Professional Documents
Culture Documents
Dfi 105
Dfi 105
net/publication/275037470
Article in DFI Journal The Journal of the Deep Foundations Institute · March 2014
DOI: 10.1179/1937525514Y.0000000002
CITATIONS READS
3 211
3 authors, including:
All content following this page was uploaded by Rauli Lautkankare on 17 April 2015.
new deep foundations and on the through holes for include, among others, at least the diameter and material
ground heat collector piping and technical implementation thickness of the piles and pipes, the distance of the pipes
of such piping in these load transfer structures. The term from each other and from the ground, the filling material
‘through hole’ means a penetration or an inlet going inside the pile, and the soil properties.
through the (super)structure above the pile. Openings, When designing the piles, the increased corrosion has to
pipe passages and holes that accommodate the heat be taken into account. The corrosion risk exists in the
collector pipes as they pass through the load transfer layers where the space between soil particles is not
structure are referred to ‘through holes’ hereafter. This completely filled with water and oxygen is present.
study is part of the FIN-C2M project. The FIN-C2M Typically this is the case just under the foundations where
project is part of the Case 2 Micropile Research Project gravel or sand has been used as a filling material to form a
in collaboration with the International Society for capillarity layer and the upper part of the pile is in contact
Micropiles. with that moist filling material. This corrosion problem
has recently been countered by installing a centrally
positioned steel pin. In most cases a rebar with a length
From pile to energy pile of 3 m and a width of 32 mm was placed in the center of
Current know-how and technology make the use of energy the pile leaving about half a meter of the bar above the pile
piles possible in certain projects. There are some specific cap (Fig. 1). The space required by the pin(s) must be
limitations and possibilities related to energy piles that taken into account when designing the heat collector
need to be taken into account when estimating the energy piping. Another possibilities are to use stainless steel
production investments and life cycle of buildings. Two quality in upper parts of the piles or cover the upper part
such limitations are namely the mean distance between the with grout.
piles and the length of the piles. This is vital for obtaining A traditional pile is transformed into an energy pile by
sufficient ground heat for the building and for ensuring the installing inside the pile a plastic ground heat collector
temperature balance in the ground (Juvonen, 2009). pipe filled with a heat carrier fluid. The plastic used in
The ground thermal balance also needs to be taken into these pipes is usually polyethene (PE). The most common
account when designing the energy pile field. That was types of PE used are medium-density MDPE, high-density
also researched in the FIN-C2M project. The balance is HDPE, and cross-linked PEX. The service life of these
relatively easy to achieve in buildings having both heating plastic pipes is usually between fifty and a hundred years
and cooling. Furthermore, energy pile systems maximize (ISO/TR 9080, 1992). The plastic pipes are kept separately
their efficiency when they operate seasonally. The ground by using plastic divider. A sufficient distance between
thermal balance explains why energy piles need a certain pipes is required for avoiding thermal short circuit and
minimum distance between each others. In Nordic having a good efficiency in system. In small diameter
countries where heating needs are higher than cooling, it energy piles with outer diameter between 100 and 300 mm
is necessary to study the ground thermal response case-by- the typical pipe configuration inside the piles is simple
case. This is the case especially in buildings using energy U-tube.
only for heating. To keep the thermal balance it is The liquid circulating in the collector pipes in Finland is
important to avoid ground freezing due to the massive most commonly bioethanol. The freezing point of a 30%
heat extraction (Pérez Cervera, 2013). It is recommended ethanol mixture is 217uC. Depending on the application
that at least 70% of the heating energy needs to be ethanol can be replaced with another antifreeze agent
recharged during the summer time (Uotinen et al., 2012). such as propylene glycol in groundwater areas, betaine
Four or five meters have been sufficient distance between or potassium formate. As potassium formate is more
the energy piles in new buildings in Finland and over 15 m corrosive than other heat transfer agents, corrosion
sufficient length of the piles (Vesamäki, 2011). inhibitors must be used. The freezing point of heat
If the construction is to be fitted with a deep foundation transfer agents varies between products which might
in any case, it might be reasonable to consider energy piles. affect the selection of the solution. In addition to lowering
Any piles large enough for the ground heat collector the freezing point, a heat transfer agent has other
piping are suitable as energy piles. These include at least important qualities such as low viscosity, high thermal
steel pipe piles and concrete piles with holes. Of these two conductivity, and high specific heat capacity (Juvonen and
only steel pipe piles have been used in underpinning Lampinlampi, 2013).
projects. There is also some experience of using concrete Nowadays constructions are generally designed to have
piles with holes in new constructions (Tompuri, 2010; a 100–200 year service life; and thus, the heat collector
Vuorio, 2009). pipes may well need replacement during that period. Pipes
Almost all common steel pile sizes are suitable for may also break due to other reasons than age-related
energy piles. Only the smallest piles are too narrow for the weakening. During transportation, storage or installation
heat collector piping. On the other hand, they are not and when handled at the construction site, precision is
commonly used in underpinning projects due to their low important as plastic pipes scratch easily and are then
load-bearing capacity. In larger piles the distance between unusable. As pipe installations performed alongside
the heat collector pipes and the heat source, namely the underpinning projects are usually performed in cramped
ground, may become an issue. Optimization of the basements, the risk of breaking the pipes is much higher
primary circuit system requires more studying because than that of breaking with the usual piping of heat wells
there are many factors affecting efficiency. Such factors outside the actual building (Uskali, 2013).
Energy piles and load transfer structures this study the energy collector pipes are added to the
sequence charts to show their installation phase on the
The common load transfer structures comprise reinforced process (Figs. 2–5). As a rule, energy piles cannot be used
concrete beams, steel beams, walls, pilasters and tension with jet grouted columns. In Figs. 2–5 all such load transfer
anchors. One of the challenges of using energy piles in cases are depicted that are immediately compatible with
underpinning projects has to do with the load transfer energy piles. All things considered the through holes for
structures, specifically the through holes for ground heat ground heat collector pipes need to be designed for each
collector pipes. Through holes make it possible for ground individual case even when using types of load transfer
heat collector pipes to traverse the load transfer structures. structures that are immediately compatible with energy
In the FIN-C2M project this is studied on the basis of load piles. However, some general principles can be presented.
transfer cases by examining which types of load transfer In five of the load transfer cases the ground heat
structures are suitable for energy piles. There are 13 collector pipes can be led directly through the pile cap.
recognized load transfer cases which are presented in With reinforced concrete beams or encasings it is enough
sequence charts (Lehtonen, 2011). According to the studies to encase the pipes. Solutions in new constructions are
nine of these cases are suitable for use with energy piles. In based on this technique.
2 Load transfer cases where ground heat collector pipes can be led directly through pile cap. Cases 2, 3 and 5 (Lehtonen,
2011. Edited by Heli Kanerva-Lehto)
3 Load transfer cases where ground heat collector pipes can be led directly through pile cap. Cases 7 and 8 (Lehtonen,
2011. Edited by Heli Kanerva-Lehto)
In load transfer structures where a steel beam is centered angle, the through hole needs to be vertically larger
right on top of the pile cap, one possibility is to lead the (Fig. 9). When the pipes are led out of the pile, they are
collector pipes from the pile through the load transfer insulated. An insulated pipe is subject to less condensa-
structure by using a double-web steel beam (Fig. 6) and tion. Pipes are led to manifolds and onwards to a utility
leading the pipes through the hole(s) in the flange or by room. With longer pipes, larger diameters or grooves can
using two or more steel beams so that the pipes are taken be used to compensate for pressure loss.
out through a gap left directly on top of the pile (Fig. 7). The width and height of the through holes are
Where a solution with a steel beam right on top of the dependent on the diameter of the pipes and their bending
pile is desired, the pipes can be led out through the side of radius or the space required by angle joints. At its smallest
the pile before the pile cap (Figs. 8 and 9). The through the through hole can have the width of two pipe diameters
hole can be made to the desired spot on site when the pile and the height of one pipe diameter, in cases where 90u
is at its final depth and cut to its final elevation. This angle joints are used. The most common pipe diameter is
structure is practically untested and has been devised 32 mm, resulting in a 32664 mm through hole. In
specifically for underpinning projects. With 90u angle practice some margin is required during installation. If a
joints, the through holes can be relatively small (Fig. 8). If base weight is used during installation, the space required
the pipes are led through by bending them to an acute by it also needs to be taken into account. Modern cast iron
4 Load transfer cases where pipes need to be led out through side of pile before pile cap, alternatively using special jack
system depicted in Fig. 10. Cases 9, 10 and 11 (Lehtonen, 2011. Edited by Heli Kanerva-Lehto)
5 Load transfer cases where pipes need to be led out through side of pile before pile cap, alternatively using special jack
system depicted in Fig. 10. Case 12 (Lehtonen, 2011. Edited by Heli Kanerva-Lehto)
base weights are often 400 mm long, therefore, getting one possible to lead the collector pipes out of the pile through
through a hole in the side of the pile requires a larger the pile cap with a special jack system and by using steel
through hole if the pile diameter is small. structures so that an angle joint can be installed.
The same principle can be applied in structures where
pile pretension is achieved by jacking directly on top of the
pile cap (Figs. 4 and 5). A through hole may weaken the
Hybrid energy piles
load bearing capacity of the pile, and thus the pile might A hybrid energy micropile solves two issues in under-
need reinforcement around it. pinning projects: transferring the load of the building and
In load transfer structures where tension anchors are collecting the geothermal energy from boreholes under the
used and pile pretension is achieved by jacking directly on piles. Thus, heat wells are here not located next to the
top of the pile cap and where cutting holes for the pipes is building, instead, they are under the building. Compared
not possible, a new solution (Fig. 10) has been found. It is with energy piles hybrid energy piles allow the harvesting
of energy at a greater depth of up to hundreds of meters.
6 Double-web steel beam and pipes led through hole in 7 Two steel beams and pipes led through gap between
flange beams
10 Collector pipes led through pile cap and passed by special jack system. (Original drawing by Vesa Sarola, edited by
Rauli Lautkankare)
could increase as much as to 1?5 kg m–1, making a 30 m imposes an ever increasing load on the installation crew
long pipe weigh 45 kg with an additional weight of 15 kg and the pipes themselves. The pile could even collapse
for the base weight. from the strain. In an opposite situation where the pile is
When the heat collector pipes are fed into the pile, the filled with water but the pipes are empty, the sinking of
center of the pile must be filled with water. Water creates pipes is difficult due to flotation. The water used during
lift inside the pipe and facilitate installation. The base the installation may be left inside the pile if the pile is
weight helps the pipe settle into place and prevents the designed to be water filled. In Finland piles are typically
pipes from rubbing against the pile walls. If the pile is not filled with concrete. The use of concrete is supported by its
full of water but the pipe is, the weight of the pipes good thermal conductivity and the way it bonds with a
11 Hybrid energy pile. Extra load bearing capacity and corrosion resistance is gained with smaller micropile inside load
bearing pile (Original drawing by Vesa Sarola, edited by Rauli Lautkankare)
steel pile to form a load-bearing composite structure. The the steel beam cases and the special jack system cases. The
selection of filling material has a great significance in the sequence charts depict the theoretical installation phases
long run as the increased thermal conductivity affects but every underpinning project to be implemented with
the energy gain positively throughout the life cycle of the energy piles should be studied individually.
structure. Then why is concrete not always used even Beside technical feasibility, the project economy must be
though it has better thermal conductivity than water? considered. On the basis of studies and models which
Water filling has its own advantages as the pipes can be take into account climate conditions, soil properties and
replaced more easily if they break or reach the end of their heating and cooling solutions in buildings, energy piles are
life cycle. economically feasible in Finland. Energy micropiles in
Before the pipes are installed inside the pile, they should underpinning projects are one solution for extracting heat
be tested while filled with liquid at 3 bar pressure for from the ground and thereby for reducing the greenhouse
over an hour to detect any leaks (Juvonen, 2009). At the gas emissions of energy production.
beginning of the installation, the sharp edged top of the
steel pile should be covered with a round edged plastic
ring, for example. This prevents pipes from scratching.
References
When the base weight reaches the tip of the pile, the pipes Arola, T. 2014. Golder Associates Ltd, an interview.
are installed. If the pile is to be filled with concrete, the Banks, D. 2008. An introduction to thermogeology: ground source
heating and cooling, Oxford, Blackwell Publishing Ltd.
filling is performed as underwater casting. Bourne-Webb, P., Amatya, B. and Soga, K. 2009. A framework of
understanding energy pile behaviour, Darmstadt Geotechnics
No. 18, Int. Conf. on Deep foundations – CPRF and energy pile,
Conclusions Darmstadt, Germany, May, Frankfurt am Main, Institute and
Laboratory of Geotechnics, 315–324.
As a result of this study technical solutions were found for
Brandl, H. 2006. Energy foundations and other thermo-active ground
combining energy micropiles and ground heat collector structures, Géotechnique, 56, (2), 81–122.
pipes with nine load transfer structure cases. In five cases Ebnöther, A. 2008. Energy piles, The European Experience, GeoDrilling
the work can be done as in a new building. There is also a 2008 Conf., Peterborough, England, UK, April–May. http://
special solution if steel beams need to be used. In four www.gshp.org.uk/conference2008.html
ISO/TR 9080. 1992. Thermoplastic pipes for the transport of fluids.
cases the pipes must be led out through the side of the pile
Juvonen, J. (ed.) 2009. Lämpökaivo – Maalämmön hyödyntäminen
before the pile cap or alternatively, a special jack system pientaloissa. Heat well – ground-source heat in one-family houses,
needs to be used. This system allows collector pipe Environment guide 2009, Helsinki, Finnish Environment Institute
installation right after the piling phase and jacking after (SYKE). http://www.ymparisto.fi/download.asp?contentid5108597
piping without breaking the pipes. &lan5fi
Juvonen, J. and Lapinlampi, T. 2013. Energiakaivo – Maalämmön
The geological features in Finland allow utilization of hyödyntäminen pientaloissa. Energy well – ground-source heat in one-
energy and hybrid energy piles. There are some regulations family houses, Environment guide 2013, Helsinki, Ministry of Environ-
and recommendations which need to be considered. The ment. Available only in Finnish. http://www.ym.fi/fi-FI/Ajankohtaista/
length of the energy piles should be at least 15 m and the Julkaisut/Ymparistoopas_YO/YO_2013_Energiakaivo(24946)
Juvonen, J. 2014. Finnish Environment Institute (SYKE), an interview.
distance between the energy piles at least four or five
Lehtonen, J. 2011. Underpinning project; owners’ views on technology,
meters. A minimum distance of 15 m between hybrid economy and project management, Aalto University publication series,
energy piles is required, as is usually the case with heat Doctoral dissertations 80/2011, Aalto University, Espoo, Finland.
wells in Finland. This distance is a recommendation and it Ma, X. L. and Grabe, J. 2009. Influence of groundwater flow on efficiency
depends on the angle of the borehole and the properties of of energy piles, Darmstadt Geotechnics No. 18, Int. Conf. on Deep
foundations – CPRF and energy piles, Darmstadt, Germany, May,
the soil. The diameter or the material thickness of the steel Frankfurt am Main, Institute and Laboratory of Geotechnics.
micropiles needs not be altered when the piles are in National Energy and Climate Strategy Government Report to Parliament
energy use. In addition, the load-bearing capacity is not on 20 March 2013. 2013. Työ-ja elinkeinoministeriön julkaisuja,
reduced either by the borehole under the hybrid energy Energy and the climate 8/2013. Helsinki, Ministry of Employment
and the Economy. Available only in Finnish. http://www.tem.fi/files/
pile or the energy use of the pile. In Finland, The bedrock
20585/Selontekoehdotus_311008.pdf
is solid and the piles are mainly end-bearing. Pahud, D. and Hubbuch, M. 2007. Measured thermal performances of the
Both energy pile types are usually filled with bentonite energy pile system of the Dock Midfield at Zürich Airport, Proc. Eur.
or concrete but even water may be used as a filling Geothermal Cong., Unterhaching, Germany, May–June. http://
material. Materials which have good thermal conductivity www.geothermal-energy.org/pdf/IGAstandard/EGC/2007/195.pdf
Pérez Cervera, C. 2013. Ground thermal modelling and analysis of energy
have an advantage over time because of the improved pile foundations, Master’s dissertation, Aalto University, Espoo,
efficiency ratio. Water as a filling material is possible and Finland.
makes the collector pipes replaceable. Ruukki. 2013. Innova 2 Technopolis – Steel piles utilising ground-source
The risk of corrosion in the upper parts of the steel piles heat. http://www.ruukki.com/References/Public-buildings-offices/
Innova-2-Technopolis-Steel-piles-utilising-ground-source-heat
can be dealt with in several ways: by using stainless steel
The EU climate and energy package. 2008. http://ec.europa.eu/clima/
parts, by covering the piles with grout, by using extra steel policies/package/index_en.htm
bars inside the piles, or by using thicker material. The The Finnish Heat Pump Association SULPU. Now more than half a
hybrid energy piles may also contain a smaller inner pile million heat pumps, 2013. http://www.sulpu.fi/in-english
inside the load-bearing pile and thus forming a composite Tompuri, V. 2010. Energy pile is a secret that is kept in silence,
Energiapaalu on vaiettu salaisuus, Rakennuslehti 4?2?2010.
structure. Available only in Finnish.
There are still challenges and questions to be tackled Uotinen, V.-M., Repo, T. and Vesamäki, H. 2012. Energy piles – ground
and answered concerning the installation, for example in energy systems integrated to steel foundations piles, NGM 2012