 Owner Supertech  Tower height 121

Limited meter
 Project started in year  32 floors in T16 & 29
2004. floors in T17
 Project 'Emerald
Court' society’
 Location city's Sector
93A Noida
 Tower 16 Apex and
Tower 17 Ceyanne
 The Resident Welfare Association (RWA) says that the twin towers were
built in violation of fire safety norms, and open space norms.
 The distance between T-16 and T-17 was kept only at 9m
 The garden space area near T-1 was utilized for the construction of the
twin towers

Violation of distance requirement under Building Regulations


9 mtrs. distance was to be maintained between Tower 17 and Tower 1 at the
ground level
Notably, NBR 2006 stipulated that distance between two adjacent building
blocks shall not be less than half of the height of the tallest building.
The minimum distance between Tower 17 and Tower 1 should be 36.5 mtrs.
However, the actual distance between these two towers was only 9 mtrs.
Violation of NBR 2010
The height of Tower 16 and Tower 17 was increased to 121 mtrs and
distance between them is only 9 mtrs but according to NBR2010 it should
be 16.
Violation of NBC 2005
National Building Code, 2005 (“NBC 2005”) prescribes maintenance of
open spaces for buildings above the height of 10 mtrs.
the minim open space around Tower 17 should have been 20.45 mtrs. as
opposed to actual 9 mtrs between Tower 17 and Tower 1
Violation of Fire Safety Norms
The side and rear space around the building must be 16 mtrs. The
distance between Tower 1 and Tower 17 was only 9 mtrs.
Consent of RWA
provides for common areas and facilities. Under Section 5(2), the
percentage of the undivided interest of each owner of a flat in the
common areas and facilities, as expressed in the Declaration, shall not be
altered without the consent of all the owners of the flats expressed
through an amended Declaration which shall be executed and registered
under the Act.