You are on page 1of 2

health, safety and environment 3

Lifting the lid on process risk


Jeremy Codd shares an insurance view of when things go wrong
THE insurance industry has the PHA actions
unfortunate perspective of seeing
Date Project stage Outstanding
things go wrong with costly regularity. Completed
Software Hardware
However with this experience comes
a keenness to share lessons learned, Jan 07 Detailed design 0 30 50
often long before legislation demands Mar 07 Procurement 15 30 35
the required improvements. It can be May 07 Construction end of phase 1 25 25 30
frustrating for insurance engineers fresh
from a chemical site that has suffered Jul 07 Construction end of phase 2 30 25 25
a loss (and installed measures to try Sep 07 Pre-start up review 45 20 15
to prevent it ever happening again) Sep 07 Construction end of phase 3 55 20 5
then to visit a site that fails to even
Oct 07 Precommissioning 56 20 4
recognise the same issue.
Oct 07 Start of commissioning 67 10 3
a quantifiable risk
In the UK, hazardous installations Notes on PHA actions (or recommendations):

or facilities must demonstrate to the – Accepted as complete only if signed off by PHA lead or chair.
– Software actions apply to those dealing with procedural or management issues and may ordinarily not be
Health & Safety Executive (HSE) that completed after construction.
they have made the risk to people as – Hardware actions are those requiring actual physical measures affecting the design.
low as reasonably practicable (ALARP).
ALARP is defined by levels of individual Figure 2: Addressing PHA recommendations over the course of a project
fatality risk. For members of the public,
designed safety cause managers to accept cheaper, possibly
the Hazardous Installations Directorate
Chemical plants are built by multi- less robust solutions. It is good practice
(HID) gives the corresponding fatality
disciplined teams of engineers but the for the PHA leader or chair to sign off
risk levels as 10–4 to 10–6 per year (see
initial designs are usually drawn up by recommendations once solutions have been
Figure 1).
chemical engineers and it is at this stage satisfactorily implemented. Actual detail of
Since the 1974 Flixborough disaster, PHA recommendations – especially the ones
particular emphasis has been placed on the design’s safety is scrutinised by a
PHA. The chemical engineers are invited, that took a long time to sign off – would
safe design. Most facilities now built to further help insurance risk engineers.
process hazardous chemicals undergo along with peers from other disciplines,
to present the design for hazard Figure 2 shows typical progress in
detailed risk assessments and seek ways
analysis. Through line-by-line analysis, addressing PHA recommendations over the
to reduce the likelihood of catastrophe.
the PHA team is able to pinpoint areas course of a project. The table illustrates
Various process hazard analysis (PHA)
that need attention in order to reduce how satisfactory hardware recommendations
methods can be used, the most common
the level of risk to an acceptable level. are implemented throughout the project
of which is the hazard and operability,
In an ideal world it would be possible life. Interestingly from this example
or Hazop, study. The analysis is usually
to design a plant safe enough for the last few were not completed during
led by a simple series of questions
construction and are likely to have
that define how and where things children to play on – but the real world
needed rework or justification for non-
can go wrong through a consensus of requires affordable practical solutions. A
implementation.
experienced opinion. By defining the PHA study will recommend improvements
hazards and quantifying the risks they to a design, which can be expensive. It revisiting safety
present, process plants can calculate the can happen that PHA recommendations Similarly, with operational plant it is
probability of a fatal incident. are rationalised. possible to measure a site’s commitment
Insurance engineers spend much time Armed with detailed PHA information, to the integrity of a design ratified by a
analysing sites in order to quantify the surveying insurance risk engineers could PHA. A site’s credence to the PHA process
level of risk they pose. The quality of determine which elements of a process is a reflection of its safety culture. The UK
these assessments improves with the plant they wish to investigate before compliance guidelines and enforcement
level of detail gathered by the surveying they even arrive at a site. However, procedures for process safety management
teams year on year. Incorporating this PHAs tend to be highly confidential and of highly hazardous chemicals (CPL 02-02-
information into algorithms is an even inaccessible to non-employees. 045, revised) says that the PHA should be
better way of quantifying the likelihood A site’s commitment to safety can revisited every five years, which requires
Figure 1: of a loss. However, to give reliable be revealed by the respect it gives commitment to comprehensively achieve.
Boundaries of odds requires a lot of detail and quality PHA findings. It is good practice to However, without diligent revisiting of a
acceptable and information. Repeat surveys over several monitor outstanding recommendations PHA, any hazardous installation cannot
unacceptable years are one option; but there is and make sure they are analysed demonstrate continuing risk management,
fatality risk another way. early and implemented. The further a and could even be accused of failing to
project progresses, the more expensive meet its public responsibilities. Every site
Individual fatality risk
it is to perform retrospective design undergoes changes to its design and/or
Acceptable Unacceptable work to implement PHA-recommended operation, and the cumulative effect of
safeguards. Financial pressures can these changes over time can fundamentally
1 in 1 million years 1 in 10,000 years

30 tce april 2008 www.tcetoday.com


health, safety and environment 3

change the plant from the design


Identified Dates Time to implement Cost of
presented to the PHA team. Most sites Recommendations
processes of five- or number of PHA man- implementing
assess the risks posed by individual generated at last
requiring PHA yearly outstanding hours recommendations
changes prior to their introduction, but review
review reviews recommendations GBP
an overall review of the PHA provides a
safety net for the cumulative effect of Distillation –
changes and the opportunity to apply 1997 &
new standards, codes and best practices. Reformer 20 6 months 400 100,000
Aug 04
Figure 3 shows a typical summary of
Blending Due 08
operating plant PHA reviews. It suggests
that the site’s distillation process needs Solvent extraction Feb 04 15 7 months 320 80,000
to be reviewed, and that there might be Ethylene Sep 04 10 5 months 240 100,000
issues with the polymerisation unit. Polymerisation Mar 06 15 3 outstanding 240 50,000
the basis of safety
PHA studies identify and define the At the PHA stage, assumptions have limited number of events that can occur Figure 3: A typical
designed framework within which the to be made such as the properties of in any given set of pipes and vessels. A summary of
hazards must be contained. Consider the the pipework and vessels, an example of PHA seeks to determine these plausible operating plant
following simplified example: a liquefied which might be the strength of a pipe possibilities each of which can be PHA reviews
flammable gas is passed through a under pressure to contain the dangerous evaluated by further quantitative studies
reactor and mixed with other reactants. materials within. An operating plant in order to meet acceptable risk criteria.
Let us say that too much of one reactant cannot sustain this assumption without Statistical summaries of PHA
(Z) leads to a runaway reaction, causing a reliable programme of inspection programmes are easy to produce. If a
over pressure. Engineers install devices and maintenance. Not surprisingly, company is unable to provide them,
to measure and control the flow of inspection and maintenance practices then this could be taken as an indicator
reactants, provide a reaction kill feature heavily in insurance risk of a lack of fundamental risk reduction
chemical to inject if control is lost and engineering surveys. Even when all activities. A good site will be one
install a bursting disc on the reactor hazards of a process plant have been that seeks to revisit and adhere to the
vent that relieves to flare in case of defined and quantified, the plant can guidance offered by the PHA, as doing
overpressure. The events that can lead be compromised at any time by human so will directly influence its prospects
to catastrophe are identified but even error. Extending the analysis of risk down of suffering a loss. Even an older site
multiple protections can only reduce the to individual items of equipment helps that was constructed before the advent
risk of overpressure because no single identify leak-prone points, ie pump seals, of commonplace PHAs may not have
piece of equipment is 100% reliable. pipe joints and pressure relief devices. any original PHA records but can start
Figure 4 shows how a quantifiable These studies can highlight the need for the process of PHAs and achieve the
structure emerges. Instruments, engineered improvements to equipment exemplary standard of a five-yearly
controllers and safety devices all serve integrity or secondary safety initiatives review.
to keep the hazard contained but each such as fire protections and emergency ‘Best practice’ sites usually give
with a probability of failure. If say each scenario responses. inspection and maintenance the priority
element had a 1% chance of failure needed to preserve the design intent.
the best of sites They also keep abreast of industry
then too much Z would have a 1 in 100
Full PHA studies lift the lid on the risks developments and apply lessons learned
chance of going out of control, with a
associated with any given process plant. long before regulatory pressures dictate.
1 in 100 chance of not being able to
Without a demonstrable commitment
kill the reaction, and a further 1 in 100 In conclusion, all site functions
to PHA reviews, a site cannot reliably
chance of not safely relieving the reactor are sustained by the operating plant
control the potential for catastrophe. A
overpressure. Giving a 0.013 = 0.000001 and exemplary management of process
process plant’s PHA performance gives a safety will protect that plant and its
chance of failure, too much Z carries a 1
useful leading indicator of the health of workforce from devastating loss. An
in 1m chance of failure.
its process safety management. Do refer installation that holds the containment
maintaining the design to the Health and Safety Executive’s of its hazards as its utmost priority also
The safeguards installed above are excellent publication HSG254 Developing benefits from a culture of safety that
clearly critical and the loss of any one process safety indicators. percolates throughout its systems of
of them increases the chance of failure It is sometimes said that actuarially work.
by one hundredfold. The duty of care it is not easy to assess a chemical
for these items must be paramount. plant’s likelihood of a loss because of the future?
In order to ensure this level of safety, the relatively small number of sites and This article demonstrates just how useful
the installed protective equipment or incidents, compared to say car accidents. a measure of hazard management PHA
systems should be identified as critical However, each insured major hazard site statistics can be. However this is just
and sufficiently tested and maintained. is responsible for quantifying the level one indicator. With reference again
There are inherent weaknesses in every of risk it poses. A catastrophic incident to the publication HSG254, in time
plant and a workforce unaware of them is at a chemical facility has a measurable chemical sites will be able to present Jeremy Codd
a dangerous combination. chance of occurrence because there are a to visiting insurance engineers a whole (jeremy.codd@
suite of metrics indicating the status zurich.com) is
Figure 4: Containing the risks of of all the risk control systems. A site a senior risk
a runaway reaction with inbuilt health checks of its process engineer with
hazards management will be safer and Zurich Global
more attractive to the insurer. tce Energy

www.tcetoday.com april 2008 tce 31

You might also like