PROJECT QUOTATION
250 CUBIC METER BIOGAS PLANT
Our Mission is to provide economically attractive and alternative energy production solutions that can
reduce the dependence on conventional energy systems.
Revgreen Pakistan designs, manufactures, installs, and commissions Biogas Plants that are ROBUST
and SIMPLE to operate
Revgreen Pakistan Services: -
• Consultancy
• Design & Installation of Biogas Plants
• Materials & Equipment Supplies
• Feedstock Supply Chain
• Operations & Maintenance
2. Executive Summary
Maaz Ahmed approached Revgreen Pakistan to furnish a proposal for installation of biogas plant. The
requirement of the project is to replace 50 cylinders of 15 kg and 25 cylinders of 45 kg Monthly. For this,
250 cubic meter of biogas plant is required. This will provide 105 - 120 Cubic Meters of Bio-Methane
daily. Low cost activated carbon filters will remove CO2, H2S & other impurities to purify the gas.
The Proposal is based upon Animal Manure any other feedstock will change the biogas yield
The above-mentioned calculation based upon the quantities of manure, any reduction in the quantities
will reduce the amount of biogas produced.
In below document the scope and details of the project will be explained.
Biogas is a mixture of CH4 methane (50%-70%) and carbon dioxide (30%-40%) with traces of
hydrogen sulphide and water vapour. The gas can be obtained by fermenting any kind of
Agriculture, Animal, Municipal, Food Industry organic biodegradable waste. It is a sustainable
source of renewable fuel and can also be produced by harvesting Energy crops like Maize, Grass,
Beet and Sunflower etc.
4. Objectives
By installing the plant, the following objectives will be achieved:
6. Proposed Solution
The core of the biogas plant will be a 250 CUM lagoon digester excavated in earth. The digester will
be built with concrete super structure and will be covered with Geo-Membrane for the storage of
gas. The animal manure will be procured into the Feeding Tank. The manure will be mixed with
water to achieve optimum feeding conditions.
The slurry coming out of the digester will collected in a brick superstructure digestate tank the
storage of liquid Organic Manure.
As described above biogas is mixture of Methane, Carbon dioxide and other gases and water vapour.
Methane (CH4) is the only gas that is combustible and it constitutes 50-55% of all the biogas
produced in the anaerobic process. Revgreen Pakistan will use low-cost filters for the purification
of biogas. The gas will be passed through the filtering system and then will be stored in Gas Storage
Tank for further supply and use.
Gas
Mixing & Main Purification & Gas Storage
Compressor
Feeding Tank Digester System Tank
This is a very high-level cost of bio-methane production and ROI. Any additional revenue from
compost/Biomass fuel is not included in the savings. This cost may vary with variation in feedstock
cost etc.
12.Plant Operations
As a producer of biogas plants, REVGREEN PAKISTAN can influence some of the most significant cost
factors that are relevant for the operation of a biogas plant, including:
• Power consumption
• Availability
• Construction time
• Commissioning phase
Operationally stable technology and high efficiency for a first-class price/performance ratio depends on
many factors. Revgreen will provide one full time resource for a period of 15 days for training &
production of biogas.
A fulltime resource will be provided by the client for the project training & knowledge transfer.
14.Mobilization Period
A mobilization period of 15 Days will be required after the project is approved and this period
will not be included in the Project schedule.
15.Change in Scope
Any change or enhancement in the scope as per signed requirement specifications would be
considered as a change request. Revgreen Pakistan would charge accordingly for any scope
change Request (s).
The Quotation is valid for 20 days and does not include any taxes