PATNA BLOCK-C PLAN VS ACTUAL (PEB)

Date- 14-Mar

Base Line Start date

Base Line End date

Till Date Complete


Balance Quantity

15-Mar

16-Mar

17-Mar

18-Mar

19-Mar

20-Mar
Complete Up To
Total Quantity

previous week

Till Date % of

REMARKS
Weekly Cumulative

Achivment
Unit
Construction Activities

Achive
ment
Plan
P A P A P A P A P A P A

PEB Activities
Material Fabrication/ Inspection at Factory Ton 1700 450 11/27/2023 3/30/2024 1250.00 1250 74%

Receipt of Materials at site Ton 1700.00 599.390 12/7/2023 4/10/2024 1052.84 17.77 30.00 1100.61 65%

Main frame Erection with Mezznine


Column Erection nos 290 120 12/10/2023 3/5/2024 170.00 0 0 170 59%

Jack beam Erection nos 84 34 12/15/2023 3/12/2024 47.00 1 2 0 3 50 60%

Mezzanine Beam Erection nos 123 61 12/15/2023 3/12/2024 62.00 0 0 62 50%

Joist Erection nos 396 352 12/20/2023 4/3/2024 44.00 0 0 44 11%

Rafter nos 210 86 12/25/2023 3/13/2024 117.00 1 3 3 0 7 124 59%

Canopy Rafter nos 71 31 1/17/2023 3/15/2024 40.00 0 0 40 56%

Alignment//Secondary framming //Tightning


Clit nos 1134 856 12/29/2023 3/28/2024 278.00 0 0 278 25%

"Z" Purlin nos 4717 2121 12/29/2023 3/28/2024 2442.00 28 12 50 64 0 154 2596 55%

"C" Purling nos 282 249 2/5/2024 3/28/2024 29.00 2 2 0 4 33 12%

Bracing Road nos 408 219 1/5/2024 4/1/2024 179.00 10 0 10 189 46%

Sag Road nos 12467 7849 1/10/2024 4/1/2024 4276.00 172 150 20 0 342 4618 37%

Flange Bracing (F.B.C) nos 8660 4561 12/25/2023 4/1/2024 3875.00 90 70 14 50 0 224 4099 47%

Strut Pipe (STP) nos 20 14 1/31/2024 4/1/2024 5.00 1 0 1 6 30%

JAL ANGEL nos 336 231 105.00 0 0 105 31%

IC ANGEL nos 241 146 95.00 0 0 95 39%

RAC ANGEL nos 372 189 183.00 0 0 183 49%

Monitor erection noc 28 22 2/5/2024 3/30/2024 6.00 0 0 6 21%

Roof Insulation SQM 45219 29918 2/9/2024 4/4/2024 12309.00 440.00 440 1232 880 0 2992.00 15301.00 34%

SSR Sheet profiling Ton 0 0 2/9/2024 4/4/2024 0.00 0 0 0 #DIV/0!

SSR Sheet Profiling Machine Preparation 0 0 2/6/2024 2/8/2024 0.00 0 0 0 #DIV/0!

Roofing/ Sheeting work Erection SQM 45,219.00 29918 2/10/2024 4/4/2024 12309.00 440.00 440 1232 880 0 2992.00 15301.00 34%

Cladding Insulation - 0 2/25/2024 4/14/2024 0.00 0 0 0 #DIV/0!

Cladding work Errection Sqft 0 0 2/25/2024 4/14/2024 0.00 0 0 0 #DIV/0!

Canopy Sheet Sqft 0 3/18/2024 4/5/2024 0.00 0 0 0

Mezzanine Deck Sheeting Sqft 0 3/20/2024 4/1/2024 0.00 0 0 0

Downtake pipe / Gutters & Finishing Rm 0 4/6/2024 4/20/2024 0.00 0 0 0


466931.15445504
778.53 -322.08
LABOUR DEPLOYMENT OF DIFFERENT ACTIVITIES

Total No. of

FORMAN

RIGGER

FITTER
Labour
SL NO

Helper
Descripion of Activities REMARKS

Material sarching & shifting 6 3 0 3


1

Material assembly 8 1 4 1 2
2

Primary Erection 4 0 1 1 2
3

Secondary Erection 20 1 16 0 3
4

Roof sheeting 30 30
5

TOTAL MANPOWER 68 2 54 2 10

MAN POWER AND EQUIPMENT DETAILS EQUIPMENT DETAILS

EQUIPMENT

PLAN
MANPOWER DETAILS PLANNED ACTUAL Remarks
NO
SL

REM
ARK
UAL
ACT
NED

S
1 Sr. Project Manager 1
2 Project Manager - 1 Torque Wrinch - 2
3 Engineer's - 1 WATER TANKER - 0
4 Safety Officer - 1 Hydra - 3
5 Supervisor - 2
6 FOUR MAN - 2
7 RIGGER - 54
8 FITTER - 2
9 Helper/Unskilled - 10
12 Eqpt Operator - 4

TOTAL 78
PATNA BLOCK-C PLAN VS ACTUAL (PEB)
Date- 9-Mar

Till Date % of Achivment


Complete Up To previous
Base Line Start date

4-Feb

5-Feb

6-Feb

7-Feb

8-Feb

9-Feb
Base Line End date

Till Date Complete


Balance Quantity
Weekly Cumulative

This week achive


Total Quantity

REMARKS
persentage
week
Unit
Construction Activities

Achivement
Plan
P A P A P A P A P A P A

PEB Activities
Material Fabrication/ Inspection at Factory Ton 1700 600 11/27/2023 3/30/2024 1100.00 1100 65%

Receipt of Materials at site Ton 1700.00 679.780 12/7/2023 4/10/2024 1020.22 1020.22 60%

Main frame Erection with Mezznine 0.00


Column Erection nos 290 120 12/10/2023 3/5/2024 163.00 3 2 2 0 7 #DIV/0! 170 59%

Jack beam Erection nos 84 37 12/15/2023 3/12/2024 47.00 0 0 #DIV/0! 47 56%

Mezzanine Beam Erection nos 123 61 12/15/2023 3/12/2024 60.00 2 0 2 #DIV/0! 62 50%

Joist Erection nos 396 352 12/20/2023 4/3/2024 44.00 0 0 #DIV/0! 44 11%

Rafter nos 210 93 12/25/2023 3/13/2024 102.00 3 3 3 2 2 2 3 3 6 15 250% 117 56%

Canopy Rafter nos 71 31 1/17/2023 3/15/2024 40.00 0 0 #DIV/0! 40 56%

Alignment//Secondary framming //Tightning 0.00


Clit nos 1134 856 12/29/2023 3/28/2024 278.00 0 0 #DIV/0! 278 25%

"Z" Purlin nos 4717 2275 12/29/2023 3/28/2024 2198.00 32 20 28 20 56 20 28 22 20 78 80 244 305% 2442 52%

"C" Purling nos 282 261 2/5/2024 3/28/2024 11.00 5 5 0 10 #DIV/0! 21 7%

Bracing Road nos 408 229 1/5/2024 4/1/2024 155.00 8 12 4 0 24 #DIV/0! 179 44%

Sag Road nos 12467 8191 1/10/2024 4/1/2024 3668.00 200 20 68 20 20 44 196 20 100 80 608 760% 4276 34%

Flange Bracing (F.B.C) nos 8660 4785 12/25/2023 4/1/2024 3211.00 44 250 186 44 140 0 664 #DIV/0! 3875 45%

Strut Pipe (STP) nos 20 15 1/31/2024 4/1/2024 3.00 1 1 0 2 #DIV/0! 5 25%

JAL ANGEL nos 336 231 105.00 0 0 #DIV/0! 105 31%

IC ANGEL nos 241 146 95.00 0 0 #DIV/0! 95 39%

RAC ANGEL nos 372 189 90.00 93 93 93 93 100% 183 49%

Monitor erection noc 28 22 2/5/2024 3/30/2024 6.00 0 0 6 21%

Roof Insulation SQM 45219 32910 2/9/2024 4/4/2024 7160.89 308.00 800 800 1628 900 968 800 924.11 700 1320 4000 5148.11 12309.00 27%

SSR Sheet profiling Ton 0 2/9/2024 4/4/2024 0.00 0 0 0


SSR Sheet Profiling Machine Preparation 0 2/6/2024 2/8/2024 0.00 0 0 0
Roofing/ Sheeting work Erection SQM 45,219.00 32910 2/10/2024 4/4/2024 7160.89 308.00 800 800 1628 900 968 800 924.11 700 1320 4000 5148.11 12309.00 27%

Cladding Insulation 0 2/25/2024 4/14/2024 0.00 0 0 0


Cladding work Errection Sqft 0 2/25/2024 4/14/2024 0.00 0 0 0

Canopy Sheet Sqft 0 3/18/2024 4/5/2024 0.00 0 0 0

Mezzanine Deck Sheeting Sqft 0 3/20/2024 4/1/2024 0.00 0 0 0

Downtake pipe / Gutters & Finishing Rm 0 4/6/2024 4/20/2024 0.00 0 0 0


466931.15445504
778.53 -241.69
LABOUR DEPLOYMENT OF DIFFERENT ACTIVITIES

Total No. of

FORMAN

RIGGER

FITTER
Labour
SL NO

Helper
Descripion of Activities REMARKS

Material sarching & shifting 6 3 0 3


1

Material assembly 8 1 4 1 2
2

Primary Erection 4 0 1 1 2
3

Secondary Erection 20 1 16 0 3
4

Roof sheeting 30 30
5

TOTAL MANPOWER 68 2 54 2 10

MAN POWER AND EQUIPMENT DETAILS EQUIPMENT DETAILS

EQUIPMENT

PLAN
MANPOWER DETAILS PLANNED ACTUAL Remarks
NO
SL

REM
ARK
UAL
ACT
NED

S
1 Sr. Project Manager 1
2 Project Manager - 1 Torque Wrinch - 2
3 Engineer's - 1 WATER TANKER - 0
4 Safety Officer - 1 Hydra - 3
5 Supervisor - 2
6 FOUR MAN - 2
7 RIGGER - 54
8 FITTER - 2
9 Helper/Unskilled - 10
12 Eqpt Operator - 4

TOTAL 78
PATNA BLOCK-C PLAN VS ACTUAL (PEB)

Date- 2-Mar

Till Date % of Achivment


Complete Up To previous
Base Line Start date

26-Feb

27-Feb

28-Feb

29-Feb
Base Line End date

1-Mar

2-Mar

Till Date Complete


Balance Quantity

This week achive


Weekly Cumulative

Total Quantity

Balance Days

REMARKS
persentage
Plan / Day

week
Unit
Construction Activities

Achivement
Plan
P A P A P A P A P A P A

PEB Activities

Material Fabrication/ Inspection at Factory Ton 1700 600 11/27/2023 3/30/2024 13 131 1000.00 100 1100 65%

Receipt of Materials at site Ton 1700.00 679.780 12/7/2023 4/10/2024 24 71 979.60 40.62 1020.22 60%

Main frame Erection with Mezznine 0 0.00

Column Erection nos 290 127 12/10/2023 3/5/2024 -12 -11 151.00 3 5 4 0 12 #DIV/0! 163 56%

Jack beam Erection nos 84 37 12/15/2023 3/12/2024 -5 -7 47.00 0 0 #DIV/0! 47 56%

Mezzanine Beam Erection nos 123 63 12/15/2023 3/12/2024 -5 -13 56.00 2 1 1 0 4 #DIV/0! 60 49%

Joist Erection nos 396 352 12/20/2023 4/3/2024 17 21 44.00 0 0 #DIV/0! 44 11%

Rafter nos 210 108 12/25/2023 3/13/2024 -4 -27 101.00 1 0 1 #DIV/0! 102 49%

Canopy Rafter nos 71 31 1/17/2023 3/15/2024 35.00 5 0 5 #DIV/0! 40 56%

Alignment//Secondary framming //Tightning 0.00

Clit nos 1134 856 12/29/2023 3/28/2024 11 78 278.00 0 0 #DIV/0! 278 25%

"Z" Purlin nos 4717 2519 12/29/2023 3/28/2024 11 229 2151.00 18 9 20 0 47 #DIV/0! 2198 47%

"C" Purling nos 282 271 2/5/2024 3/28/2024 52 5 11.00 0 0 #DIV/0! 11 4%

Bracing Road nos 408 253 1/5/2024 4/1/2024 87 3 153.00 2 0 2 #DIV/0! 155 38%

Sag Road nos 12467 8799 1/10/2024 4/1/2024 82 107 2696.00 78 108 138 208 192 248 0 972 #DIV/0! 3668 29%

Flange Bracing (F.B.C) nos 8660 5449 12/25/2023 4/1/2024 15 363 2966.00 70 21 20 30 40 64 0 245 #DIV/0! 3211 37%

Strut Pipe (STP) nos 20 17 1/31/2024 4/1/2024 61 0 2.00 1 0 1 #DIV/0! 3 15%

JAL ANGEL nos 336 231 105.00 0 0 #DIV/0! 105 31%

IC ANGEL nos 241 146 95.00 0 0 #DIV/0! 95 39%

RAC ANGEL nos 372 282 90.00 0 0 #DIV/0! 90 24%

Monitor erection noc 28 22 2/5/2024 3/30/2024 54 6.00 0 0 6 21%

Roof Insulation SQM 45219 38058 2/9/2024 4/4/2024 55 1425.72 968.85 1025 880 924 968.66 969 0 5735.17 7160.89 16%

SSR Sheet profiling Ton 0 2/9/2024 4/4/2024 55 0.00 0 0 0

SSR Sheet Profiling Machine Preparation 0 2/6/2024 2/8/2024 2 0.00 0 0 0

Roofing/ Sheeting work Erection SQM 45,219.00 38058 2/10/2024 4/4/2024 54 1425.72 968.85 1025 880 924 968.66 969 0 5735.17 7160.89 16%

Cladding Insulation 0 2/25/2024 4/14/2024 49 0.00 0 0 0

Cladding work Errection Sqft 0 2/25/2024 4/14/2024 49 0.00 0 0 0

Canopy Sheet Sqft 0 3/18/2024 4/5/2024 18 0.00 0 0 0

Mezzanine Deck Sheeting Sqft 0 3/20/2024 4/1/2024 12 0.00 0 0 0

Downtake pipe / Gutters & Finishing Rm 0 4/6/2024 4/20/2024 60 0.00 0 0 0


NOTE:-
1. The work stopped for two days (13TH & 14TH FEB 2024) due to rain.
466931.15445504
778.53 -241.69
LABOUR DEPLOYMENT OF DIFFERENT ACTIVITIES

Total No. of

FORMAN

RIGGER

FITTER
Labour
SL NO

Helper
Descripion of Activities REMARKS

Material sarching & shifting 6 3 0 3


1

Material assembly 8 1 4 1 2
2

Primary Erection 4 0 1 1 2
3

Secondary Erection 20 1 16 0 3
4

Roof sheeting 30 30
5

TOTAL MANPOWER 68 2 54 2 10

MAN POWER AND EQUIPMENT DETAILS EQUIPMENT DETAILS


SL NO

REMARKS
PLANNED
MANPOWER DETAILS PLANNED ACTUAL Remarks EQUIPMENT

ACTUAL
1 1
Sr. Project Manager

2 Torque Wrinch 2
Project Manager - 1 -

3 WATER TANKER 0
Engineer's - 1 -

4 Hydra
Safety Officer - 1 - 3

5
Supervisor - 2

6
FOUR MAN - 2

7
RIGGER - 54

8
FITTER - 2

9
Helper/Unskilled - 10

12
Eqpt Operator - 4

TOTAL 78
PATNA BLOCK-C PLAN VS ACTUAL (PEB)
Date- 24-Feb

Base Line Start date

19-Feb

20-Feb

21-Feb

22-Feb

23-Feb

24-Feb
Base Line End date

Till Date Complete


Weekly

Balance Quantity

This week achive


Complete Up To
Total Quantity

previous week

Till Date % of
Cumulative

REMARKS
Achivment
persentage
Unit

Achivement
Construction Activities

Plan
P A P A P A P A P A P A

PEB Activities
Material Fabrication/ Inspection at Factory Ton 1700 700 11/27/2023 3/30/2024 1000.00 1000 59%

Receipt of Materials at site Ton 1700.00 720.400 12/7/2023 4/10/2024 923.90 55.70 979.60 58%

Main frame Erection with Mezznine 0.00


Column Erection nos 290 139 12/10/2023 3/5/2024 147.00 4 0 4 #DIV/0! 151 52%

Jack beam Erection nos 84 37 12/15/2023 3/12/2024 45.00 2 0 2 #DIV/0! 47 56%

Mezzanine Beam Erection nos 123 67 12/15/2023 3/12/2024 55.00 1 0 1 #DIV/0! 56 46%

Joist Erection nos 396 352 12/20/2023 4/3/2024 44.00 0 0 #DIV/0! 44 11%

Rafter nos 210 109 12/25/2023 3/13/2024 94.00 6 1 0 7 #DIV/0! 101 48%

Canopy Rafter nos 71 36 1/17/2023 3/15/2024 35.00 0 0 #DIV/0! 35 49%

Alignment//Secondary framming //Tightning 0.00


Clit nos 1134 856 12/29/2023 3/28/2024 278.00 0 0 #DIV/0! 278 25%

"Z" Purlin nos 4717 2566 12/29/2023 3/28/2024 1896.00 88 18 18 6 16 109 0 255 #DIV/0! 2151 46%

"C" Purling nos 282 271 2/5/2024 3/28/2024 11.00 0 0 #DIV/0! 11 4%

Bracing Road nos 408 255 1/5/2024 4/1/2024 131.00 18 4 0 22 #DIV/0! 153 38%

Sag Road nos 12467 9884 1/10/2024 4/1/2024 2096.00 103 96 96 122 70 0 487 #DIV/0! 2583 21%

Flange Bracing (F.B.C) nos 8660 5694 12/25/2023 4/1/2024 2339.00 116 110 96 60 70 175 0 627 #DIV/0! 2966 34%

Strut Pipe (STP) nos 20 18 1/31/2024 4/1/2024 2.00 0 0 #DIV/0! 2 10%

JAL ANGEL nos 336 231 79.00 8 18 0 26 #DIV/0! 105 31%

IC ANGEL nos 241 146 0.00 23 28 24 20 0 95 #DIV/0! 95 39%

RAC ANGEL nos 372 282 0.00 90 0 90 #DIV/0! 90 24%

Monitor erection noc 28 22 2/5/2024 3/30/2024 0.00 6 0 6 6 21%

Roof Insulation SQM 45219 43793 2/9/2024 4/4/2024 0.00 223 447 756 0 1426 1426 3%

SSR Sheet profiling Ton 0 2/9/2024 4/4/2024 0.00 0 0 0


SSR Sheet Profiling Machine Preparation 0 2/6/2024 2/8/2024 0.00 0 0 0
Roofing/ Sheeting work Erection SQM 45,219.00 43793 2/10/2024 4/4/2024 0.00 223 447 756 0 1426 1426 3%

Cladding Insulation 0 2/25/2024 4/14/2024 0.00 0 0 0


Cladding work Errection Sqft 0 2/25/2024 4/14/2024 0.00 0 0 0
Canopy Sheet Sqft 0 3/18/2024 4/5/2024 0.00 0 0 0
Mezzanine Deck Sheeting Sqft 0 3/20/2024 4/1/2024 0.00 0 0 0
Downtake pipe / Gutters & Finishing Rm 0 4/6/2024 4/20/2024 0.00 0 0 0
NOTE:-
1. The work stopped for two days (13TH & 14TH FEB 2024) due to rain.

466931.15445504
778.53 -201.07
LABOUR DEPLOYMENT OF DIFFERENT ACTIVITIES

Total No. of

FORMAN

RIGGER

FITTER
SL NO

Labour

Helper
Descripion of Activities REMARKS

Material sarching & shifting 6 4 0 2


1

Material assembly 10 0 8 2 4
2

Primary Erection 13 1 5 1 1
3

Secondary Erection 18 1 16 1 1
4

TOTAL MANPOWER 47 2 33 4 8

MAN POWER AND EQUIPMENT DETAILS EQUIPMENT DETAILS

REMARKS
PLANNED
SL NO

ACTUAL
MANPOWER DETAILS PLANNED ACTUAL Remarks EQUIPMENT

1 1
Sr. Project Manager
2 Torque Wrinch 2
Project Manager - 1 -
3 Engineer's - 1 WATER TANKER - 0
4 Safety Officer - 1 Hydra - 3
5 Supervisor - 2
6 FOUR MAN - 2
7 RIGGER - 33
8 FITTER - 4
9 Helper/Unskilled - 8
12 Eqpt Operator - 4

TOTAL 57
PATNA BLOCK-C PLAN VS ACTUAL (PEB)
Date- 17-Feb

Base Line End date

Till Date Complete


Balance Quantity

This week achive


Complete Up To
Base Line Start
Total Quantity

previous week

Till Date % of
12-Feb

13-Feb

14-Feb

15-Feb

16-Feb

17-Feb

REMARKS
Weekly

Achivment
persentage
Cumulative

Unit

date
Construction Activities

Achiv
Plan
P A P A P A P A P A P A

e
PEB Activities
Material Fabrication/ Inspection at Factory Ton 1700 700 11/27/2023 3/30/2024 1000.00 1000 59%

Receipt of Materials at site Ton 1700.00 776.100 12/7/2023 4/10/2024 843.97 41 39.1 923.90 54%

Main frame Erection with Mezznine


Column Erection nos 290 143 12/10/2023 3/5/2024 147.00 0 0 #DIV/0! 147 51%
Jack beam Erection nos 84 39 12/15/2023 3/12/2024 45.00 0 0 #DIV/0! 45 54%
Mezzanine Beam Erection nos 123 68 12/15/2023 3/12/2024 55.00 0 0 #DIV/0! 55 45%
Joist Erection nos 396 352 12/20/2023 4/3/2024 44.00 0 0 #DIV/0! 44 11%
Rafter nos 210 116 12/25/2023 3/13/2024 94.00 0 0 #DIV/0! 94 45%
Canopy Rafter nos 71 36 1/17/2023 3/15/2024 35.00 0 0 #DIV/0! 35 49%
Alignment//Secondary framming //Tightning
Clit nos 1134 856 12/29/2023 3/28/2024 278.00 0 0 #DIV/0! 278 25%
"Z" Purlin nos 4717 2821 12/29/2023 3/28/2024 1679.00 45 57 75 40 0 217 #DIV/0! 1896 40%
"C" Purling nos 282 271 2/5/2024 3/28/2024 11.00 0 0 #DIV/0! 11 4%
Bracing Road nos 408 277 1/5/2024 4/1/2024 111.00 7 6 7 0 20 #DIV/0! 131 32%
Sag Road nos 12467 10371 1/10/2024 4/1/2024 1646.00 112 130 132 76 0 450 #DIV/0! 2096 17%
Flange Bracing (F.B.C) nos 8660 6321 12/25/2023 4/1/2024 1933.00 162 160 84 0 406 #DIV/0! 2339 27%
Strut Pipe (STP) nos 20 18 1/31/2024 4/1/2024 2.00 0 0 #DIV/0! 2 10%
JAL ANGEL nos 336 257 0.00 20 0 18 18 23 0 79 #DIV/0! 79 24%
Monitor erection 2/5/2024 3/30/2024 0.00 0 0 0
Roof Insulation sqf 2/9/2024 4/4/2024 0.00 0 0 0
SSR Sheet profiling Ton 0 2/9/2024 4/4/2024 0.00 0 0 0
SSR Sheet Profiling Machine Preparation 0 2/6/2024 2/8/2024 0.00 0 0 0
Roofing/ Sheeting work Erection Sqft 0 2/10/2024 4/4/2024 0.00 0 0 0
Cladding Insulation 0 2/25/2024 4/14/2024 0.00 0 0 0
Cladding work Errection Sqft 0 2/25/2024 4/14/2024 0.00 0 0 0
Canopy Sheet Sqft 0 3/18/2024 4/5/2024 0.00 0 0 0
Mezzanine Deck Sheeting Sqft 0 3/20/2024 4/1/2024 0.00 0 0 0
Downtake pipe / Gutters & Finishing Rm 0 4/6/2024 4/20/2024 0.00 0 0 0

NOTE:-
1. The work stopped for two days (13TH & 14TH FEB 2024) due to rain.
778.53 -145.37
39.0599999999999
LABOUR DEPLOYMENT OF DIFFERENT ACTIVITIES

Total No. of

FORMAN

RIGGER

FITTER
SL NO

Labour

Helper
Descripion of Activities REMARKS

Material sarching & shifting 6 4 0 2


1

Material assembly 10 0 8 2 4
2

Primary Erection 13 1 5 1 1
3

Secondary Erection 18 1 16 1 1
4

TOTAL MANPOWER 47 2 33 4 8

MAN POWER AND EQUIPMENT DETAILS EQUIPMENT DETAILS

REMARKS
PLANNED
SL NO

ACTUAL
MANPOWER DETAILS PLANNED ACTUAL Remarks EQUIPMENT

1 1
Sr. Project Manager
2 Torque Wrinch 2
Project Manager - 1 -

3 WATER TANKER 0
Engineer's - 1 -

4 Hydra
Safety Officer - 1 - 3
5 Supervisor - 2
6 FOUR MAN - 2
7 RIGGER - 33
8 FITTER - 4
9 Helper/Unskilled - 8
12 Eqpt Operator - 4

TOTAL 57
PATNA BLOCK-C PLAN VS ACTUAL (PEB)
Date- 10-Feb

Till Date % of Achivment


Complete Up To previous
Base Line Start date

Base Line End date

10-Feb

Till Date Complete


5-Feb

6-Feb

7-Feb

8-Feb

9-Feb
Weekly

Balance Quantity

This week achive


Total Quantity
Cumulative

REMARKS
persentage
week
Unit
Construction Activities

Achive
Plan
P A P A P A P A P A P A

PEB Activities

Material Fabrication/ Inspection at Factory Ton 1700 700 11/27/2023 3/30/2024 900.00 100 1000 59%

Receipt of Materials at site Ton 1700.00 856.030 12/7/2023 4/10/2024 795.18 20.29 28.5 843.97 50%

Main frame Erection with Mezznine

Column Erection nos 290 143 12/10/2023 3/5/2024 132.00 3 2 8 3 2 5 3 2 2 15 15 100% 147 51%

Jack beam Erection nos 84 39 12/15/2023 3/12/2024 40.00 1 2 1 3 1 1 1 2 7 5 71% 45 54%

Mezzanine Beam Erection nos 123 68 12/15/2023 3/12/2024 42.00 1 1 1 6 1 4 1 2 2 1 7 13 186% 55 45%

Joist Erection nos 396 352 12/20/2023 4/3/2024 44.00 1 2 2 2 3 4 14 0 0% 44 11%

Rafter nos 210 116 12/25/2023 3/13/2024 91.00 3 3 1 3 1 3 3 1 3 18 3 17% 94 45%

Canopy Rafter nos 71 36 1/17/2023 3/15/2024 33.00 1 1 2 1 1 1 1 6 2 33% 35 49%

Alignment//Secondary framming //Tightning

Clit nos 1134 856 12/29/2023 3/28/2024 278.00 3 3 3 3 3 3 18 0 0% 278 25%

"Z" Purlin nos 4717 3038 12/29/2023 3/28/2024 1568.00 20 12 20 6 20 8 20 31 20 35 54 135 111 82% 1679 36%

"C" Purling nos 282 271 2/5/2024 3/28/2024 0.00 5 8 10 5 5 3 5 5 35 11 31% 11 4%

Bracing Road nos 408 297 1/5/2024 4/1/2024 66.00 5 6 5 9 5 10 11 5 10 5 9 35 45 129% 111 27%

Sag Road nos 12467 10821 1/10/2024 4/1/2024 1148.00 50 60 50 84 50 50 342 50 12 50 300 498 166% 1646 13%

Flange Bracing (F.B.C) nos 8660 6727 12/25/2023 4/1/2024 1350.00 40 46 30 72 30 40 130 30 48 50 287 220 583 265% 1933 22%

Strut Pipe (STP) nos 20 18 1/31/2024 4/1/2024 2.00 2 1 1 1 1 1 7 0 2

Monitor erection 2/5/2024 3/30/2024 0.00 0 0 0

Roof Insulation sqf 2/9/2024 4/4/2024 0.00 0 0 0

SSR Sheet profiling Ton 0 2/9/2024 4/4/2024 0.00 0 0 0

SSR Sheet Profiling Machine Preparation 0 2/6/2024 2/8/2024 0.00 0 0 0

Roofing/ Sheeting work Erection Sqft 0 2/10/2024 4/4/2024 0.00 0 0 0

Cladding Insulation 0 2/25/2024 4/14/2024 0.00 0 0 0

Cladding work Errection Sqft 0 2/25/2024 4/14/2024 0.00 0 0 0

Canopy Sheet Sqft 0 3/18/2024 4/5/2024 0.00 0 0 0

Mezzanine Deck Sheeting Sqft 0 3/20/2024 4/1/2024 0.00 0 0 0


Downtake pipe / Gutters & Finishing Rm 0 4/6/2024 4/20/2024 0.00 0 0 0
778.53 -65.44
LABOUR DEPLOYMENT OF DIFFERENT ACTIVITIES

Total No. of

FORMAN

RIGGER

FITTER
SL NO

Labour

Helper
Descripion of Activities REMARKS

Material sarching & shifting 6 4 0 2


1

Material assembly 10 0 8 2 4
2

Primary Erection 13 1 5 1 1
3

Secondary Erection 18 1 16 1 1
4

TOTAL MANPOWER 47 2 33 4 8

MAN POWER AND EQUIPMENT DETAILS EQUIPMENT DETAILS


SL NO

REMARK
ACTUAL
PLANNE
MANPOWER DETAILS PLANNED ACTUAL Remarks EQUIPMENT

S
D
1 1
Sr. Project Manager
2 Torque Wrinch 2
Project Manager - 1 -

3 WATER TANKER 0
Engineer's - 1 -

4 Hydra
Safety Officer - 1 - 4
5
Supervisor - 2
6
FOUR MAN - 2
7
RIGGER - 33
8
FITTER - 4
9
Helper/Unskilled - 8
12
Eqpt Operator - 5

TOTAL 58
PATNA BLOCK-C PLAN VS ACTUAL (PEB)
Date- 3-Feb

Base Line Start date

Base Line End date

Till Date Complete


Balance Quantity

This week achive


29-Jan

30-Jan

31-Jan
Complete Up To

1-Feb

2-Feb

3-Feb
Weekly

Total Quantity

previous week

Till Date % of

REMARKS
Achivment
persentage
Cumulative

Unit
Construction Activities

Achive
Plan
P A P A P A P A P A P A

PEB Activities

Material Fabrication/ Inspection at Factory Ton 1700 800 11/27/2023 3/30/2024 900.00 100 900 53%

Receipt of Materials at site Ton 1700.00 904.820 12/7/2023 4/10/2024 686.99 60.00 31.54 16.65 795.18 47%

Column Erection nos 290 158 12/10/2023 3/5/2024 123.00 3 1 2 3 3 2 3 1 2 4 15 9 60% 132 46%

Jack beam Erection nos 84 44 12/15/2023 3/12/2024 33.00 1 2 1 3 1 2 1 0 1 2 7 7 100% 40 48%

Mezzanine Beam Erection nos 123 81 12/15/2023 3/12/2024 38.00 1 1 1 1 2 1 2 2 7 4 57% 42 34%

Joist Erection nos 396 352 12/20/2023 4/3/2024 44.00 1 2 2 2 3 4 14 0 0% 44 11%

Rafter nos 210 119 12/25/2023 3/13/2024 78.00 2 2 2 3 2 1 2 3 2 6 12 13 108% 91 43%

Canopy Rafter nos 71 38 1/17/2023 3/15/2024 33.00 1 1 1 1 1 2 7 0 0% 33 46%

Alignment//Secondary framming //Tightning


Clit nos 1134 856 12/29/2023 3/28/2024 278.00 3 3 3 3 3 3 18 0 0% 278 25%

"Z" Purlin nos 4717 3149 12/29/2023 3/28/2024 1493.00 20 25 20 20 20 17 20 20 10 35 3 135 75 56% 1568 33%

"C" Purling nos 282 282 2/5/2024 3/28/2024 0.00 0 0 #DIV/0! 0 0%

Bracing Road nos 408 342 1/5/2024 4/1/2024 25.00 5 6 5 5 7 6 10 6 8 5 10 32 41 128% 66 16%

Sag Road nos 12467 11319 1/10/2024 4/1/2024 579.00 50 36 50 89 50 108 50 66 50 74 50 196 300 569 190% 1148 9%

Flange Bracing (F.B.C) nos 8660 7310 12/25/2023 4/1/2024 804.00 30 72 40 58 50 84 30 116 40 88 40 128 230 546 237% 1350 16%

Strut Pipe (STP) nos 20 18 1/31/2024 4/1/2024 0.00 2 0 2 2


Monitor erection 2/5/2024 3/30/2024 0.00 0 0 0
Roof Insulation sqf 2/9/2024 4/4/2024 0.00 0 0 0
SSR Sheet profiling Ton 0 2/9/2024 4/4/2024 0.00 0 0 0
SSR Sheet Profiling Machine Preparation 0 2/6/2024 2/8/2024 0.00 0 0 0
Roofing/ Sheeting work Erection Sqft 0 2/10/2024 4/4/2024 0.00 0 0 0
Cladding Insulation 0 2/25/2024 4/14/2024 0.00 0 0 0
Cladding work Errection Sqft 0 2/25/2024 4/14/2024 0.00 0 0 0
Canopy Sheet Sqft 0 3/18/2024 4/5/2024 0.00 0 0 0
Mezzanine Deck Sheeting Sqft 0 3/20/2024 4/1/2024 0.00 0 0 0

Downtake pipe / Gutters & Finishing Rm 0 4/6/2024 4/20/2024 0.00 0 0 0


778.53 -16.65
LABOUR DEPLOYMENT OF DIFFERENT ACTIVITIES

Total No. of

FORMAN

RIGGER

FITTER
SL NO

Labour

Helper
Descripion of Activities REMARKS

Material sarching & shifting 6 4 0 2


1

Material assembly 10 0 8 2 4
2

Primary Erection 13 1 5 1 1
3

Secondary Erection 16 1 14 1 1
4

TOTAL MANPOWER 45 2 31 4 8

MAN POWER AND EQUIPMENT DETAILS EQUIPMENT DETAILS

REMARKS
PLANNED
SL NO

ACTUAL
MANPOWER DETAILS PLANNED ACTUAL Remarks EQUIPMENT

1 1
Sr. Project Manager
2 Torque Wrinch 2
Project Manager - 1 -

3 WATER TANKER 0
Engineer's - 1 -
4 Safety Officer - 1 Hydra - 4
5 Supervisor - 2
6 FOUR MAN - 2
7 RIGGER - 31
8 FITTER - 4
9 Helper/Unskilled - 8
12 Eqpt Operator - 5

TOTAL 56
PATNA BLOCK-C PLAN VS ACTUAL (PEB)
Date- 27-Jan

Base Line Start date

Base Line End date

Till Date Complete


22-Jan

23-Jan

24-Jan

25-Jan

26-Jan

27-Jan
Balance Quantity

This week achive


Weekly

Complete Up To
Total Quantity

previous week

Till Date % of
Balance Days

REMARKS
Cumulative

Achivment
persentage
Plan / Day
Unit
Construction Activities

Achive
Plan
P A P A P A P A P A P A

PEB Activities
Material Fabrication/ Inspection at Factory Ton 1700 800 11/27/2023 2/15/2024 -31 -55 750.00 150 150 900 53%

Receipt of Materials at site Ton 1700.00 1013.010 12/7/2023 3/26/2024 9 189 671.89 15.10 686.990 40%

Column Erection nos 290 167 12/10/2023 3/6/2024 -11 -15 112.00 3 2 2 6 3 2 3 2 3 15 11 73% 123 42%

Jack beam Erection nos 84 51 12/15/2023 3/7/2024 -10 -5 30.00 1 1 1 1 1 1 2 2 7 3 43% 33 39%

Mezzanine Beam Erection nos 123 85 12/15/2023 3/7/2024 -10 -9 36.00 1 1 1 1 2 1 2 7 2 29% 38 31%

Joist Erection nos 396 352 12/20/2023 3/7/2024 -10 -35 5.00 1 2 11 2 14 2 14 3 4 0 14 39 279% 44 11%

Rafter nos 210 132 12/25/2023 3/9/2024 -8 -17 70.00 2 3 2 2 1 2 2 2 4 12 8 67% 78 37%

Canopy Rafter nos 71 38 33.00 1 1 1 1 1 2 7 0 0% 33 46%

Clit nos 1134 856 12/29/2023 2/8/2024 -38 -23 278.00 3 3 3 3 3 3 18 0 0% 278 25%

"Z" Purlin nos 4717 3224 12/29/2023 3/28/2024 11 293 1388.00 20 35 20 20 20 32 20 30 38 130 105 81% 1493 32%

"C" Purling nos 282 282 1/15/2024 3/20/2024 65 4 0.00 0 0 #DIV/0! 0 0%

Bracing Road nos 408 383 1/5/2024 3/20/2024 75 5 0.00 6 7 6 12 6 25 417% 25 6%

Sag Road nos 12467 11888 1/10/2024 3/28/2024 78 152 362.00 50 88 50 50 48 50 73 50 50 8 300 217 72% 579 5%

Flange Bracing (F.B.C) nos 8660 7856 12/25/2023 3/28/2024 11 714 680.00 30 40 40 40 40 60 124 250 124 50% 804 9%

Strut Pipe (STP) nos 20 20 1/1/2024 3/28/2024 87 0 0.00 0 0 0


Monitor erection 1/15/2024 3/28/2024 73 0.00 0 0 0
Roof Insulation sqf 1/25/2024 3/30/2024 65 0.00 0 0 0
SSR Sheet profiling Ton 0 1/20/2024 3/10/2024 50 0.00 0 0 0
SSR Sheet Profiling Machine Preparation 0 1/20/2024 1/30/2024 10 0.00 0 0 0
Roofing/ Sheeting work Erection Sqft 0 2/7/2024 4/12/2024 65 0.00 0 0 0
Cladding Insulation 0 2/17/2024 4/10/2024 53 0.00 0 0 0
Cladding work Errection Sqft 0 2/22/2024 4/15/2024 53 0.00 0 0 0
Canopy Sheet Sqft 0 2/29/2024 4/15/2024 46 0.00 0 0 0
Mezz Structure Sqft 0 1/24/2024 3/9/2024 45 0.00 0 0 0
Deck Sheeting Ton 0 2/28/2024 3/14/2024 15 0.00 0 0 0

Downtake pipe / Gutters & Finishing Rm 0 2/23/2024 4/23/2024 60 0.00 0 0 0


LABOUR DEPLOYMENT OF DIFFERENT ACTIVITIES

Total No. of

FORMAN

RIGGER

FITTER
Labour
SL NO

Helper
Descripion of Activities REMARKS

Material sarching & shifting 3 1 0 2


1

Material assembly 12 0 6 2 4
2

Primary Erection 8 1 5 1 1
3

Secondary Erection 15 1 12 1 1
4

TOTAL MANPOWER 38 2 24 4 8

MAN POWER AND EQUIPMENT DETAILS EQUIPMENT DETAILS

REMARKS
PLANNED
SL NO

ACTUAL
MANPOWER DETAILS PLANNED ACTUAL Remarks EQUIPMENT

1 1
Sr. Project Manager
2 Torque Wrinch 2
Project Manager - 1 -

3 WATER TANKER 0
Engineer's - 1 -
4 Safety Officer - 1 Hydra - 4
5 Supervisor - 2
6 FOUR MAN - 2
7 RIGGER - 24
8 FITTER - 4
9 Helper/Unskilled - 8
12 Eqpt Operator - 5

TOTAL 49
PATNA BLOCK-C PLAN VS ACTUAL (PEB)
Date- 20-Jan

Base Line Start date

Base Line End date

Till Date Complete


Balance Quantity

This week achive


Complete Up To

15-Jan

16-Jan

17-Jan

18-Jan

19-Jan

20-Jan
Total Quantity

previous week

Till Date % of
Weekly

REMARKS
Achivment
persentage
Cumulative

Unit
Construction Activities

Achive
Plan
P A P A P A P A P A P A

PEB Activities

Material Fabrication/ Inspection at Factory Ton 1700 950 11/27/2023 2/15/2024 750.00 750 44%

Receipt of Materials at site Ton 1700.00 1028.110 12/7/2023 3/26/2024 671.89 671.890 40%

Main frame Erection with Mezznine 0 12/10/2023 3/9/2024 0.00

Column Erection nos 290 178 12/10/2023 3/6/2024 77.00 3 1 2 3 8 2 15 3 5 2 6 15 35 233% 112 39%

Jack beam Erection nos 84 54 12/15/2023 3/7/2024 29.00 1 0 1 1 1 2 2 1 8 1 13% 30 36%

Mezzanine Beam Erection nos 123 87 12/15/2023 3/7/2024 14.00 1 1 8 1 13 2 22 1100% 36 29%

Joist Erection nos 396 391 12/20/2023 3/7/2024 0.00 2 3 0 5 5 1%

Rafter nos 210 140 12/25/2023 3/9/2024 64.00 2 4 3 2 2 3 3 3 16 6 38% 70 33%

Canopy Rafter nos 71 38 0.00 8 24 8 8 8 0 8 1 32 33 103% 33 46%

Clit nos 1134 856 12/29/2023 2/8/2024 251.00 7 20 0 27 278 25%

"Z" Purlin nos 4717 3329 12/29/2023 3/28/2024 1054.00 30 19 30 41 40 68 40 20 50 111 80 75 270 334 124% 1388 29%

"C" Purling nos 282 282 1/15/2024 3/20/2024 0.00 0 0 0 0%

Bracing Road nos 408 408 1/5/2024 3/20/2024 0.00 0 0 0 0%

Sag Road nos 12467 12105 1/10/2024 3/28/2024 68.00 30 18 30 15 30 70 30 56 30 58 40 77 190 294 155% 362 3%

Flange Bracing (F.B.C) nos 8660 7980 12/25/2023 3/28/2024 421.00 40 62 40 84 40 38 40 54 40 1 40 20 240 259 108% 680 8%

Strut Pipe (STP) nos 20 20 1/1/2024 3/28/2024 0.00 0

Monitor erection 1/15/2024 3/28/2024 0.00 0

Roof Insulation sqf 1/25/2024 3/30/2024 0.00 0

SSR Sheet profiling Ton 0 1/20/2024 3/10/2024 0.00 0

SSR Sheet Profiling Machine Preparation 0 1/20/2024 1/30/2024 0.00 0

Roofing/ Sheeting work Erection Sqft 0 2/7/2024 4/12/2024 0.00 0

Cladding Insulation 0 2/17/2024 4/10/2024 0.00 0

Cladding work Errection Sqft 0 2/22/2024 4/15/2024 0.00 0

Canopy Sqft 0 2/29/2024 4/15/2024 0.00 0

Mezz Structure Sqft 0 1/24/2024 3/9/2024 0.00 0

Deck Sheeting Ton 0 2/28/2024 3/14/2024 0.00 0

Downtake pipe / Gutters & Finishing Rm 0 2/23/2024 4/23/2024 0.00 0


3/17/2024

194

64
LABOUR DEPLOYMENT OF DIFFERENT ACTIVITIES

Total No. of

FORMAN

RIGGER

FITTER
SL NO

Labour

Helper
Descripion of Activities REMARKS

Material sarching & shifting 6 1 0 5


1

Material assembly 12 0 6 2 4
2

Primary Erection 8 1 5 1 1
3

Secondary Erection 19 1 16 1 1
4

TOTAL MANPOWER 45 2 28 4 11

MAN POWER AND EQUIPMENT DETAILS EQUIPMENT DETAILS

REMARKS
PLANNED
SL NO

ACTUAL
MANPOWER DETAILS PLANNED ACTUAL Remarks EQUIPMENT

1 1
Sr. Project Manager
2 Torque Wrinch 2
Project Manager - 1 -

3 WATER TANKER 1
Engineer's - 1 -

4 Hydra
Safety Officer - 1 - 4
5
Supervisor - 2
6
FOUR MAN - 2
7
RIGGER - 28
8
FITTER - 4
9
Helper/Unskilled - 11
12
Eqpt Operator - 5

TOTAL 56
PATNA BLOCK-C PLAN VS ACTUAL (PEB)
Date- 13-Jan

This week achive persentage

Till Date % of Achivment


Complete Up To previous

Cumulative
Weekly
10-Jan

11-Jan

12-Jan

13-Jan
Base Line Start date

Base Line End date

8-Jan

9-Jan

Till Date Complete


Balance Quantity
Total Quantity

Balance Days

REMARKS
week
Unit
Construction Activities

Achive
Plan
P A P A P A P A P A P A

PEB Activities

Material Fabrication/ Inspection at Factory Ton 1700 950 11/27/2023 2/15/2024 -31 750.00 750
0 0 44%

Receipt of Materials at site Ton 1700.00 1028.110 12/7/2023 3/26/2024 9 671.89 671.890
0 0 40%

Column Erection nos 290 12/10/2023 3/6/2024 -11 65.00 3 1 2 1 3 2 2 1 3 5 2 2 80% 77


213 15 12 27%

Jack beam Erection nos 84 12/15/2023 3/7/2024 -10 20.00 1 1 1 1 2 1 1 2 2 2 3 113% 29


55 8 9 35%

Mezzanine Beam Erection nos 123 12/15/2023 3/7/2024 -10 12.00 1 1 1 1 100% 14
109 2 2 11%

Rafter nos 210 146 12/25/2023 3/9/2024 -8 48.00 2 2 3 4 2 2 3 3 3 1 3 4 100% 64


16 16 30%

Clit nos 1134 12/29/2023 2/8/2024 -38 239.00 12 251


883 0 12 22%

"Z" Purlin nos 4717 12/29/2023 3/28/2024 11 791.00 30 67 30 70 40 70 40 50 80 56 97% 1054


3663 270 263 22%

"C" Purlin nos 282 1/15/2024 3/20/2024 65 0.00 0


282

Bracing Road nos 408 408 1/5/2024 3/20/2024 75 0.00 0

Sag Road nos 12467 12399 1/10/2024 3/28/2024 78 0.00 70 70 68 49% 68


140 68 1%

Flange Bracing (F.B.C) nos 8660 12/25/2023 3/28/2024 11 196.00 40 46 40 67 40 40 20 50 92 107% 421
8239 210 225 5%

Strut Pipe (STP) nos 20 1/1/2024 3/28/2024 87 0.00 0


20

Monitor erection 1/15/2024 3/28/2024 73 0.00 0

Roof Insulation sqf 1/25/2024 3/30/2024 65 0.00 0

SSR Sheet profiling Ton 1/20/2024 3/10/2024 50 0.00 0


0

SSR Sheet Profiling Machine Preparation 1/20/2024 1/30/2024 10 0.00 0


0

Roofing/ Sheeting work Erection Sqft 2/7/2024 4/12/2024 65 0.00 0


0

Cladding Insulation 2/17/2024 4/10/2024 53 0.00 0


0

Cladding work Errection Sqft 2/22/2024 4/15/2024 53 0.00 0


0

Canopy Sqft 2/29/2024 4/15/2024 46 0.00 0


0

Mezz Structure Sqft 1/24/2024 3/9/2024 45 0.00 0


0

Deck Sheeting Ton 2/28/2024 3/14/2024 15 0.00 0


0

Downtake pipe / Gutters & Finishing Rm 2/23/2024 4/23/2024 60 0.00 0


0
194

64
LABOUR DEPLOYMENT OF DIFFERENT ACTIVITIES

Total No. of

FORMAN

RIGGER

FITTER
SL NO

Labour

Helper
Descripion of REMARKS
Activities

Material
sarching & 6 1 0 5
shifting
1

Material 12 0 6 2 4
assembly
2

Primary Erection 8 1 4 1 2

Secondary Erecti 12 1 9 1 1

TOTAL MANPOW 38 2 20 4 12

MAN POWER AND EQUIPMENT DETAILS EQUIPMENT DETAILS


SL NO

MANPOWER DETAIL PLANNED ACTUAL Remarks


EQUIPMENT PLANNED ACTUAL REMARKS
1 1
Sr. Project Manager

2 Torque Wrinch 2
Project Manager - 1 -

3 WATER TANKER 1
Engineer's - 1 -

4 Hydra
Safety Officer - 1 - 4
5
Supervisor - 2
6
FOUR MAN - 2
7
RIGGER - 20
8
FITTER - 4
9
Helper/Unskilled - 12
12
Eqpt Operator - 5

TOTAL 49
PATNA BLOCK-C PLAN VS ACTUAL (PEB)
Date- 6-Jan

Till Date % of Achivment


Complete Up To previous

Cumulative
Weekly
Base Line Start date

Base Line End date

Till Date Complete


1-Jan

2-Jan

3-Jan

4-Jan

5-Jan

6-Jan

This week achive


Balance Quantity
Total Quantity

Balance Days

REMARKS
persentage
week
Unit
Construction Activities

Achive
Plan
P A P A P A P A P A P A

PEB Activities

Material Fabrication/ Inspection at Factory Ton 1700 892 11/27/2023 2/15/2024 -31 808.00 808
0 0 48%

Receipt of Materials at site Ton 1700.00 1076.130 12/7/2023 3/26/2024 9 607.640 18 16.23 623.870
18 16 37%

Column Erection nos 290 12/10/2023 3/6/2024 -11 59 2 2 1 1 1 1 1 4 86% 65


225 7 6 22%

Jack beam Erection nos 84 12/15/2023 3/7/2024 -10 14 1 1 1 1 1 1 2 4 100% 20


64 6 6 24%

Mezzanine Beam Erection nos 123 12/15/2023 3/7/2024 -10 12 2 0% 12


111 2 0 10%

Joist Erection nos 12/20/2023 3/7/2024 -10 0 0


0 0
Rafter nos 210 162 12/25/2023 3/9/2024 -8 38 2 2 3 2 3 2 2 2 4 83% 48
12 10 23%

Clit nos 1134 12/29/2023 2/8/2024 -38 239 7 7 0% 239


895 14 0 21%

"Z" Purling nos 4717 12/29/2023 3/28/2024 11 530 20 30 20 25 20 61 20 41 20 104 261% 791
3926 100 261 17%

"C" Purling nos 282 1/15/2024 3/20/2024 65 0 0


282

Bracing Road nos 408 408 1/5/2024 3/20/2024 75 0 0

Sag Road nos 12467 12467 1/10/2024 3/28/2024 78 0 0

Flange Bracing (F.B.C) nos 8660 12/25/2023 3/28/2024 11 172 20 14 20 20 10 20 20 24% 196
8464 100 24 2%

Strut Pipe (STP) nos 20 1/1/2024 3/28/2024 87 0 0


20

Monitor erection 1/15/2024 3/28/2024 73 0 0

Roof Insulation sqf 1/25/2024 3/30/2024 65 0 0

SSR Sheet profiling Ton 1/20/2024 3/10/2024 50 0 0


0

SSR Sheet Profiling Machine Preparation 1/20/2024 1/30/2024 10 0 0


0

Roofing/ Sheeting work Erection Sqft 2/7/2024 4/12/2024 65 0 0


0

Cladding Insulation 2/17/2024 4/10/2024 53 0 0


0

Cladding work Errection Sqft 2/22/2024 4/15/2024 53 0 0


0

Canopy Sqft 2/29/2024 4/15/2024 46 0 0


0

Mezz Structure Sqft 1/24/2024 3/9/2024 45 0 0


0

Deck Sheeting Ton 2/28/2024 3/14/2024 15 0 0


0

Downtake pipe / Gutters & Finishing Rm 2/23/2024 4/23/2024 60 0 0


0
194

64
LABOUR DEPLOYMENT OF DIFFERENT ACTIVITIES

Total No. of

FORMAN

RIGGER

FITTER
Labour
SL NO

Helper
Descripion of Activities REMARKS

Material sarching & 4 1 1 0 2


shifting
1

Material assembly 12 0 6 2 4
2

Primary Erection 8 1 4 2 1
3

Secondary Erection 6 0 6 0 0
4

TOTAL MANPOWER 30 2 17 4 7

MAN POWER AND EQUIPMENT DETAILS EQUIPMENT DETAILS


SL NO

MANPOWER DETAILS PLANNED ACTUAL Remarks ACTUAL REMARKS


PLANNED
EQUIPMENT
1 1
Sr. Project Manager
2
Torque 2
Project Manager - 1 Wrinch -

3
WATER 1
Engineer's - 1 TANKER -

4 Hydra
Safety Officer - 1 - 4

5
Supervisor - 2
6
FOUR MAN - 2
7
RIGGER - 17
8
FITTER - 4
9
Helper/Unskilled - 7
12
Eqpt Operator - 5

TOTAL 41
PATNA BLOCK-C PLAN VS ACTUAL (PEB)
Date-30-12-2023

Till Date % of Achivment


Complete Up To previous

Cumulative
Base Line Start date

Weekly
Base Line End date

25-Dec

26-Dec

27-Dec

28-Dec

29-Dec

30-Dec

Till Date Complete


This week achive
Balance Quantity
Total Quantity

Balance Days

REMARKS
persentage
week
Construction Activities Unit

Achive
Plan
P A P A P A P A P A P A

PEB Activities
Material Fabrication/ Inspection at Factory Ton 1700 892 11/27/2023 2/15/2024 -31 790 18 0 18 808 48%
Receipt of materials at site Ton 1700 1092 12/7/2023 3/26/2024 9 592 16 0 16 608 36%
Column Erection nos 290 231 12/10/2023 2/8/2024 -38 49 5 5 2 5 1 5 1 5 3 5 3 30 10 33% 59 20%
Jack beam Erection nos 78 64 12/15/2023 2/15/2024 -31 7 1 1 1 1 1 1 1 2 1 1 2 6 7 117% 14 18%
Mezzanine beam Erection nos 123 111 12/15/2023 2/15/2024 -31 8 2 2 2 2 2 1 2 3 12 4 33% 12 10%
Joist Erection nos 12/20/2023 2/20/2024 -26 0 0 0 0
Rafter nos 165 127 12/25/2023 3/9/2024 -8 24 2 2 2 2 3 2 3 2 3 2 3 12 14 117% 38 23%
Clit nos 1134 895 12/29/2023 2/8/2024 41 218 22 22 22 22 22 22 21 132 21 16% 239 21%
"Z" Purlin nos 4717 4187 12/29/2023 3/28/2024 90 407 25 30 32 26 48 48 10 96 123 128% 530 11%
"C" Purlin nos 282 282 1/15/2024 3/20/2024 65 0 0
Bracing Road nos 408 408 1/5/2024 3/20/2024 75 0 0
Sag Road nos 12467 12467 1/10/2024 3/28/2024 78 0 0
Flange Bracing (F.B.C) nos 8660 8488 12/25/2023 3/28/2024 11 112 10 50 172 2%
Strut Pipe (STP) nos 20 20 1/1/2024 3/28/2024 87 0 0
Monitor erection 12/27/2023 3/28/2024 92 0 0
Roof Insulation sqf 1/5/2024 3/30/2024 85 0 0
SSR Sheet profiling Ton 0 1/13/2024 3/3/2024 50 0 0
SSR sheet machine instalation 0 1/8/2024 1/13/2024 5 0 0
Roofing/ Sheeting work Erection Sqft 0 2/7/2024 4/12/2024 65 0 0
Cladding Insulation 0 2/17/2024 4/10/2024 53 0 0
Cladding work Errection Sqft 0 2/22/2024 4/15/2024 53 0 0
Canopy Sqft 0 2/29/2024 4/15/2024 46 0 0
Mezz Structure Sqft 0 1/24/2024 3/9/2024 45 0 0
Deck Sheeting Ton 0 2/28/2024 3/14/2024 15 0 0
Downtake pipe / Gutters & Finishing Rm 0 2/23/2024 4/23/2024 60 0 0
194

64
LABOUR DEPLOYMENT OF DIFFERENT ACTIVITIES

Carpen
SL NO

Driller

Helper
Mason
Total No. of

Fitter
Descripion of Activities REMARKS

ter
Labour
1 0 0 0 0 0 0
2 0 0 0 0 0 0
3 0 0 0 0 0 0
4 0 0 0 0 0 0
5 0 0 0 0 0 0
6 0 0 0 0 0 0
0 0 0 0 0 0
7 0 0 0 0 0 0
TOTAL MANPOWER 0 0 0 0 0 0

MAN POWER AND EQUIPMENT DETAILS EQUIPMENT DETAILS


MANPOWER DETAILS PLANNED ACTUAL Remarks
NO
SL

EQUIPMENT PLANNED ACTUAL REMARKS


1 Sr. Project Manager 1
2 Project Manager - 1 Excavator -
3 Engineer's - 1 JCB -
4 Safety Officer - 1 Roller -
5 Supervisor - 1 Grader -
6 FOUR MAN - 1 FORK LIFT -
7 RIGGER - 14 BATCHING PLANT RMC -
8 FITTER - 4 PAVER PLANT -
9 Helper/Unskilled - 8 WATER TANKER - 1
10 Driller - 0 DUMPER -
11 Helper/Unskilled - 0 DG SET -
12 Eqpt Operator - 4 Tractor -
13 Surveyor - Crane (30MT) -
14 Survey helper - TM -
15 FFS -Electrical & Security team - Concrete Pump -
16 Welder - Hydra - 4
17 Painter - Manlifter -
TOTAL 36 Vibrator (ElectricaL) -
Vibrator (petrol ) -
Compactor -
Reinforcement cutting machine ( Chop saw) -

Reinforcement Bending machine -


Ply cutting Machine -
Auto Level SET -
Total Station SET -
PATNA BLOCK-C PLAN VS ACTUAL (PEB)
Date-23-12-2023

Complete Up To previous week

This week achive persentage

Till Date % of Achivment


Cumulative
Weekly
18-Dec

19-Dec

20-Dec

21-Dec

22-Dec

23-Dec
Base Line Start date

Base Line End date

Till Date Complete


Balance Quantity
Total Quantity

Balance Days

REMARKS
Plan / Day
Construction Activities Unit

Achive
Plan
P A P A P A P A P A P A

PEB Activities
Material Fabrication/ Inspection at Factory Ton 1700 910 11/27/2023 2/15/2024 -31 -55 790 0 0 790 46%
Receipt of materials at site Ton 1700 1108 12/7/2023 3/26/2024 9 189 592 0 0 592 35%
Column Erection nos 290 241 12/10/2023 2/8/2024 -38 -6 38 4 4 1 4 3 4 4 4 7 24 11 46% 49 17%
Jack beam Erection nos 78 71 12/15/2023 2/15/2024 -31 -2 4 1 1 0 1 1 1 1 1 1 1 6 3 50% 7 9%
Mezzanine beam Erection nos 123 115 12/15/2023 2/15/2024 -31 -4 8 2 2 2 2 2 2 12 0 0% 8 7%
Joist Erection nos 12/20/2023 2/20/2024 -26 0 0 0 0 0
Rafter nos 165 141 12/25/2023 3/9/2024 -8 -18 12 2 1 2 3 2 2 2 2 2 2 2 2 12 12 100% 24 15%
Clit nos 1134 916 12/29/2023 2/8/2024 41 22 156 10 28 24 0 62 #DIV/0! 218 19%
"Z" Purlin nos 4717 4310 12/29/2023 3/28/2024 90 48 260 24 23 23 25 23 29 0 147 #DIV/0! 407 9%
"C" Purlin nos 282 282 1/15/2024 3/20/2024 65 4 0 0
Bracing Road nos 408 408 1/5/2024 3/20/2024 75 5 0 0
Sag Road nos 12467 12467 1/10/2024 3/28/2024 78 160 0 0
Flange Bracing (F.B.C) nos 8660 8548 12/25/2023 3/28/2024 94 91 112 #DIV/0! 112 1%
Strut Pipe (STP) nos 20 20 1/1/2024 3/28/2024 87 0 0 0
Monitor erection 12/27/2023 3/28/2024 92 0 0
Roof Insulation sqf 1/5/2024 3/30/2024 85 0 0
SSR Sheet profiling Ton 0 1/13/2024 3/3/2024 50 0 0
SSR sheet machine instalation 0 1/8/2024 1/13/2024 5 0 0
Roofing/ Sheeting work Erection Sqft 0 2/7/2024 4/12/2024 65 0 0
Cladding Insulation 0 2/17/2024 4/10/2024 53 0 0
Cladding work Errection Sqft 0 2/22/2024 4/15/2024 53 0 0
Canopy Sqft 0 2/29/2024 4/15/2024 46 0 0
Mezz Structure Sqft 0 1/24/2024 3/9/2024 45 0 0
Deck Sheeting Ton 0 2/28/2024 3/14/2024 15 0 0
Downtake pipe / Gutters & Finishing Rm 0 2/23/2024 4/23/2024 60 0 0
194

64
LABOUR DEPLOYMENT OF DIFFERENT ACTIVITIES

Carpen
SL NO

Driller

Helper
Mason
Total No. of

Fitter
Descripion of Activities REMARKS

ter
Labour
1 0 0 0 0 0 0
2 0 0 0 0 0 0
3 0 0 0 0 0 0
4 0 0 0 0 0 0
5 0 0 0 0 0 0
6 0 0 0 0 0 0
0 0 0 0 0 0
7 0 0 0 0 0 0
TOTAL MANPOWER 0 0 0 0 0 0

MAN POWER AND EQUIPMENT DETAILS EQUIPMENT DETAILS


MANPOWER DETAILS PLANNED ACTUAL Remarks
NO
SL

EQUIPMENT PLANNED ACTUAL REMARKS


1 Sr. Project Manager 1
2 Project Manager - 1 Excavator -
3 Engineer's - 1 JCB -
4 Safety Officer - 1 Roller -
5 Supervisor - 1 Grader -
6 FOUR MAN - 1 FORK LIFT -
7 RIGGER - 14 BATCHING PLANT RMC -
8 FITTER - 4 PAVER PLANT -
9 Helper/Unskilled - 6 WATER TANKER - 1
10 Driller - 0 DUMPER -
11 Helper/Unskilled - 0 DG SET -
12 Eqpt Operator - 2 Tractor -
13 Surveyor - Crane (30MT) -
14 Survey helper - TM -
15 FFS -Electrical & Security team - Concrete Pump -
16 Welder - Hydra - 3
17 Painter - Manlifter -
TOTAL 32 Vibrator (ElectricaL) -
Vibrator (petrol ) -
Compactor -
Reinforcement cutting machine ( Chop saw) -

Reinforcement Bending machine -


Ply cutting Machine -
Auto Level SET -
Total Station SET -
PATNA BLOCK-C PLAN VS ACTUAL (PEB)
Date-16-12-2023

Till Date % of Achivment


Cumulative
Base Line Start date

Weekly
Base Line End date

15-Dec

16-Dec

Till Date Complete


This week achive
Balance Quantity
Total Quantity

Balance Days

REMARKS
persentage
Plan / Day
Construction Activities Unit

Achive
Plan
P A P A

PEB Activities
Material Fabrication/ Inspection at Factory Ton 1700 910 11/27/2023 2/15/2024 80 21 21 40 21 42 40 95% 790 46%
Receipt of materials at site Ton 1700 1108 12/7/2023 3/26/2024 110 15 30 29.64 30 29.64 99% 592 35%
Column Erection nos 290 252 12/10/2023 2/8/2024 60 4 4 4 4 8 4 50% 38 13%
Jack beam Erection nos 78 74 12/15/2023 2/15/2024 62 1 1 0 1 2 2 2 100% 4 5%
Mezzanine beam Erection nos 123 115 12/15/2023 2/15/2024 62 2 2 2 4 0 0% 8 7%
Joist Erection nos 12/20/2023 2/20/2024 62 0
Rafter nos 165 153 12/25/2023 3/9/2024 75 2 2 2 4 4 4 100% 12 7%
Clit nos 1134 978 12/29/2023 2/8/2024 41 24 25 38 25 38 152% 156 14%
"Z" Purlin nos 4717 4457 12/29/2023 3/28/2024 90 50 50 20 33 50 53 106% 260 6%
"C" Purlin nos 282 282 1/15/2024 3/20/2024 65 4
Bracing Road nos 408 408 1/5/2024 3/20/2024 75 5
Sag Road nos 12467 12467 1/10/2024 3/28/2024 78 160
Flange Bracing (F.B.C) nos 8660 8548 12/25/2023 3/28/2024 94 91 91 16 91 16 18% 112 1%
Strut Pipe (STP) nos 20 20 1/1/2024 3/28/2024 87 0
Monitor erection 12/27/2023 3/28/2024 92
Roof Insulation sqf 1/5/2024 3/30/2024 85
SSR Sheet profiling Ton 0 1/13/2024 3/3/2024 50
SSR sheet machine instalation 0 1/8/2024 1/13/2024 5
Roofing/ Sheeting work Erection Sqft 0 2/7/2024 4/12/2024 65
Cladding Insulation 0 2/17/2024 4/10/2024 53
Cladding work Errection Sqft 0 2/22/2024 4/15/2024 53
Canopy Sqft 0 2/29/2024 4/15/2024 46
Mezz Structure Sqft 0 1/24/2024 3/9/2024 45
Deck Sheeting Ton 0 2/28/2024 3/14/2024 15
Downtake pipe / Gutters & Finishing Rm 0 2/23/2024 4/23/2024 60
LABOUR DEPLOYMENT OF DIFFERENT ACTIVITIES
Carpenter
SL NO

Driller

Helper
Mason

Total No. of
Fitter
Descripion of Activities REMARKS
Labour

1 0 0 0 0 0 0
2 0 0 0 0 0 0
3 0 0 0 0 0 0
4 0 0 0 0 0 0
5 0 0 0 0 0 0
6 0 0 0 0 0 0
0 0 0 0 0 0
7 0 0 0 0 0 0
TOTAL MANPOWER 0 0 0 0 0 0
MAN POWER AND EQUIPMENT DETAILS EQUIPMENT DETAILS

SL NO
MANPOWER DETAILS PLANNED ACTUAL Remarks
EQUIPMENT PLANNED ACTUAL REMARKS

1 Sr. Project Manager 1


2 Project Manager - 1 Excavator -
3 Engineer's - 1 JCB -
4 Safety Officer - 1 Roller -
5 Supervisor - 1 Grader -
6 FOUR MAN - 1 FORK LIFT -
7 RIGGER - 14 BATCHING PLANT RMC -
8 FITTER - 4 PAVER PLANT -
9 Helper/Unskilled - 6 WATER TANKER - 1
10 Driller - 0 DUMPER -
11 Helper/Unskilled - 0 DG SET -
12 Eqpt Operator - 2 Tractor -
13 Surveyor - Crane (30MT) -
14 Survey helper - TM -
15 FFS -Electrical & Security team - Concrete Pump -
16 Welder - Hydra - 3
17 Painter - Manlifter -
TOTAL 32 Vibrator (ElectricaL) -
Vibrator (petrol ) -
Compactor -
Reinforcement cutting machine ( Chop saw) -

Reinforcement Bending machine -


Ply cutting Machine -
Auto Level SET -
Total Station SET -