5 metres.
iv. Develop and communicate specific JHA for all activities.
v. Close monitoring to be kept for sudden wave and sea awash the main deck. Ensure
sufficient free deck space available for the crew to escape from any danger.
vi. Obtain frequent weather forecast daily for a better weather analysis during monsoon. To
stop work if such operation may endanger crew life and vessel safety where Stop Work
Policy may be applied.
5.6.1 Towing operation
The diving contractor should have guidelines and weather limits for working in adverse weather,
written relative to the capability of the vessel or floating/ fixed structure. Local weather forecasts
should be consulted before commencing any diving operation. The diving operation should be in
line with the Marine MOPO.
While divers underwater may not be directly affected by the various effects of weather, these can
have an effect on diving operations in a number of different ways:
i. Wind speed and direction can make station-keeping difficult for the support vessel/ floating
structure;
ii. Rain and fog will cause a reduction in surface visibility, possibly creating a hazard for the
support vessel/floating structure;
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 55 of 145
iii. Bad weather can make working on deck extremely hazardous for the diving crew,
particularly with adverse combinations of wind, rain, snow, etc.;
iv. Hot weather can cause overheating. In particular, umbilical stored on deck are more
susceptible to overheating by warm air or direct sunlight;
v. Extreme heat, including direct sunlight or cold, can cause the temperature inside deck
chambers to rise or fall to dangerous levels. In such conditions the internal temperature
should be monitored and kept at a comfortable level;
vi. Extreme heat, including direct sunlight, or cold can adversely affect divers acting as standby
divers who will be static but dressed in most of their diving equipment.
vii. Arrangements should be made to keep the standby diver sheltered, at a comfortable
temperature and well hydrated.
ix. Operations should, therefore, be carefully monitored with regard to the safety of both
personnel and equipment.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 56 of 145
The scope of this section is to screen and ensure the marine crew is capable to perform the
operational requirement effectively.
In doing so, the vessel crew screening guideline will ensure that the competency, skill and
experience of the personnel engaged and assigned for the work on the vessel is aligned with the
requirement of Oil and Gas industry.
The vessel crew is the personnel involved in vessel operation carrying out specific duties to ensure
the vessel is running safely and efficiently. Each crew member has his/her own special function
and schedule to run the vessel operation for 24 hours and as long as he/she is at sea.
This section covers the marine crew of Offshore Support Vessels (OSV).
The main objectives of this section are as follows but not limited to:
i. Standardize the requirement for engagement of marine crew for PETRONAS operations.
ii. Establish a mechanism to control the marine crew who are not preferred due to the
previous history in the industry.
This section involves the verification process and if necessary interview process and the result of
behaviour through observation based on the actual trial. These actions will eventually reveal
sufficient information about a person’s competency, skill and experience.
In addition, verification of a person’s document will provide an indication that the person is
competent and has been trained.
The overall process is a management procedure that ensures the person engaged by the
contractor to work for PETRONAS is capable and satisfies the contractual requirements.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 57 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 58 of 145
6.2.1 Master
The person of overall in charge of the vessel who is solely responsible for the safety of the crew
and the vessel at all times. He/she is the ship owner’s representative and accountable for safe
operations of the vessel.
6.2.2 Chief Officer
The second in command in the vessel organization and reports to the Master. He/she is in charge
of the vessel maintenance and cargo operation. He/she is at times, replaces Master in term of
manoeuvring the vessel.
6.2.3 Chief Engineer
Responsible for the safe operations of the vessel’s machineries. He/she is the person in charge of
the Engine Department and reports to the Master.
6.2.4 Second Engineer
He/she assists Chief Engineer for the maintenance of the vessel machineries and equipment.
He/she reports to the Chief Engineer.
6.2.5 Dynamic Positioning Officer
All certificates of competency (COC) held by the Master, Officers and crew shall be issued by the
Marine Department, Ministry of Transport, Malaysia or respective country authority. The type of
certificates shall be compatible with the voyage limit of the vessel.
6.3.1 Supplementary certificates
The supplementary certificates shall be valid, issued or recognised by the Marine Department,
Ministry of Transport, Malaysia or respective country authority or recognised governing bodies
(for DP). For oil and gas safety training, the certificates shall be issued by PETRONAS’ approved
training providers.
For foreign officers having issued with Certificate of Competency (COC) from respective country
authority, the Certificate of Recognition (COR) shall be issued by Marine Department Malaysia.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 59 of 145
The concept of taking precaution and mitigation action is adopted in this screening process. This
is to ensure that the possibility of risk associated with the personnel engaged for the particular
job can be eliminated or controlled to an acceptable level ALARP (As Low As Reasonably
Practicable)
Contractors to ensure:
i. The Master and Chief Engineer have a minimum of two (2) years of oil and gas experience.
ii. Other Officers and Ratings requirements are as per Exhibit VI - Crew Details in the contract
document.
6.4.1 VERIFICATION BY PETRONAS
The contract holder should have sufficient information to conduct the screening. He/she should
conduct a complete review of the information from the original documents or an officially verified
copy carried by the person. Verification of the documents is critical to ensure that it is properly
endorsed and signed by the appropriate authority.
The screening process is required to address and verify the following requirements:
i. To ensure that the documentation is valid.
ii. To ensure that the person is familiar with the job and possess the necessary skills and
experience.
iii. To ensure the understanding of PETRONAS HSE policies.
iv. AAE for Senior Officers
Documents should be viewed for their validity and to see if there are any limitations, sanctions
associated with the documents. Certification and details for individual crew should include the
following:
Personal details:
i. Curriculum Vitae (CV)
ii. medical fitness status – Medical Fitness Certificate approved by Marine Department and
PETRONAS Approved Medical Examination
iii. Ability to converse in English
Employment details:
i. Experience – ship type, rank & tour of duty
ii. Area of operation
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 60 of 145
Manager of the contract holder should be accountable to approve the acceptance of the vessel
crew. On completion of the screening process, the contract holder satisfied with the result should
then recommend the decision to the respective manager for approval.
The vessel owner/operator to upload to the crew screening system at least 3 days in advance, to
provide ample time to contract holder to carry out the process. The following documentation to
be uploaded for the process.
6.5.1 Documentation Required
i. Medical Report:
a) Original copy to be kept by agent/owner
b) Photocopy to be kept by PETRONAS
ii. Copies of
a) Certificate of Competency (COC) for Malaysian - Deck Officers/Engineers as per
STCW requirements.
b) Certificate of Watch Keeping for Malaysian - Able Seamen (AB), Oiler/Greaser
c) Certificate of Recognition (COR) for foreigners issued by the Marine Department of
Malaysia.
iii. Original documents or an officially certified true copy of Discharge Book (Seamen’s Book).
iv. Curriculum Vitae (CV)
v. Original documents or an officially certified true copy of additional training:
a) Basic Rigging & Slinging (for Deck Crew)
b) Food Handling (for Cook)
c) Helicopter Underwater Escape Training (HUET) (where required such as for crew
change using helicopter)
vi. PETRONAS Offshore Safety Passport (OSP)
6.6 INTERVIEW PROCESS
If deemed necessary by the shipowner/operator, an interview session should take place. The
interview should abide by the followings:
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 61 of 145
Contractor to record and update the appropriate vessel file for reference and auditing purposes.
All records to be retained for a period of contract.
The contractor should ensure all records on the crew screening process is maintained and to
establish a mechanism to control over the marine crew who are not preferred due to the previous
history in the industry. Consideration should be given to maintain a computerized database for
the information.
It is the responsibility of the contract holder to ensure all marine crew are properly screened via
crew screen system prior to working onboard a vessel that engaged in PETRONAS operation.
Contract holder should be responsible to conduct the vessel crew screening process. In case
he/she is not on-site available he/she may delegate to his / her subordinates who are trained and
possess the knowledge, skills and experience to conduct the crew screening process.
6.9 NON-APPROVAL / REJECTION
Infringement of the requirements may lead to a non-approval of the marine crew and render
them not to be accepted. This may be due the following issues;
i. Failure to provide a valid certificate of competency.
ii. Failure to provide necessary safety training certificates.
iii. Failure to provide drug and alcohol medical check-up.
iv. Involved in serious police case or contravening with the law and regulation.
v. The crew that has been suspended by PETRONAS.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 62 of 145
vi. Other relevant issues with the crew e.g. attitude, disciplinary, skill and
competency issues, on which the contract holder has the ground and evidence
that the crew is not suitable for the scope of work.
The crew who fails the screening process to be replaced with an acceptable person.
Final acceptance is the sole discretion of PETRONAS upon complying with these requirements and
national regulations.
6.10 SHIP OWNER RESPONSIBILITY
It is the crew’s responsibility to keep training and certificates valid whilst working with a vessel
contracted to PETRONAS. The documentation kept by the contract holder is a measure of control
to ensure all vessels engaged by PETRONAS are valid at all times. This is to avoid any untoward
incidents which may lead to fines or arrest by the government authority which may eventually
lead to a delay in PETRONAS activities.
6.10.2 Familiarization assessment
For those with less than two years of experience in the oil and gas industry should be subjected
to an assessment. Master in command should be responsible to conduct an assessment and
report the result to the shipowner so that appropriate action can be taken. Shipowner later will
report the result and action taken to the contract holder for approval.
6.10.3 Tour of duty
A crew change to take place whenever the crew has worked on-board the vessel for a maximum
period as follows:
i. For Field Support Vessel (at location standby vessel) – a maximum of 60 days on-
board and a minimum of 10 days leave.
ii. For sector run (milk run) vessel including drilling support vessel – a maximum 90
days on-board and a minimum of 10 days leave.
The contractor may use this guideline in determining a marine crew acceptance for their own
recruitment process. However, for a marine crew expected to be working with PETRONAS, the
final acceptance subject to approval by PETRONAS’ contract holder.
6.11 COMMUNICATION
The general means of communication between the owner and/or agent and contract holder is
normally via telephone and email.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 63 of 145
All marine crew should comply with Standard Training and Certification for Watchkeeper (STCW)
95, as amended to Manila Convention 2010 required by the Marine Department. In addition to
the above, appropriate safety training should be attended by marine crew suitable as per
operation requirement.
As per PPGUA Vol 11- Marine Management, only medically fit personnel are allowed to work
offshore. The age of all marine crew in between minimum 18 years to maximum 60 years old for
PETRONAS Upstream activities. However, the marine crew that are above 60 years may be
considered subject to the compulsory Stress Test, prove fit to work in medical declaration, and
discretion of PETRONAS’s management.
All marine crew to undergo a medical examination to certify their fitness before joining the OSV
and Marine Support Craft for offshore operations. Below are the requirements:
i. Valid Medical Fitness Certificates (MFC) issued by the clinics or hospitals approved by the
Malaysia Marine Department.
ii. Valid PETRONAS Medical Examination issued by the clinics or hospitals which listed as
PETRONAS’ Approved Medical Examiners (AMEs) as per PETRONAS Guideline on Medical
Assessment of Fitness to Work for Offshore Workers.
iii. Valid Typhoid and Hepatitis A (if required) injection are required for all Cook and food
handlers.
Frequency of Medical Fitness and Examination for all marine crew should be in line with the
Malaysia Shipping Notices NPM 5/1999 MEDICAL AND EYESIGHT STANDARD FOR SEAMEN. The
marine crew who, while holding a valid medical certificate, suffers a condition covered by this
Notice which precludes seafaring, should arrange for an additional approved medical examination
as soon as possible after diagnosis, following which the revised medical certificates should be
issued. Frequency of medical fitness assessment to be determined by PETRONAS’ Approved
Medical Examiners (AMEs).
6.13 TYPE OF CERTIFICATES COMPETENCY AND THEIR LIMITATIONS
Type of Certificates of Competency required for Master and Crew serving each offshore support
vessel should meet the requirement of Safe Manning Certificate issued by the Marine
Department, Malaysia. The voyage limitation should be in accordance with the limitation
stipulated in the Certificates of Competency. Issuance of Certificates of Competency should be in
accordance with the requirement of IMO’s STCW (as amended) and be recognized by the Marine
Department, Malaysia.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 64 of 145
This guideline describes the normal operation for bunkering of Marine Gas Oil (MGO) / Diesel
Oil (MDO) from supply base to vessel, vessel to vessel, vessel to/from Offshore facilities e.g.
FSO, FPSO, drilling rig and barge.
It covers the activities performed by PETRONAS and or its agent personnel and vessels
personnel from requisition of the bunker to confirmation of receipt of the bunker.
This guideline is to provide a proper procedure for the safe and efficient bunkering of Marine
Gas Oil (MGO) or Diesel Oil at all locations.
7.1 ROLES AND RESPONSIBILITY
The following details the Roles and Responsibilities of the principal personnel associated with
fuel bunkering.
7.1.1 Offshore Installation Manager (OIM) / Company Site Representative (CSR) / Drilling Supervisor
Stand-by at Jetty during the bunker loading operation. Liaise with the supplier via the agreed
channel of radio trucking or radio VHF. Ensure pre-transfer toolbox meeting take place
onboard the vessel before bunkering operation begins. Completion and signed off bunkering
Pre-Loading Plan (Appendix 6) and Safety Checklist (Appendix 7). To witness the task of
independent surveyor if any.
7.1.3 Bunker supplier
Establish proper and effective communication for the bunkering operation. Operate loading
pump for starting and stopping bunker operation and to agree on emergency shutdown
execution. It is recommended that the Certificate of Quality (COQ) is provided by the supplier
prior to the bunkering operation.
It is recommended that supplier to provide a surveyor to witnesses the shore tanks gauging
prior bunkering.
Internal
64
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 65 of 145
This sample is to be used solely for the determination of compliance with Annex VI of MARPOL
73/78. In compliance to MARPOL 73/78 Annex VI requirement, also to note that the details of
fuel oil for combustion purposes delivered to, and used onboard the ship, to be recorded in
the bunker delivery note which contains at least the information specified as below:
Port
Date of commencement of delivery
Name, address, and telephone number of the marine fuel oil supplier
Product name(s)
Quantity (metric tons)
Density at 15°C (kg/m3)
Sulphur content (% m/m)
Note: A declaration signed and certified by the fuel oil supplier's representative that the fuel oil supplied is in
conformity with the above regulation.
i. Sampling methods
The sample should be obtained using one of the following methods:
a) manual valve-setting continuous-drip sampler
b) time proportional automatic sampler
c) flow proportional automatic sampler
The sampling device should be of a type approved in accordance with one of the
following standards:
a) ISO 3170
b) ASTM D 4057
c) BS 3195
Sample bottle kits will complete requirements for sampling equipment on board.
To facilitate cross reference, details of the seal identification may also be recorded on the
bunker delivery note.
In all cases, each Master remains responsible for the safety of his own ship, its crew and
cargo, and should not permit such safety to be prejudiced by the action of others.
Internal
66
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 67 of 145
Requisition for bunker has to be made to the Logistics Supply base via agreed communication
means.
Logistic Department will send a bunker requisition to the Supplier by fax or email or using the
appropriate document.
Request by vessel or installation should be made at least 24 hours if required prior to the
supply.
7.2.2 Hoses
The hoses used for bunker transfer should be specially designed, constructed, certified for
handling petroleum products and be of strength and size suitable for actual operation.
The hoses should be of adequate length to allow movement of vessel and jetty/installation
due to swell.
Hose end coupling to be properly marked to avoid mixed up with other hoses.
Vessel to provide 2 lengths x 60 ft x 3” size reinforced rubber hoses complete with camlock
couplings. Various sizes of reducers; 3” to 2” and 4” to 3” are required. It to be fitted with a
self-sealing or quick shut off valve mechanism at the end of the hose to prevent spillage. A
highly visible colour floatation collar to be fitted along the hose section.
Hose to be hydro-tested to at least 1.5 times of it working pressure annually and date of
testing to be marked on the hose. It is recommended that hose should be changed out
approximately every five (5) years or when it deemed necessary due to internal fatigue or
visible damage to the hose layers. The record should be maintained & produced upon request.
7.2.3 Operation readiness
The vessel securely moors at the jetty/installation and permission is given to conduct the
operation.
Prior bunkering, Master to ensure the tank is acceptable and ready to receive bunker. The
tank to be free of water and contamination.
Internal
67
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 68 of 145
The vessel to be provided with water and gasoline finding paste to aid the accuracy of
sounding.
Tank gauging for all nominated and non-nominated tanks to take place prior commencement
and completion of each bunkering operation.
Tank gauging and sampling are recommended to be conducted by the independent surveyor
and be witnessed by PETRONAS representative.
If there is a substantial amount of water or contamination found in the tank, then it has to be
reported to supply base immediately. The bunkering should not commence and water and
contaminants should be drained/removed on instruction/confirmation of Base
Superintendent until found satisfactory.
Whilst calculating the Remaining On Board (ROB), the vessel to apply the trim correction and
interpolate to ascertain actual quantity. In the event of the trim and list correction tables are
not tabulated for the maximum values, the Master to ensure that the vessel is even keel and
upright or within the tabulated correction limit prior gauging process.
The sampling of MGO / diesel oil should be done on commencement, during and upon
completion of the bunkering process.
1. Pre-Loading Plan
Prior bunkering, the Pre-Loading Plan (Appendix 6) to be completed by the Person in
Charge and posted near the point of transfer.
2. Pre-Transfer Tool Box Meeting
The Pre-Transfer Toolbox meeting to be taken place onboard the vessel, in person,
between the Person in Charge, before bunkering operation begins and should cover the
following:
3. A review of each item on the Bunker Safety Checklist (Appendix 7) and flow meter
calibration records.
4. A discussion on the initial flow rate and maximum allowable flow rate, emergency
shutdown procedures and topping off.
5. Communication procedures between shore and vessel involved.
6. Start-up and Shutdown Criteria
7. Bunkering should not commence unless the following criteria are met:
i. All the conditions of the Pre-Transfer Tool Box meeting are met.
ii. All the conditions of the Bunker Checklist are met.
iii. Either visual, voice or radio contact to be maintained by both parties.
iv. Topping off is discussed.
Internal
68
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 69 of 145
If the weather or sea conditions deteriorate to such an extent that there is any doubt
regarding the safe operation, it should be terminated.
If any oil spills or other incidental pollution occur, the contingency plan should be brought into
operation which includes immediate reporting to Supply Base on the agreed communication
system.
The hose should be drained and blinded before being brought back to the jetty.
Any variance of bunker received and supply to be recorded and letter of protest (LOP) is to be
issued.
Night bunkering activities is not recommended. However, due to some circumstances, such a
requirement cannot be avoided. If it is required, prior to night bunkering activities, a joint risk
assessment to be conducted by OIM and Master of the vessel. Additional lighting is provided
and only a single operation is to be permitted.
7.5 COMMUNICATION AND REPORTING
Master of the vessel to report ROB on daily basis to Logistics Operations as per respective unit
reporting format.
The vessel owner to ensure these reports are sent to the respective base on a daily basis.
In addition, the following report should be sent to the Logistics Supply Base.
Internal
69
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 70 of 145
any interruption or incident during bunker transfer operation e.g. bunker transfer is
abandoned due to bad weather or for any reason whatsoever; oil spill, flow meter
malfunction, etc.
The pre-loading plan to be retained on-board with bunker safety checklist and letter of protest
if any for the duration of the contract.
The vessel Master or deck officer in charge shall make an entry in the vessel deck log book
stating that the Pre-Transfer Toolbox meeting was conducted by the Person in Charge of
bunkering.
Upon completion of bunkering, vessel Master or his/her designee to sign Bunker Delivery
Receipt issued by the supplier and retains one copy on-board.
All fuel transfer carried out is to be entered into the sounding book, Oil Record Book Part 1 -
Machinery Space Operations (All Ships of 400 GRT and above) and engine room as well as deck
log book.
7.7 SAFETY PRECAUTIONS DURING BUNKERING
i. The vessel to be securely moored alongside jetty /vessel. Ensure that vessel mooring
line are attended to a regular basis to check if any excessive tension.
ii. Bunkering to the facility may be allowed by station-keeping manually or in Dynamic
Positioning mode. A joint Risk Assessment should be prepared to demonstrate risk
reduced to ALARP level. For station keeping manually, a vessel needs to be on standby
in the vicinity in case of any emergencies e.g. engine breakdown etc.
iii. Ensure fuel transfer hose is in good condition (e.g. no kink, not damaged etc.) with
sufficient length of hose and properly lashed.
iv. The hose to be fitted with quick release coupling (cam lock) to cater for emergency
situation.
v. The vessel’s crew to be responsible to ensure hose’s connection/disconnection is
properly executed and cleaned up of any spill.
vi. For bunkering at an offshore location, Duty Engineer to be stationed at fuel emergency
stop button located on the bridge and act immediately in case of emergency.
vii. Communication between Deck Officer on duty, Able Body(AB) and Barge personnel
should be maintained at all times to monitor the fuel transfer operation.
viii. Minimum oil spill equipment (e.g. sawdust, pail, shovel, absorbent rags, etc.) should
be ready at all times to cater for any spill.
ix. All deck scuppers to be plugged during the fuel transfer operation.
x. The main engine to be on standby mode at all times during fuel transfer operation and
ready to be used in case of emergency and vessel can immediately cast off.
xi. Commence transferring of fuel with a lower pumping rate and gradually increase to
permitted flow rate.
xii. Any spill overboard to be reported immediately to the Supply Base duty personnel /
OIM.
xiii. The sequence of tanks to be bunkered to be agreed upon by the responsible vessel
officer and Supply Base/platform personnel.
Internal
70
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 71 of 145
xiv. Before commencing fuel transfer, at least two (2) appropriate portable fire
extinguishers are to be available near the fuel transfer manifolds.
xv. Flag “BRAVO” to be hoisted to indicate that fuel transfer is in progress.
xvi. At night, a single all-round red light is to be displayed.
xvii. The duty officer onboard vessel, platform and/or in charge personnel at supply base
should be in attendance at all times during the fuel transfer. A regular sounding of each
tank is to be carried out to ensure no overflowing.
xviii. Fuel transfer to be suspended in the event of thunder and lightning within the vicinity.
xix. Hot work is not permitted onboard vessel during fuel transfer activities.
xx. Oil spill kit to be made ready at bunkering point for immediate use.
xxi. Bunkering activities should not be carried out in adverse weather or sea condition
(Refer to the Marine MOPO).
It should be possible to stop bunkering supply immediately upon request. Delivering station
emergency shutdown point is to be manned at all time. Testing of the equipment to be carried
out by Chief Engineer prior to any bunkering and result to be recorded in engine logbook.
7.7.2 Training
The person in charge of bunkering at the vessel, jetty, base or platforms to be trained to follow
this guideline with an emphasis on the Pre-Transfer Tool Box meeting and items for which the
personnel is responsible. This training session should include all crew members who are likely
to assist in the bunkering operation. The following should be included in the training:
i. Bunker Pre-Loading Plan (as per Appendix 6)
ii. Bunker Safety Checklist (as per Appendix 7)
iii. Tank gauging/sampling
iv. Deck watch requirement to monitor for oil spills.
v. Shutdown procedures which allow personnel to immediately shut down the
bunkering operation.
vi. Emergency response in case of spillage including drill
vii. Communication procedures
The vessel Master should make an entry in logbook noting that training was conducted by
the Person in charge and recording the names of the crew of those who attended.
Internal
71
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 72 of 145
This section describes proper procedure and standards for mooring system for offshore fields.
Offshore mooring buoys are deployed for the purpose of mooring smaller vessels like the
Landing Craft Tanks (LCT), field standby vessel, crew boats and material barges at offshore
locations with water depth, not more than 100 metres.
Offshore mooring buoys should only be deployed in places where there are high marine
activities and for the platform with living quarters.
For FSO and FPSO, site assessment on prevailing wind and sea including the route of tanker
approaches need to be carried out in determining the suitable location to deploy the buoy
8.1 OBJECTIVES
i. Quick mooring and unmooring, this is especially vital to area standby vessels to
respond to emergency situations.
ii. No risk of accidental anchoring on pipelines.
iii. Securing point.
iv. Fuel-saving.
8.2 MOORING SYSTEM STANDARDS
This section provides a minimum standard of the mooring systems. This is to accommodate
the different needs of the mooring system subject to the sizes of vessels.
The minimum standards for the mooring buoy system are defined as per:
Table 13 - Vessel of 500 Gross Registered Tonnage (GRT) and above.
Table 14 - Vessel of less than 500 Gross Registered Tonnage (GRT).
Table 15 - Selection of Anchor
Figure 7 - Offshore Mooring Systems
Figure 8 - Crucifix Buoy for Vessel of more than 500 GRT
Figure 9 - Crucifix Buoy for Vessel of less than 500 GRT
Figure 10 - Flipper Delta Anchor (7 or 3 tons)
Figure 11 - Danforth Anchor (7 or 3 tons)
Figure 12 - Anchor Chain and Arrangement
Figure 13 - Primary Anchor Wire
Figure 14 - Buoy Shackles 35 tons SWL
Figure 15 - Polypropylene Rope
Figure 16 - Anchor / Pick Up Buoy
Internal
72
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 73 of 145
The table below provides minimum standards of mooring system for a vessel of 500 GRT and
above. However, maximum vessel deadweight of 7000 tons is allowable to moors in calm
weather.
Offshore Mooring System (up to 100 metres depth of water) (See Figure 7)
Buoy (A) Anchor (B) Anchor chain (C) Anchor Wire (D)
Crucifix buoyancy 7 tons Flipper Delta or 30 mm diameter 2” diameter of wire x
tank with a cross. Danforth anchor chain x 27 m long 60 m (min) or (Water
Minimum buoyancy (Figure 10 & 11) (approximate one depth + 30%) =
of 3 tons. Painted See also table for shackle) whichever is higher
with highly visible selecting anchor type (Figure 12) (Figure13)
colour (Table 15)
(Figure 8)
Offshore Mooring system (up to 100 metres depth of water) (See Figure 7)
Buoy Chain (C) Buoy Shackle (F) Mooring Rope with Pick Up Buoy (H)
floating sleeve (G)
30 mm diameter 35 tons shackle 20 m long Buoy net inflatable,
chain x 2 m long (Figure 14) polypropylene or Red 15" x 20" L x 48"
(Figure 12) nylon rope. circ. with a minimum of
(Figure 15) 30 mm diameter x 3m
long synthetic rope.
(Figure 16)
Table 13 - Vessel of 500 GRT and above
Internal
73
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 74 of 145
The table below provides minimum standards of the mooring system for a vessel of less than
500 GRT. However, maximum vessel deadweight of 3000 tons is allowable to moors in calm
weather.
Offshore Mooring System (up to 100 metres depth of water) (See Figure 7)
Buoy (A) Anchor (B) Anchor chain (C) Anchor Wire (D)
Crucifix buoyancy 3 tons 30 mm diameter 2” diameter of wire x
tank with a cross. Flipper Delta or chain x 27 m long 60 m (min) or (Water
Minimum buoyancy Danforth anchor (approximate one depth + 30%) =
of 3 tons. Painted (Figure 10 & 11) shackle) whichever is higher
with highly visible See also table for (Figure 12) (Figure 13)
colour selecting anchor type
(Figure 9) (Table 15)
Offshore Mooring system (up to 100 metres depth of water) (See Figure 7)
Buoy Chain (C) Buoy Shackle (F) Mooring Rope with Pick Up Buoy (H)
floating sleeve (G)
30 mm diameter 35 tons shackle 20 m long Buoy net inflatable,
chain x 2 m long (Figure 14) polypropylene or Red 15" x 20" L x 48"
(Figure 12) nylon rope. circ. with a minimum of
(Figure 15) 30 mm diameter x 3m
long synthetic rope.
(Figure 16)
Type of seabed
Anchor Class IV
Class I Sands Class II Mud Class III Stiff clays
Heterogeneous
Recommended Recommended
Flipper Delta Do not use Do not use
Application Application
Recommended Recommended
Danforth Can use Do not use
Application Application
Table 15 – Selection of Anchor
Internal
74
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 75 of 145
Internal
75
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 76 of 145
Weight W F TL H
kg lbs mm In mm in mm in mm in
3000 6615 2830 111 3/8 2285 90 3380 133 1070 42 ½
7000 15435 3750 147 5/8 2995 118 4440 174 7/8 1405 55 3/8
Figure 10 - Flipper Delta Anchor (7 or 3 tons)
Internal
76
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 77 of 145
A B C D E
Weight
kg lbs Mm mm mm mm mm
3180 7000 3120 2960 790 1880 1260
7260 16000 4100 4000 1047 2470 1660
Figure 11 - Danforth Anchor (7 or 3 tons)
Internal
77
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 78 of 145
Swivel (S.W)
Common Link (C) and Enlarge Link (E.L)
Internal
78
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 79 of 145
Internal
79
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 80 of 145
The buoy should be located preferably outside the platform parameter (more than a 500
metres zone).
Buoy to be located at a location free of pipeline/cable, subsea structure and not in the way of
supply vessel when approaching the boat landing or supply area of the platform.
The location chosen is suitable based on prevailing wind/current at the location so that at any
time should the rope parted or drag occurs, the vessel will not drift towards the platform.
Location of the buoy to be made known to all vessels plying to the location. The notification
to be made by supply base Marine Superintendent of Latitude / Longitude and Northing and
Easting of mooring buoy for TOPO chart. Notification to the authority is subject to the
requirement of the authority at each region/country.
8.6 MOORING LIMITATION
Buoy system as per Table 13, holding capacity is approximately 70 tons and able to take 7000
tons of drag of a vessel whilst buoy system as per Table 14, holding capacity is approximately
30 tons and able to take a drag of a vessel of 3000 tons.
Average gross tonnage of offshore support vessels is less than 1000 tons per vessel.
Taking into safety factor, the wind and sea condition, the number of vessels allowed to moor
at the offshore mooring buoy are as per table 16 below:
Prior mooring at Offshore Mooring buoy, all vessels to get approval from Offshore Installation
Manager (OIM) via Radio Officer of the platform.
Vessel Master to check on buoy condition such as buoy body, mooring line is in good condition
prior mooring.
All vessels should inform the radio room of the Mooring System condition before, during and
after mooring.
The maximum number of vessel can moor as per table 16. The first vessel to arrive at the
Offshore Mooring Buoy will secure the mooring line from the buoy on her bow (single moor).
The second vessel bow soft line will tie up to the first vessel stern mooring bitts (double moor).
The third vessel bow soft line will tie up to the second vessel stern mooring bitts (triple moor).
The practice of vessels securing other than tandem configuration is not allowed.
Internal
80
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 81 of 145
Master of each vessel is requested to inform to Offshore Installation Manager (OIM) at site if
they observe any damage to the buoys and moorings or found unsafe to be moored on to.
OIM will communicate the same to Marine Superintendent at Regions.
The bridge should be manned at all time during the stay at the mooring buoy.
Mooring to buoy does not relieve the Master from his obligation of responsibility and good
seamanship while at the location.
Internal
81
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 82 of 145
The following table below illustrates the frequency of the recommended inspection and/or
maintenance for each item of equipment.
EQUIPMENT TASK FREQUENCY RESPONSIBILITY
Buoy body Check structure Each mooring OIM / OSV Master
Assess paintwork Monthly OIM / OSV Master
Inspection of arrangement up to Not more than 6 months OIM / Logistic.
buoy pigtail
Anchor / Check buoy position 3 monthly (by vessel GPS). OIM / OSV Master
Anchor chains
and primary Underwater inspection and to Yearly OIM / Logistic
anchor wire retrieve by anchor handler and
inspect thoroughly. To replace worn
equipment.
Maintenance program to be captured in respective Platform Preventive Maintenance System and the
Mooring Buoy System to be treated as part of platform asset. Any missing mooring buoy or marker/
pick up buoy should be reported for replacement.
Internal
82
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 83 of 145
This section is applicable to towing, mooring and anchor handling activities carried out for
PETRONAS wide operation.
i. To ensure the safety of personnel involved in moving, towing, mooring and anchor
handling activities;
ii. To prevent damage to the environment, pipelines, sub-sea facilities and other marine
structures during all activities;
iii. To identify the responsibilities of all relevant parties involved in the execution of the
activities; and
iv. To stipulate guideline on the requirement of towing, mooring and anchor handling
equipment.
9.1 ROLES AND RESPONSIBILITY
The following describes the responsibilities of key personnel involved in the moving, towing,
mooring and anchor handling operations.
9.1.1 Company Site Representative (CSR)/Company Man
i. Is the designated PETRONAS representative onboard and as such is the sole point of
contact through which all rig/barge move notifications/exterior communications will
pass. In consultation with the relevant parties, he has the ultimate authority to stop any
unsafe operations from being carried out at site.
ii. To be accountable for PETRONAS interest for the safe and efficient operation at site.
iii. To promote HSE through implementing and leading good HSE practices at the worksite
to achieve incident-free operations.
iv. To liaise with the Rig Manager/Rig Mover with regard to rig move, towing, mooring and
anchor handling activities.
v. To liaise with the Barge Master/Barge Mover/ Workboat Master and Marine Controller
with regard to barge move, towing, mooring, anchor handling and workboat activities.
vi. To liaise between contractor rig/barge personnel and the PETRONAS management
onshore.
vii. To be responsible for accepting the vessels (Tow/AHT) on/off hire figures if applicable.
viii. To be responsible for accepting the final position at the location.
ix. To obtain Location Approval Certificate (if applicable) and an overview of infrastructure
on the seabed including verified information on sea bottom conditions and any
obstructions, and disseminate this information to Rig Manager/Barge Master/Rig
Mover/Workboat master and marine controller.
x. To refer to any approved procedure and Marine Manual of Permitted Operations prior
execution. Any deviation shall require approved PETRONAS Management of Change
(MOC).
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 84 of 145
i. Responsible to approve anchor pattern for ongoing and upcoming projects prior to
commencement of anchor handling activities;
ii. Responsible to screen appointment of Marine Controllers for PETRONAS.
iii. Approves deviation to existing anchor pattern in consultation with onsite PETRONAS
Marine Controller should the need arises;
iv. Liaise with PMT management on ongoing offshore activities on the need basis; and
v. His position resides in the main office as part of the operational team.
9.1.3 Marine Controller
vi. To ensure that all the operation adhered to planned procedures, international and local
regulations;
PETRONAS Marine Controller presence is required but not limited to the following:
b) Approaching a platform.
c) In-field towing.
d) Barge crawling within the field and in the vicinity of other barges and other subsea
facilities.
e) Salvaging operations within 500 metres of gazette area and/or close proximity to
subsea facilities etc.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 85 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 86 of 145
ii. The Positioning Surveyor to review the move procedures, especially the positioning
tolerances, and will accurately log the units‟ position and heading throughout the
move and anchor handling operations. he/she:
a) Prepare a report that captures all the important aspects of the positioning
operations.
b) Install, if possible, any and all required navigation packages on AHT/AHTS prior to
their departure from the present location.
c) Responsible for providing constant data showing the position of the unit at all
times during the move and during anchor handling and ensure that all relevant
field data is displayed on the navigation display screens as appropriate.
d) Utilize the Differential Global Positioning System (DGPS) to ensure that the jacket,
pipeline and anchors are positioned within the target area and corridor as
specified by PETRONAS.
e) The survey team onboard the rig/barge will operate the survey system to monitor
and guide the movements of the barge and anchor handling tugs and ensure that
safety zones around existing structures and pipelines will not be entered by the
rig’s/barge’s anchors.
f) Liaise with the Rig/Barge Mover and Marine Controller with respect to navigation
equipment status and position confidence.
g) Perform system checks to prove navigation system confidence prior to
commencement of the move and at intervals during the move operation. Any
failures/shortfalls in navigation equipment shall be immediately reported to the
Rig/Barge Mover and Marine Controller.
h) Ensure that all positioning systems on the unit and AHT/AHTS vessels are
operating correctly and highlight at an early stage any positioning problems which
could delay the operations or place any assets at risk.
i) Maintain detailed logs of all movements of the unit as advised by the Rig/Barge
Mover and Marine Controller.
j) Ensure that positioning equipment set up, operations and equipment
demobilization on the unit are carried out in a safe manner;
k) Immediately report all survey related incidents to the Rig Manager, Rig/Barge
Mover and Marine Controller/Appointed Marine Captain;
l) Check and endorse the final rig/barge position.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 87 of 145
d) Provision of Tug Management System onboard the two (2) minimum or more
Anchor Handling Tugs (AHT‟s) to continually monitor and display the Tug position
relative to anchor drop point, as prescribed from the rig/barge, and permit all
anchor drop and recover locations to be recorded automatically on the rig/barge.
Additionally, to provide for control and display at AHT position, heading and
speed at all-time onboard the rig/barge.
e) All anchor drops and recovery positions to be recorded, plotted and documented.
f) Provision of the BMS Display to the winch operators for correct control of barge
position along the proposed pipeline (for pipelay barge).
g) Provision of portable Ultra Short Base Line (USBL) acoustic positioning system and
mini beacons to track the position of a Remotely Operated Vehicle (ROV)
deployed from the barge and to position subsea structures.
h) Provision of BMS (if required) for standalone AHT.
i. The Rig/Barge Mover appointed is responsible for all aspects of the moving, towing,
mooring and anchor handling operation and as such his appointment should be
recorded in the logbook. All activities to be recorded and endorsed by the Rig
Manager/Barge Master.
ii. To be competent in all aspects of jack‐up (rig mover) movement including towing, afloat
stability, seaworthiness, navigation, appraisal of weather and passage planning:
a) Have suitable jack‐up experience and a working knowledge of jacking operations
(Rig Mover);
b) Review the planned routing and highlight any shallow patches, underwater
obstructions or hazards to navigation that may lie in or in the proximity of the
intended towing route;
c) To discuss the towing route with the appointed towing vessels;
d) To ensure the rig/barge is ready for the tow by inspecting the following, but not
limited to; Sea Fastenings, Mooring Systems, Tow Equipment and Arrangements,
Stability and Load Distribution, and Watertight Integrity Plan;
e) Familiar with the details of the arrival location, water depth, soil details,
anticipated penetrations and recommendations detailed within the Location
Approval Certificate;
f) Familiar with the positioning detail of the new location; platform configuration if
applicable, details of position tolerances and potential platform interference;
g) Familiar with the technical capabilities of the jacking system (Rig Mover);
h) To brief the anchor handling vessels on the procedures for the rig/barge move;
i) To execute anchor handling operation in a safe and professional manner in
accordance with the requirement;
j) To be responsible for the correct deployment of anchors associated with the
operations and should ensure that the equipment provided is fit for purpose;
k) To control the movement and actions of all vessels associated with the operations
after consultation with the Rig Manager and Marine Controller;
l) To communicate with assisting vessels on VHF radio;
m) To ensure that any and all additional marine equipment provided for mooring i.e.
pennants, shackles, anchors, etc., are certified and correctly recorded upon
deployment together with the purpose for which the equipment is deployed; and
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 88 of 145
n) To ensure that all unused items of mooring equipment are correctly manifested
for return on completion of the operations.
The vessel Master(s) will at all-time be responsible for the safety of their crew, vessel(s), and
during towing, the safety of the tow:
i. The designated lead towing vessel will be responsible for the tow and routing while
underway and will give direction to any secondary vessel(s) involved in the towing
operation;
ii. To have a clear understanding of the operations that they are to engage in and have
input at the pre-moving meeting or be advised on its content by the Rig/Barge
Mover/Marine Controller;
iii. To confirm that all machinery and propulsion systems are operational/available and
that their vessels are adequately manned to carry out continuous 24‐hour operations;
iv. To ensure their vessels are fully stocked with fuel, lubes and other essentials for at least
7 days continuous operation or otherwise instructed;
v. To ensure that crews, when working on deck, are suitably dressed with the correct
Personal Protective Equipment (PPE) for the job at hand; Hard Hat, Safety Boots, Safety
Glasses and a Life vest, etc.;
vi. To ensure that the appropriate navigation warnings are transmitted at regular intervals
throughout the passage, to warn other vessels of the rig/barge position and progress;
vii. To continuously monitor water depth during the operations at all time and aware of the
vessel and tow draft relative to available water depth, sea height and tide;
viii. To report to the Rig/Barge Mover for any change in condition onboard his vessel that
may affect the operation;
ix. Responsible for ensuring all move and anchor handling operation is carried out in
accordance with safe working practices and observe good seamanship;
x. To ensure that all anchor handling equipment is tested, inspected and in good order;
xi. To maintain the rig/barge towed in a safe position throughout the towing operation;
xii. To ensure that the equipment/machinery is regularly inspected, certified and remains
in operating condition;
xiii. To ensure compliance with the minimum manning requirements for navigation and
anchor handling activities;
xiv. To ensure that planned operations to be performed within current provisions for
working hours and rest periods unless 24 hours’ work requirement is required;
xv. To ensure that a safe Job Hazard Analysis has been performed in accordance with the
work specification;
xvi. To ensure that passage planning is carried out and made available prior sailing out to
location while on tow; and
xvii. To comply with PETRONAS CIMMV requirements.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 89 of 145
The Rig/Barge Engineer will have the responsibility of ensuring the correct operation of the
unit’s marine systems and equipment during the operations. He or she:
i. To provide an Afloat Stability calculation prior to commencement of the move and will
provide stability calculations in the elevated and preload conditions as appropriate
ensuring that any changes to the loading and distribution of weights upon the rig are
accounted for;
ii. To ensure the correct deployment of competent personnel and establish good
communication procedures between his personnel; and
iii. To ensure that all personnel are fully briefed on their duties and responsibilities with
regards to the operations.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 90 of 145
The selection procedure for the anchor handling tug is important for the work to proceed as
planned. Selecting the wrong vessel can result in a failure with much waste of time, money
and effort. Often when there is a failure the vessel is criticized without much thought being
given to whether the vessel is actually capable of performing the work in the first place.
The following parameters to be considered in determining the suitability of vessel
specifications.
9.2.1 Towing
i. The depth of the water and the condition at the bottom of the mooring site to
determine the vessel power and winch power;
ii. Estimated maximum sea/swell height, wind force and current to determine the vessel
size, engine and thruster power;
iii. The type and weight of anchor to be used to determine the size of stern gate, size of
roller and deck space;
iv. The size, type and length of the wire to be deployed to determine vessel power, winch
power and stopper system;
v. Method of deployment either by permanent chaser/buoyed system to determine
winch power, drum capacity, stopper size and type;
vi. The need to run piggyback anchor to determine deck space and pennant storage
capacity;
vii. The need to handle extra chain to determine locker capacity and gypsy size;
viii. Barge/rig winch-type and payout speed; and
ix. The need to run specialized mooring, combination support or preload to determine
deck space, work drums, storage reel capacity and numbers of combination stoppers.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 91 of 145
Towing vessel to be chosen based on a basic set of criteria which will specify the minimum
available towing force or by acceptable calculations depends on the area of operations which
may include Marine Warranty Surveyor requirements. Table 18 shows typical boat types /
specifications for a range of operations as reference to Oilfield Seamanship Volume 6 – Barge
Mooring.
NO. Rig/Barge Type and number of vessel
*1. Large semi-submersible drilling unit 2 x AHTS 12,000 BHP or
- 8 chain/wire mooring lines equivalent to 120T bollard pull
- Up to 130 metres of water depth
Open ‟ unobstructed location”
*2. Large semi-submersible drilling unit 3 x AHTS 12,000 BHP or
- 8 chain/wire mooring lines equivalent to 120T bollard pull
- Up to 150 metres of water depth
Obstructed location – wellheads/pipelines
3. Large pipelay barge 1 x AHTS 14,000 BHP or
- 12 wire mooring lines equivalent to 150 T bollard pull
- Up to 155 metres of water depth 1 x AHT 12,000 BHP or
- Engaged in pipe laying equivalent to 120 T bollard pull
1 x AHT 8,500 BHP or
equivalent to 100 T bollard pull
*4. Large work barge including tender/jack-up rig 2 x AHT 9,000 BHP or
- 12 wire mooring lines equivalent to 110 T bollard pull
- Up to 100 metres of water depth
Mooring alongside platform
5. Small work barge 2 x AHT 7,500 BHP or
- 8/10 wire mooring lines equivalent to 80 T bollard pull
- Up to 130 metres of water depth
Engaged in trenching/jetting
If the size of the vessel recommended is not available, two smaller vessels can be used in tandem
to assist in anchor deployment and retrieval.
*indicates propulsion assisted.
Table 18 – Typical specifications and number of the vessel require for towing and anchor handling.
This section describes procedures on rig move for Jack-up, Tender and Semi-Submersible Rig.
It also includes procedures on barge move when performing various engineering works at
offshore facilities.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 92 of 145
a) Time of the move and duration of the stay in the new location with emphasis
on expected weather and tidal conditions;
b) All towing vessels have sufficient consumables i.e. Fuel, lubricating oil, hydraulic
oil, drinking water and food for the intended duration of the move plus 25 % of
reserve (minimum 7 days);
c) Sub-sea survey report - any shallow gas, seabed obstructions, nature of the
bottom and expected penetration depth;
d) Towing route plan taking into account prevailing weather, navigation aids, en-
route, the proximity of shoals and other navigation dangers, towing draft, and
a contingency plan to cater for deteriorating weather, equipment/machinery
failure and port of refuge;
e) Prepare anchor patterns for approval for new locations, taking consideration of
departure of present location;
f) Any requirement for divers;
g) Presence of other marine units in the vicinity;
h) Stability calculation to be carried out and confirm capable to carry out the
intended job;
i) The pre-move meeting is attended by all interested parties;
j) Rig/barge owner/contractor to ensure that the rig/barge mover is onboard
prior commencing operations;
k) Vessel requirements as per Section 3 of this document; and
l) Complete the Pre-Move Plan.
m) Contingency plan
n) Possible shelter areas;
1) Localities where the rig may jack down in an emergency;
2) Availability of other vessel en-route;
3) Rig's draft under various weather conditions; and
4) Port of refuge.
i. The rig/barge is underway once the last anchor is lifted off the bottom.
However, the Rig/Barge mover to continue to maintain control of the operation
until the anchor handling vessel disconnects the last pennant or anchor wire;
ii. The rig is then 'On Tow' and the Rig/Barge mover to clearly inform the Tug
master;
iii. When the rig is 'On tow' the responsibility of the tow rests with the Master of
the tug.
iv. To adhere the approved passage plan at all times;
v. During the tow, the angle of roll and/or pitch should not exceed those shown
on the rig’s critical motion curve. In the event these limits are approached, the
towing course and/or speed should be altered as necessary to keep the unit’s
motions from exceeding these limits;
vi. Positions will be requested from the lead tug as required. Positions will be
plotted on a navigation chart in order that any possible hazards may be
identified. The rigs overall draft to be communicated to the lead towing vessel.
A visual/radar watch is to be maintained by the lead tow vessel and attending
towing vessels and targets which may endanger the tow to be plotted;
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 93 of 145
vii. Where the risk of collision is deemed to exist then action should be taken
according to the International Rules and Regulations for the Prevention of
Collisions at Sea;
viii. The lead tow vessel will be responsible for transmitting radio navigation
warnings on VHF and MF at suitable intervals throughout the course of the tow;
ix. The tow passage ends upon arrival at the new location. However, the rig is still
"on tow" until the first anchor is dropped; and
x. Table 19 shows Towing Average Speed using towing vessel with bollard pull
matched to tow type in weather condition where wind speed is between 15- 20
knots and sea height not more than 3 metres from ahead.
Type of Tow Towing Average Speeds
Twin hulled semi-submersible at transit draft 5.5 to 6.0 knots
Triangular jack-up unit (Three-legged type) 3.0 to 4.5 knots
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 94 of 145
1. A tow pennant of 23 metres in length. The size of the tow pennant should be equal or
bigger than the main tow wire. The use of nylon stretcher is not allowed;
2. A towing wire of 1000 metres in length. The size of the wire should be compatible with
the vessel bollard pull, minimum breaking strength being 2 times the maximum static
bollard pulls of the vessel;
3. Tow bar, gob-line, towing pillar or other arrangements to keep the towline in position and
to prevent girding the tug;
4. Suitable anti-chafe material to be fitted on sections of the wire where chafing is likely to
occur; and
5. A complete spare set of the above equipment to be physically available on the vessel.
1. In addition to the main towing arrangement, every rig or barge to be fitted with an
Emergency Towing Arrangement;
2. This emergency arrangement may be similar to the main towing arrangement or may
consist of a single SMIT bracket/chafe chain/pennant system fitted at the same or another
end;
3. For recovery, a pickup rope (10" x 150' buoyant synthetic rope) to be connected to the
towing pennant. At the end of this pick-up rope will be a pick- up buoy; and
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 95 of 145
4. This emergency towing arrangement to be rigged and ready for use in any inter-field tow.
It is for the purpose of keeping the barge/rig in a safe position while the main towline is
being reconnected.
1. Adequate vertical clearance from the seabed should be maintained to avoid damage to
tow wire. Catenary of towline varies with the length of the tow wire, tug
horsepower/bollard pull, resistance of the tow, speed, water depth and sea state.
2. A minimum length of towline is required for directional control, to get the rig out of the
tug's wake and to prevent the tug from being overrun by the rig/barge. An appropriate
length for the tow line should be determined using established criteria. Where no such
criteria have been established, the minimum required length (L) of the main tow line
should be determined from the formula;
L = (Bollard Pull (MT) /Breaking Load of tow line (MT)) X 1800 metres
1. Passage planning has to be developed prior barge move taking into account the safest and
economical route and that is approved and reviewed by Marine Coordinator or in some
circumstances, a third party warranty surveyor may be present for insurance purposes;
2. The passage plan should indicate abort point, no go area and contingency plan for any
emergency. The passage route to be verified against the latest updated topo data; and
3. Before commencement of tow, all towing equipment and arrangement have to be
inspected by third party surveyor and a towing certificate issued.
For short tows (less than 10 nautical miles and in good weather condition), a barge may be
towed on the anchor wire. It should be noted that when towing on an anchor wire the 'dog'
or 'pawl' on the wire drum to be engaged to ensure that the wire does not slip and to prevent
damage to the winch. Anchor winch gear clutch to be disengaged.
9.10.2 During tow passage
i. The responsibility of the tow rest with the tug master at the point when last pennant
wire or anchor wire is disconnected or in case only one AHT involved.
ii. When the last anchor is retrieved and clear from the bottom at the departure point,
throughout the passage and until the time first anchor is dropped at the final location;
a) The towing vessel to advise the Marine Controller and Barge Master on the length
of towing wire to be deployed or any alteration to that length as well as engine
power settings at all stages;
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 96 of 145
b) During the passage, the Tug Master should continuously monitor the tow. The
Tug Master is required to advise control room of all observed, anticipated or
potential dangers to navigation and observed changes to meteorological
conditions, unusual changes to barometric pressure etc; and
c) These include but not limited to closing vessels to report at agreed intervals on
the course made good, speed and distance to go, as well as estimated time arrival.
There should be a constant exchange of information between the tug and tow on
the weather forecast, dangers to navigation, changes to draft and trim likely to
create a change in the towing characteristics and any deviation from the plan.
1. Before running out anchors, PTW to be obtained from the OIM/CSR/Company Man (as
applicable) for the anchor job;
2. Although the final approach to location has been agreed and approved in the anchor
pattern, the Marine Controller may deviate from the plan as and when deemed necessary
after considering changes in the effect of environmental factors such as prevailing
weather and current and any other factor which has been anticipated in the plan. Each
deviation to be discussed and agreed with appointed marine SME prior to execution; and
3. When making an approach to site the general rule is to stem the wind and current or
whichever is dominant. This is to allow the Tow/AHT vessel maintains barge/rig position
when the first anchor is deployed and the brake is applied.
2. In the event of encountering rough weather during the passage, the following to be
considered:
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 97 of 145
i. Master of the towing boat should not allow the towing wire to be in tension
condition. Increase the tow line catenary to minimize shock load;
ii. Alteration of course and/or speed to minimize the effect of sea and swell;
iii. Pressing up slack tanks to increase stability;
iv. Keep shore informed of deteriorating conditions; and
v. Seek shelter.
vi. Monitor weather condition by taking the reading of barometer and ambient
temperature; and a close watch on the radar for the squall.
1. Anchor mooring arrangement should be designed fit for purpose and approved by an IACS
Classification Society.
2. All anchor mooring arrangement should be tested periodically by its manufacturers or its
appointed agent.
9.14 WINCHES
2. Winch brakes should be set to hold to a load of about 60 % of the Minimum Breaking Load
of the wire above which slippage can occur;
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 98 of 145
3. All wire ropes onboard to be stowed taking the following elements into considerations:
i. Reels to be clean, dry, well ventilated and covered;
ii. Reels to be away from excessively high temperatures likely to dry the wire rope
lubricant and away from any effects of welding/fabrication activities, chemicals,
chemical fumes, steam or other corrosives;
iii. Where reasonably practicable, reels of wire rope retained in storage for
prolonged periods should be regularly rotated (through 180º if possible) to
redistribute lubricant which may otherwise drain towards the bottom of the reel.
iv. Periodic outer layer checks should be conducted to establish that no significant
deterioration has occurred;
v. Wire ropes removed from storage should be thoroughly examined prior to being
put into service;
vi. Generally, the stock should be controlled to facilitate the use of the oldest wire
rope first.
4. The following type of wires and associated equipment to be subjected to the testing
regime as per the table below:
Type of wire Testing Regime Others
Tow wire (Main) After 5 years in service, destructive Termination preferred “Gold Nose “socket.
test for the length of at least 10 Socket to be subjected to MPI testing annually.
metres from termination. The interval Installation of the socket to be certified by an
of testing is not more than 2.5 years external inspector
after the first 5 years*.
Tow wire (Spare) After 5 years in service, destructive Termination preferred “Gold Nose “socket.
test for the length of at least 10 Socket to be subjected to MPI testing prior put in
metres from termination. The interval use. Installation of the socket to be certified by an
of testing is not more than 5 years external inspector
after first 5 years*.
Work Wire After 5 years in service, destructive Termination preferred “Gold Nose “socket.
test for the length of at least 10 Socket to be subjected to MPI testing annually.
metres from termination. The interval Installation of the socket to be certified by an
external inspector
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 99 of 145
1. Anchor cables may be wires, chains or wire/chain combinations. Anchor wires offer
greater flexibility in anchor handling operations especially in pipeline areas and shallow
waters.
2. It is recommended to use only Regular or Ordinary Lay wires with Independent Wire Rope
Core (IWRC). Wires should be galvanized.
3. Length and size of wires vary with the type and size of the rig/barge, typically the
minimum length being 1000 metres. Pipe-lay barges, installation barges, semi-
submersible rigs, drill-ships and vessels with self-anchor laying capability usually have
longer wires.
4. The anchor end of the wire to be fitted with a closed type Spelter Socket or Gold Nose
socket. Experience has shown that this type of socket is more robust, easier to handle and
can be replaced onboard the barge. It is also specified for the purpose of standardizing
anchor handling equipment. The use of bulldog grips for making terminations is not
acceptable.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 100 of 145
9.20 ANCHORS
A wide variety of anchors are used in mooring rigs and barges offshore. An ideal anchor should
have the following characteristics:
1. High holding power in varying soil conditions;
2. Possess good stability in its buried position and when it is dragged through the seabed
when tensioning;
3. Capability to quickly engage and penetrate the seabed upon dropping;
4. Have a low breaking out force;
5. Lightweight and easy to handle;
6. Not prone to being damaged or causing damage to anchor handling vessels; and
7. Have no moving parts, which may be clogged or jammed in operation. Anchors fitted on
the barge/rig should be of the type and size mentioned in the specifications.
The 'FLIPPER DELTA' type is most commonly used in our operations. They have been found to
be efficient and reliable, and therefore highly recommended. High holding power anchors e.g.
Stevpris and Bruce anchors are acceptable.
All anchors to be fitted with a chain pigtail (about 4 metres long) at the crown end. This is to
provide for safer handling and avoid chafing of pennant wire, which commonly occurs if they
are fitted directly to the anchor.
Some anchors, e.g. FLIPPER DELTA and STEVIN, have a provision for changing fluke angles to
suit the soil conditions. This provision should be made to use where necessary.
9.20.1 Piggy-back Anchor
A back-up anchor, which is connected to and laid in line with the main anchor, is referred to
as a piggyback anchor. The distance between the main and the piggy-back anchor is the water
depth + 50% and in no case, be less than 50 metres. To effectively lay a piggyback anchor, the
intermediate pennant should be well stretched and the anchor to be laid in the same direction
as the main anchor.
Since the laying of piggyback anchors is time-consuming and requires additional equipment,
the practice should be discouraged and carried out only as a last resort.
The use of high-efficiency anchors, like the 'Flipper Delta', will minimise the need for
piggybacks. Despite their high initial cost, experience has shown that these high-efficiency
anchors are beneficial in the long run.
When preparing for a rig or barge move, the need for piggyback anchors should be considered
so that prior arrangements can be made to acquire and transport the additional anchors and
fittings to the location.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 101 of 145
In laying piggyback anchors the requirements for anchoring in pipeline areas should be
complied with.
Pennants wires are used for laying and retrieving the anchor.
Pennant wire used should be similar in size and type to the anchor wires. Occasionally where
the anchor wire is small (e.g. 1-1/4 inch) then a slightly bigger pennant wire (e.g. 1- 1/2 inch)
may be used. This is because the wear on the pennant is usually greater than that of the
anchor wire.
The length of the pennant wire varies with water depth, expected anchor penetration, tide
and sea conditions, and type of anchor handling tug. As a practice pennant length for crucifix
type buoy is the water depth + 30 metres for hard sea bed and water depth + 50 metres for
soft mud conditions.
Pennant wire arrangement depends on the type of anchor buoy. For a suitcase type buoys,
the pennant consists of a single length of wire. The main disadvantage of this system is the
need to constantly change out the pennants to suit the locality. For a crucifix type buoy, the
pennant may consist of a combination of different lengths. Then it is only a matter of putting
together the correct length with minimum joints.
Pennant ends to be fitted with Gold Nose wire termination. For the suitcase buoy
arrangement, the buoy end may be spliced. In order to avoid excessive load at this end,
sufficient turns should be taken up on the work drum of the anchor handling tug before lifting
the anchor.
When a barge/rig is on tow it is important that the pennants are properly hung-off or stowed.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 102 of 145
Spring Buoys are buoys that are connected to anchor-wires for the purpose of giving the latter
a vertical lift. They are used when there is insufficient vertical clearance between pipelines
and anchor-wires crossing them.
SPRING BUOY
SHACKLE
PENNANT WIRE
SHACKLE
TO ANCHOR TO BARGE
NOT LESS THAN 5 M
PIPELINE
Buoy catchers are used to retrieve the anchor pennant buoys. The buoy catcher sling is
attached to a tagger winch on deck to enable it to pull the buoy clear of the water.
The recommended assembly for the buoy catcher sling should consist of the following:
i. One x 2 feet x 1/2 inch diameter chain;
ii. Two x 20 feet x 3 inches circumference wire; and
iii. One connecting ring.
All buoy catcher slings should be colour coded in accordance with the Company's procedure
for the registration, inspection and maintenance of slings and lifting tackle.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 103 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 104 of 145
i. Approach to location;
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 105 of 145
In the event of the above requirements cannot be achieved, clarification and approval to be obtained
from the PETRONAS Marine Subject Matter Expert.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 106 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 107 of 145
1. Anchor wires crossing pipelines within the elevated section of the catenary to at all
times maintain a vertical clearance of not less than 5 metres (figure 25).
2. Anchor wires crossing abandon pipelines beyond the elevated part of the catenary to
have an adequate length of ground wire before the crossing point on the pipeline.
3. The length of ground wire from the touchdown point to the crossing is not less than
100 metres (figure 26).
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 108 of 145
6. For escape in the event of an emergency. The barge to be able to clear the location of the
platform independently.
i. The anchor, its pennant wire (secondary and primary) and the buoy are transferred
to the AHT by barge crane;
ii. Connect secondary pennant wire (length depending on water depth) to the work wire
and spool it into the drum; the last set being the primary pennant which will be
connected to the anchor at the chain pigtail;
iii. Once connected take up the slack on the pennant;
iv. The barge then will pass the end of anchor wire and the AHT will pick up by means of
tugger wire and align and secure its socket at the shark jaws;
v. Connect the anchor to anchor cable; and
vi. The AHT takes the anchor on its deck or secures it against the stern roller for running.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 109 of 145
vii. The AHT takes the anchor on its deck or secures it against the stern roller for running.
9.33.2 Suitcase type buoy
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 110 of 145
8. When the anchor hoist operator is satisfied that the anchor is firmly set in the seabed,
the tension of the anchor wire is gradually increased to its working tension. He is also
to confirm that the anchor is holding before sending the AHT to her next task;
9. The amount of anchor wire paid out and the horizontal distance from fairlead derived
from survey positioning equipment is then recorded. A comparison of these distances
will be used to determine any anchor slippage;
10. At least one and a half layer of anchor wire should remain on the winch drum; and
11. After all anchors are set and before moving the barge to its working position, the
anchors should be pre-tension. If the anchor drags, redeploy and test the holding
capacity. When working adjacent to the platform, the tension on the anchor wire
should not exceed this tested tension.
There are times where the anchor is required to run under the bridge especially in a congested
area in order to maintain an even spread of anchors holding the barge. Should it be necessary
to run anchor under the bridge the following method to be used:
i. NO SUBSEA INSTALLATION IN VICINITY AND AWAY FROM JACKET LEG
ii. The AHT run the anchor as usual and drop the anchor immediately under the bridge
together with the buoy;
iii. The AHT will proceed to the other side of the bridge and retrieve the buoy and anchor;
and
iv. The anchor is then run to its intended position.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 111 of 145
In cases where it is not possible to maintain the required minimum vertical clearance from a
subsea obstruction in shallow water, despite running wires under tension. In such situations,
the anchor wire to be run static as follows:
i. The anchor buoy and pennant wire are transferred to the anchor handler. The anchor
is located on the deck of AHT and disconnected from the anchor wire. Sufficient length
of anchor wire is spooled onto the work drum to reach the target location;
ii. AHT pays out the anchor wire as she proceeds towards the anchor location; and
iii. Once the vessel is on location, the anchor is connected to anchor wire and gradually
lowered to the seabed with little headway on the AHT.
i. Raise the shark jaws and slack away the pennant wires until the socket on the last set
of pennant wire rests on it;
ii. Connect the buoy chain pigtail to the end of pennant wire;
iii. A slip hook is connected to the work wire is then attached to pennant wire;
iv. Take the weight on the work wire and lower the shark jaws; and
v. To pay-out the work wire until the slip hook and the buoy is released.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 112 of 145
If Triplex shark jaws are used, omit step 3 to 5. Manoeuvre the vessel to slack away pennant
wire. Then lower the shark jaws to release the buoy.
i. A slip hook connected to the work wire is attached to the pennant wire;
ii. Payout pennant wire until the end is at the stern. Connect the tripping wire to the slip
hook; and
iii. Continue to pay out the work wire, as the tension on the tripping wire will release the
end of pennant wire from slip hook.
i. The number of soft mooring is determined by maximum mooring load the platform is
able to take;
ii. Verify that the load is within acceptable limit;
iii. The soft mooring should consist of a weak link where the breaking strength not
exceed 75% of the allowable structure strength of the facilities;
iv. Under no circumstances a wire rope is loop directly around jacket leg as it will chafe
thus damage the leg and the wire also may come apart;
v. Means should be provided to secure the line in a figure of eight configurations to allow
for fast retrieval during an emergency and for tending the line during rising and falling
of tide; and
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 113 of 145
vi. The sequence of retrieval during emergency pull out should be addressed to all
concerned parties.
3. Job Hazard Analysis to be provided involving all personnel engaged in the operation; and
approve by the structural engineer and OIM.
9.37.1 Deployment of soft mooring
For deployment of soft mooring to jacket leg, the following procedure to be used:
i. Upon setting up a sufficient number of anchors, the barge to detach the anchor, buoy
and pennant wire from the anchor wire intended to be used;
ii. Move the barge closer to the platform by means of heaving up and slacking the anchor
wires;
iii. The derrick crane will pick up the end of anchor wire complete with soft mooring
arrangement. Alternatively, a stand-by boat could be used to transfer the line;
iv. The soft mooring is looped around the accessible jacket leg by personnel stationed on
the platform; and
v. Tension not exceeding allowable load will slowly be applied to the soft mooring line.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 114 of 145
i. There are few alternatives employed to retrieve anchor without pennant line in the event
the pennant line parted; and
a) The barge may self-pick the anchor by moving it in the direction of the anchor; or
b) Passing the anchor wire to the AHT, connect it to the work wire and recover the
anchor. (This technique is tedious and time-consuming).
ii. The most common method is by stripping out the anchor wire by means of a suitable
chaser. However, care should be taken as this method imposes very much higher strains
on chaser pennant wire as well as on the work wire. When this method is employed, the
following procedure to be adhered to:
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 115 of 145
a) Take careful note current set and wind direction which might set the AHT off the
anchor wire when stripping;
b) Pre-calculate the amount of wire needed for that water depth to achieve correct
chaser pennant wire length of one half or twice the water depth;
c) Predetermined type of sea bottom and whether the anchor has achieved full tension
test;
d) The barge is moved away from the platform, hold in position by compensating tension
on other anchor wires;
e) Slack away the anchor wire, a section of the wire is placed on the AHT deck and slips
the chaser into the anchor wire;
f) The chaser assembly (chaser and pennant wire connected to the work wire) takes the
weight of the anchor wire before releasing the section of wire;
g) Slack away the work wire to lower the chaser into the water and align the AHT along
with the anchor wire bow towards the anchor;
h) The barge will pick up tension gradually on the anchor wire to a limit below than that
of the test tension;
i) Commence stripping out the anchor wire and give particular attention on the strain
of the pennant wire (Strain increases as the chaser closes to the anchor);
j) Before breaking out the anchor, the chaser tug will attempt to slip the chaser into the
anchor shank and position itself based on the prevailing weather and availability of
nearby facilities;
k) Chaser tug breaks out the anchor by applying tension on the work wire and if
necessary use main engine to give required force. A sudden slack on the anchor wire
is an indication that the anchor breaks out from seabed; and
l) Slack on the anchor wire slightly and lift the anchor up.
PCC is the other method used to deploy and retrieve the anchor. The use of this system of
deploying and retrieving anchors imposes very much higher strains on the pennants and work
wires than normal buoyed systems.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 116 of 145
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 117 of 145
i. Once confirmed that the anchor is holding, the chaser to be stripped off and send back
to the barge/rig;
ii. Work wire to be shortened up to 1.5 times of water depth and the AHT turned around
through 180º and exactly back over the line of the chain;
iii. Work wire to be kept under very low tension during this manoeuvred;
iv. Chaser is now pulled off from the anchor and towed back to the barge/rig;
v. The chaser can be felt when it’s clear the anchor by the following;
a) A steady very low tension on work wire;
b) A steady tension on anchor lines; and
c) When chaser is on the chain and moving freely the work wire will “jump” in
rhythmic motion as the chaser is towed along. The winch operator on the
barge/rig may feel the chaser moving on the chain.
vi. When approaching the barge/rig, the vessel head to 180º when about 3 vessel length;
vii. Commence shortening of work wire and the vessel continue coming astern in line with
the anchor cable; and
viii. Move the vessel sideways clear of the anchor cable towards the pennant pick up
position under the crane.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 118 of 145
i. Take chaser pennant on deck and connect to work wire. The vessel moves off from the
barge/rig in line with the anchor wire;
ii. As the vessel approaches the distance calculated chain length from barge to anchor,
water depth, work wire length, be ready to ease down on the power;
iii. Work wire will stop twitching when the anchor is reached and the chaser comes onto
anchor; and
iv. Shorten in the work wire to 1.5 times water depth and keep steaming slow ahead while
barge/rig is slacking off tension on the anchor cable (15 metres). Upon slacking of the
cable to 15 metres, increase engine power to halfway ahead. When the tension drops
the anchor is pulled out of the ground.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 119 of 145
1. HSE is the most important element in any winch operation. The winch operator should
always take the necessary safety precautions required to prevent injury to him or
others; damage to the environment and property; and
2. Tabulated below is a list of the most common safe operation practices. Specific work
situations may require additional precautions.
i. Read and understand the winch operation manual before attempting to
operate the unit;
ii. Only trained (attended the rigging and slinging course) and experienced persons
be allowed to operate a winch;
iii. Do not use the winch for hoisting or lowering people;
iv. During operation concentrate on using correct procedures. A moment of
carelessness can allow the accident to happen;
v. Stay clear of wire ropes during operation (barricade). Do not operate the winch
if there are people near wire ropes, winch drums, level- winders (Spoolers) or
other moving parts;
vi. Never leave the winch unattended when the drive motor is running;
vii. Never climb onto the winch when the motor is running;
viii. Inspect wire ropes and attachments before operating;
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 120 of 145
ix. Replace any damaged wire rope or attachments before operating the winches
per standard industry practice;
x. Wear appropriate protective equipment during both operation and
maintenance;
xi. Use only the specified diameter wire rope;
xii. Do not exceed the winch load rating. Exceeding the load rating can damage the
winch and cause accidents;
xiii. Do not exceed rated line speeds. This can also damage the winch and cause
accidents;
xiv. Avoid excess side loading;
xv. Always leave a minimum of one full layer of wire rope on the drum;
xvi. Clean greasy or slippery deck around the winch;
xvii. Never operate with winch guards removed. All guards to be securely fastened
before operating. Make this the final step in winch maintenance along with the
removal of all tools and/or test equipment;
xviii. Never use the drum pawl to stop winch drum rotation. Such practice will create
sudden shock loads on the wire rope and winch drive, and it could severely
damage the winch or break the wire;
xix. Always stop the winch drive motor for any lubrication work;
xx. Maintain regular and systematic inspection of the winch;
xxi. Maintain regular and systematic winch lubrication; and
xxii. (Maintain communication during all winch operations. Always maintain back-
up communications. Instructions should be clearly understood and repeated
before an operation is carried out.
Internal
PTG 18.57.02
OFFSHORE MARINE OPERATIONS SAFETY November 2019
Page 121 of 145
10.0 BIBLIOGRAPHY
INTERNATIONAL STANDARDS
Title
International Convention for the Safety of Life at Sea (SOLAS)
Standard of Training, Certification and Watch Keeping for Seafarers (STCW)
IMO Guidelines for Safe Ocean Towing MSC/Circ. 884 21 Dec 1998 (IMO)
Maritime Labor Convention 2006 (MLC)
International Convention for the Prevention of Pollution from Ships (MARPOL)
Merchant Shipping Ordinance 1952, MSO 1952
PUBLICATIONS
Title
OILFIELD SEAMANSHIP
VOL. Three by Michael Hancox Anchor Handling
OILFIELD SEAMANSHIP
Vol. Five by Michael Hancox Barge Moving
OILFIELD SEAMANSHIP
VOL. Six by Michael Hancox Barge Mooring
Internal
APPENDIX 1: MARINE MANUAL OF PERMITTED OPERATIONS (MOPO)
MARINE Manual Of Permitted Operation (Marine MOPO) 2017 Rev 1
Operating Conditions
Night-time operation.
Geophysical activity.
power generation.
Platform Status
ROV in operation.
Fire Protection
Power System
port/terminal
rope/fender
wire etc.
field)
2.5m.
ACTIVITIES
A VESSEL OPERATIONS
SNATCH LIFTS / CARGO TRANSFER BY STATION KEEPING
1 Lift supply to facilities 1 10 NA NA NA 4/11 11/13 6/12 11/13 NA
Supply to platform and drilling facilities (hose handling or crane operation)
2 vice versa
Supply from OSV to OSV/barge/workboat (hose handling or crane 1 10 NA NA NA 4/11 11/13 6/12 11/13 NA
3 operation) 1 10 NA NA 4/11 11/13 6/12 11/13 NA
BULK TRANSFER (MOORED)
4 Bulk supply to/from facilities or from OSV to OSV/barge/workboat 1 10 NA NA NA 13 13 6/12 13 NA
PERSONNEL TRANSFER
5 Personnel swing rope transfer to/from fixed structures 1 10 NA NA NA 4/11 11/13 6/12 11/13 13 13
6 Personnel
Boat basket
to boat transfer
swing to/from
rope transfer vessel
(OSV to fixedfacilities
to mobile structurese.g. 1 10 NA NA NA 4/5 5/11/13 5/6/12 11/13 NA 13 13
7 workboat/barge) 1 10 NA NA NA 4/11 11/13 6/12 11/13 NA 13 13
8 Boat to boat basket transfer (OSV to mobile facilities e.g. workboat/barge) 1 10 NA NA NA 4/5 5/11/13 5/6/12 11/13 NA 13 13
9 Conventional gangway transfer 1 10 NA NA NA 4 13 6/12 NA 13 13
10 Motion compensated gangway transfer 1 10 NA NA NA 4 11/13 6/12 NA 13 13
BUNKERING
Bunker vessel to/from vessel STS (OSV to mob facilities e.g.
11 workboat/barge) 1 10 NA NA NA 4 13 6/12 11/13 NA 13 13
12 Bunker vessel to/from fixed structures 1 10 NA NA NA 4 13 6/12 11/13 NA
ANCHOR HANDLING AND TOWING
13 Towing operation 1 NA NA 13 4 4 13 NA NA 13 NA
14 Anchor handling/connecting towing bridle - Vessel < 100 ton BP 1 NA NA NA 13 2 4/11 13 2/12 NA 3/14
15 Anchor handling/connecting towing bridle - Vessel > 100 ton BP 1 NA NA NA 13 2 4/11 13 2/12 NA 3/14
STANDBY DUTY
16 Standby vessel (non-emergency) 7 NA NA NA NA NA NA 3/13 3/13 3/13 NA NA 3/14 13
WORKBOAT/BARGE
Workboat/barge OPERATION
mooring operation to fixed platform leg (incl. soft
17 mooring) 1 NA NA NA 13 4 13 NA
18 Workboat/barge gangway installation to fixed platform 1 NA NA NA 13 4 13 12 NA
19 Workboat/barge pull-off operation from platform 1 NA NA NA 4 13 2/12 NA
OFFSHORE MOORING BUOYS
20 Mooring to offshore buoy (Tying Up) 1 NA NA 8 4 13 NA 13
21 Cast-off from offshore buoy 1 NA NA 8 4 13 NA 13
DIVING/ROV OPERATIONS
22 Diving/ROV vessel activities NA NA NA NA 4 13 12 9/13 NA NA
SURVEY VESSEL
23 Survey vessel activities (e.g. side scan, pipeline survey, seismic survey) NA NA NA NA NA NA 4 13 13 NA NA 13 NA
24 Soil boring activities NA NA NA NA NA 4 13 13 NA NA 13 NA
B OFFTAKE TANKER OPERATIONS ( at SBM/FPSO/FSO/FLNG etc.)
1 Offtake personnel transfer to/from export tanker NA NA NA 4 13 12 NA NA
2 Mooring activities 1 NA NA 12 8 4 13 13 NA
3 Export hose handling activities NA NA 4 13 13 NA
4 Cargo transfer operation NA NA NA 4 13 13/14 13/14 13/14 NA
5 Personnel transfer to/from SBM NA NA NA NA NA 4 13 12 13 NA
6 Static Tow NA NA 8 NA 13 13 14 NA
C RIG MOVE OPERATIONS
1 Jack up Rig - Final approach to soft pin near fixed structure 10 NA NA NA NA 4 13 11/13 NA 13 13
2 Jack up Rig - Final approach to soft pin in open area 10 NA NA NA NA 4 13 11/13 NA 13 13
3 Semi-sub / Drillship - approach and anchor handling in shallow water 10 NA NA NA NA 4 4 13 13 13 2/12 11/13 NA 13 13
4 Semi-sub / Drillship - approach and hook up in deep water 10 NA NA NA NA 4 4 13 13 13 11/13 NA 13 13
5 Tender Rig - final approach & pre-tensioning 10 NA NA NA NA 4 13 2/12 11/13 NA 13 13
6 Rig move out from fixed structure (spud can freed) 10 NA NA NA 4 13 13 2/12 11/13 NA 13 13
D MARINE MAINTENANCE ACTIVITIES
1 Above surface inspection/maintenance - LCT buoy etc. NA NA NA NA NA NA NA 4 13 12 11/13 NA
2 Export hose inspection/maintenance NA NA NA NA NA 4 13 12 11/13 NA
3 Lifeboat/TEMPSC/Rescue Boat Sea trial NA NA NA NA NA NA
Internal
Definitions:
BARRIERS: Controls that exist for normal operations. Legend:
ACTIVITIES: Activities carried out under normal operations. Combination allowable with normal procedures
Offshore Support Vessel (OSV) : All types of offshore vessel which is self-propelled. Allow with restriction
1. Maintain continuous UHF and VHF communication. Activity not permitted in this circumstances
2. Activities require 24 hours operations shall have a minimum of 2 sets of crew and/or Working Hours as per MLC 2006 requirement. NA Not Applicable
REMARK : For Geophysical activities, it will govern by IAGC (International Association Geophysical Contractors) & IAOGP
(International Association Oil and Gas Producer) Guidelines.
Any interfacing activities between geophysical and non-geophysical operation, MOPO will supersede.
Any other activities not listed above shall have their own Site Specific Procedures and Risk Assessment endorsed by PCSB AA
Reference:
A. SOLAS (Safety of Life at Sea) 1974
B. MSO (Merchant Shipping Ordinance) 1952
C. COSWP (Code of Safe Working Practice) for Seaman 1998
D. STCW (Standard of Training, Certification and Watch keeping) for Seafarer.
E. ISM (International Safety Management) 1994
F. IAGP
G. IAGC
H. IMCA (International Marine Contractors)
I. UNCLOS (United Nations Convention of The Law of The Sea)
MOPO 2017 Rev 1
Internal
APPENDIX 2: SAMPLE OF UNANNOUNCED / PRE HIRE VESSEL HSE INSPECTION
( Owner / Contractor )
1. OSVIS
5. CCTV
6. AIS
7. FiFi
Internal
NO FINDINGS STATUS ** TIME CORRECTIVE ACTION
FRAME PLAN (Owner /
Contractor )
10. Load Line Items E.g.: watertight door, emergency escape hatch,
air vent etc.
11. PCSB 17 Marine HSE Guidelines and HSE Policy (incld ZETO Rules)
(Owner/Contractor)
Navigation E.g.: Chart and publication, RADAR, Bridge control
15 panel, BNWAS, Deck Log Book etc.
B. OTHER FINDINGS.
C. BRIEFING
Internal
1. PCSB HSE Management System and Guidelines
D. POSITIVE FINDINGS.
E. WALKABOUT PICTURE
Internal
APPENDIX 3: SAMPLE OF VESSEL QUARTERLY SELF ASSESSMENT
VESSEL INSPECTION CHECKLIST
Vessel Name :
IMO Number :
Date :
Location :
Vessel Operator:
Vessel Owner :
a) Certificate of Registry.
b) Certificate of Class.
c) Safety Management Certificate.
d) Document of Compliance.
e) International Load Line Certificate.
f) International Tonnage Certificate.
g) Passenger Certificate.
h) Ship Safety Equipment Certificate.
i) Ship Safety Radio Certificate.
j) Ship Safety Construction Certificate.
k) International Oil Pollution Certificate.
l) International Ship Security Certificate.
m) Minimum Manning Certificate. (minimum
manning to be put into remark column)
n) Ship Sanitation Control Exemption
Certificate.
o) P&I cover note.
p) Hull and Machinery Insurance cover note.
a) Boat Drill
b) Fire Drill
c) Man Over Board Drill
d) Oil Spill Drill
e) Other emergency drills
a) Hot work
b) Confined space entry
c) hazardous tasks
d) work involving high voltages
e) working at height and over the side
f) Lock Out/Tag Out processes
g) the need for multiple permits
h) work on stored systems containing stored
energy e.g. pressure vessels
Internal
4 Are the following records/logs kept up to date?
Internal
Are the following publications onboard, if
applicable?
a) EPIRB
b) SART
Internal
1.1.4 Part D: Life Saving Appliances
a) General cleanliness.
b) Is the hull free of damage?
c) Is the davit and falls in good order?
d) The inventory of the Rescue Boat counted
and in place?
e) Is the launching instruction available?
Internal
1.1.5 Part E: Fire Fighting Appliances
a) Bollards
b) Anchor windlass
c) Chain Stopper
d) Hawse pipe
a) Towing wire
b) Work / Snatching wire
c) Tugger Wire
d) Capstan
e) Crane / Davit
f) Hydraulic Pins
g) Hydraulic wire stopper
h) Stern Roller
Internal
1.1.7 Part G: Engine Room Machineries and Equipment
A) Scuppers running
B) Hood free of oil
C) No Insects or bugs
D) Cutlery clean and sufficient
E) Dry provision and cold room free of odour
and clean
Internal
1.1.9 Part I: Personnel Protective Equipment
a) Coverall
b) Hard Hats
c) Safety Boots
d) Gloves
e) Working vest
f) Safety glass / Goggles
g) Earplug or muff
The following briefing is to be conducted onboard within the Quarter, attended by all ship staff:
Internal
10 Stop Work Campaign
We hereby certify that the above statements given are true and correct as to the best of our knowledge.
( Name and signature ) ( Name and signature ) ( Name, position and signature )
The Quarterly Self-Assessment to be sent to Marine Operations Safety, Logistic HSE, PD&T on the 1st week
of January, April, July and October.
Internal
APPENDIX 4: SAMPLE OIM VESSEL VERIFICATION
YES NO
1. OSVIS
Green or Red
Internal
O DESCRIPTION COMPLIANCE REMARKS
YES NO
ON SITE-SPECIFIC PROCEDURES
11 Anchor Handling activity i.e. approved anchor pattern,
marine controller, BMS/TMS, Master’s understanding of
the requirements etc.
12 Towing equipment/machineries i.e. approved by MWS
13 Personnel Transfers via swing rope
Transfer only allowed by FCB & GP below 500GRT
Non-slip clear landing at vessel stern
3-point contact to assist personnel i.e. handrail, etc.
Adequate fenders
Safety briefing video/verbal
14 Personnel Transfers via transfer basket
Adequate deck space on the vessel
Safety briefing video/verbal
15 Bunkering
Checklist completed
16 Lifting
Snatching (approaching by stern and maintain clear
safe distance)
Alongside (vessel secured parallel)
Rigging/Slinging training
Compliance to PETRONAS colour coding on sling and
shackles
17 Mooring
Not recommended on the weather side
Adequate mooring lines
Adequate fenders
Weather watch
Timely decision to cast off
Internal
APPENDIX 5: REQUIREMENT CREW ACCEPTENCE MATRIX
Internal
APPENDIX 6: SAMPLE BUNKER PRE LOADING PLAN
Internal
PTS 12.34.56
THIS IS A SAMPLE PTS March 2015
Page 141 of 145
This safety checklist is to be completed before the commencement of any bunkering operations. One
copy is to be retained on board the vessel.
The checklist is to be completed and signed by both parties i.e. the supplying and the receiver.
Please note: the declaration at the end of the checklist needs to be signed. Adequate supervision of
the bunkering operation is to be maintained at all times by both parties. On completion of bunkering
operations, the hose is to be drained and blanks/cover fitted before transfer to the jetty/ facilities. No
fuel tanks are to be filled above 98% capacity. In the event of any following answer is NO, do not
proceed with bunkering activities.
Internal
APPENDIX 8: BEAUFORT SCALE
Beaufort Knots Mph Description Effect at sea Effect on land
Scale
1 1-3 1-3 Light air Ripples but no foam Smoke drifts in wind.
crest
2 4-6 4-7 Light breeze Small wavelets Leaves rustle, the wind felt on
face.
3 7-10 8-12 Gentle Large wavelets, Crest Small twig in constant motion,
breeze not breaking light flags extended.
4 11-16 13-18 Moderate Numerous whitecaps, Dust, leaves and loose paper
wind Waves 1-4 ft high rose. Small branches move.
5 17-21 19-24 Fresh wind Many whitecaps, some Small trees sway.
spray, Waves 4-8 ft high
6 22-27 25-31 Strong wind Whitecaps everywhere, Large branches move, difficult to
large waves 8-13 ft use umbrellas.
7 28-33 32-38 V strong White foam from waves Whole trees in motion.
wind is blown in streaks,
waves 13-20 ft high
8 34-40 39-46 Gale Edges of wave crest Twigs break off trees, difficult to
break into spindrift walk.
9 41-47 47-54 Severe gale High waves, the sea Chimney pots and slates
begins to roll spray removed.
reduce visibility, 20 ft
waves
10 48-55 55-63 Storm V. high waves 20-30 ft, Trees uprooted, structural
blowing foam gives sea damage.
white appearance
Internal
APPENDIX 9: IMPROVEMENT BASED ON INCIDENT LESSONS LEARNT INTO PTG SECTION
Internal
NO Incident Description Type Of Improvement into the PTG section
Incident
11 OSV manoeuvred in close proximity Near Miss 2.0 GENERAL INSTRUCTION TO MASTER
of FSO Sepat caused vibration to OF MARINE VESSEL (CIMMV)
mooring chain P4-P6. 2.13 Requirement for Vessel
at offshore Installation
9.0 TOWING, MOORING AND
ANCHOR HANDLING
9.13 Anchor Mooring Arrangement
12 LCT made contact to the EWDP-B Minor PD 2.0 GENERAL INSTRUCTION TO MASTER
boat landing structure during the OF MARINE VESSEL (CIMMV)
personnel transfer, 2.13 Requirement for Vessel
at offshore Installation.
13 GOM 3 unabale to maintain position Near Miss 2.0 GENERAL INSTRUCTION TO MASTER
due to weather and crossed anchor OF MARINE VESSEL (CIMMV)
wires of MC1 2.13 Requirement for Vessel
at offshore Installation
9.0 TOWING, MOORING AND
ANCHOR HANDLING
9.13 Anchor Mooring Arrangement
14 Tambah Maju lighting post hit the Minor PD 2.0 GENERAL INSTRUCTION TO MASTER
vent support and damaged OF MARINE VESSEL (CIMMV)
2.13 Requirement for Vessel
at offshore Installation
15 AHT made contact with jacket and Minor PD 2.0 GENERAL INSTRUCTION TO MASTER
resulted puncture on the hull. OF MARINE VESSEL (CIMMV)
2.13 Requirement for Vessel
at offshore Installation
16 While disconnection of Fresh water Minor PD 2.0 GENERAL INSTRUCTION TO MASTER
transfer hose from rig, it got OF MARINE VESSEL (CIMMV)
entangle at vessel's starboard side 2.18 Cargo Operation
propeller.
17 During start-up of main crane, Minor Fire 2.0 GENERAL INSTRUCTION TO MASTER
observed smoke emitting from OF MARINE VESSEL (CIMMV)
crane engine. All Stopped. Crane 2.23 Lifting/Slinging Operations
operator used portable fire
extinguisher to extinguish the small
fire.
18 Upon arrival into Bintulu Port, Minor 2.0 GENERAL INSTRUCTION TO MASTER
Neopetro 20 reported that due to LOPC OF MARINE VESSEL (CIMMV)
lifting on 3.8.19, Lube Oil drum was 2.23 Lifting/Slinging Operations
damaged. The damaged drum was
wrapped and handed over to SW
contractor for disposal.
Internal
NO Incident Description Type Of Improvement into the PTG section
Incident
19 While performing ship to ship Minor PD 2.0 GENERAL INSTRUCTION TO MASTER
transfer at location, passing swell OF MARINE VESSEL (CIMMV)
resulted both vessels to roll. This 2.16 Cargo Handling at Installation
resulted contact and minor damage
on the hand rails
20 Platform's Fuel Oil hose caught with Minor PD 7.0 FUEL BUNKERING
vessel starboard bollard and caused 7.3 Delivering and Receiving of Bunker
the hose parted. (Offshore)
Internal