Professional Documents
Culture Documents
constructandcommission.com/what-is-document-status-a-b-c-d/
This is to accept that, what is being provided is in line with project/design and contract
requirements, for works to commence.
Table of Contents
The below table details the status of documentation and what they can mean on a
project. As can be seen the Status D, is basically included to provide the reviewer with an
ability to fully reject a document. It usually means that the submitted document does not
meet what the title is, is completely inadequate to explain or describe what its intended
for, or there is significant information and data missing.
1/3
Status Status A,B,C Status A,B,C,D
General Contractor / Main Contractor and their teams create the documentation /
information.
Internal Review conducted by Main Contractor Engineers.
If internal review ok, then issue to *client team via email or some form of electronic
platform such as Aconex / Asite / Procore etc.
Client team review and provide comment / approval based upon Technical,
Installation, Commissioning & Maintainability.
*The Client Team would consist of the Client, Project Manager, Designer, Commissioning
Consultant, Facilities Team etc. [if on board early enough].
As an outline, the documents as listed in our articles below would usually be required,
relating to the commissioning process:
2/3
COMMISSIONING DOCUMENTS | 368 of them listed here
CONSTRUCTION DOCUMENTS | Explained
Material/Technical Submissions
These are generally focused upon items of equipment and materials that will be selected
and manufactured to meet the design requirements as set out in the project
specifications. The materials and equipment can range from details of pipework/cables to
generator and chillers.
Material Submissions are usually issued by the general contractor / main contractor for
approval by the design team. The commissioning manager should also support reviewing
these documents.
Drawings
The designer will usually issue a full set of design drawings to the project – these will
detail the expectations relating to what should be installed where, sizes, flow rates, and
any simple control logic, etc. The general contractor / main contractor would take these
drawings, fully coordinate the services, and produce ‘shop drawings’ / ‘working drawings’.
These shop/working drawings should be reviewed and commented upon by the project
team [designer, commissioning consultant].
Testing Procedures
Testing procedures should be developed by the General Contractor / Main Contractor for
the future commissioning works – these will range from early testing requirements such
as Weld / Pressure Testing all the way through to the final building-integrated testing.
3/3