You are on page 1of 6

FINISH TO START ( FTS )

10
16 19 23

FORM AND CAST WALL STRIP WALL

CURE

LT = 3

10-16 16-19 19-23

FORM STRIP
CAST CURE WALL
WALL

6 3 4

SINGLE RELATIONSHIP MODEL

10-16 19-23

FORM LT=3 STRIP


CAST WALL
WALL (J)
(I)

OVERLAPPING MODEL

ESDJ = EFDI + LT

LFDI = LSDJ - LT

9
THE CRITICAL PATH METHOD
HAND-OUT MAGISTER TEKNIK SIPIL
START TO START ( STS )

10 12 18 26

DEMOLISH

FOUNDATIONS

LT=2

10 12 12 18

START CONTINUE
DEMOLISH DEMOLISH

2 6

12 26

FOUNDATIONS

14

SINGLE RELATIONSHIP MODEL

10 18 12 26
LTI=2
DEMOLISH FOUNDATIONS

8 14

OVERLAPPING MODEL

ESDJ = ESDI + LTI

LSDI = LSDJ - LTI

10
THE CRITICAL PATH METHOD
HAND-OUT MAGISTER TEKNIK SIPIL
FINISH TO FINISH (FTF)

10 12 14 17

REPAIR WALLS
LT=3

INSTALL WALL CABINETS

10 14 14 17
REPAIR FINISH
WALLS WALL
CABINETS
4
3

12 14
START
WALL
CABINETS

SINGLE RELATIONSHIP MODEL

10 14 12 17
LT=3 INSTALL
REPAIR
WALLS WALL
CABINETS
4
5

OVERLAPPING MODEL

EFDJ = EFDI + LTJ

LFDI = LFDJ - LTJ

11
THE CRITICAL PATH METHOD
HAND-OUT MAGISTER TEKNIK SIPIL
START TO FINISH ( STF )

21 22 27 29 33

CONTROL WIRING
LT=5

ASSEMBLE & HOOK UP


TRANSFORMER
LT=2

22 27 27 33

START FINISH
CONTROL CONTROL
WIRING WIRING

21 27 27 29

START FINISH
ASSEMB & ASSEMB &
HOOK UP HOOK UP
TRANSFOR TRANSFOR

SINGLE RELATIONSHIP MODEL

21 29
22 33
CONTROL LTI=5 LTJ=2 ASSEMBLE
WIRING & HOOK UP
TRANSFOR

11 8
OVERLAPPING MODEL

EFDJ = ESDI + LTI + LTJ

LSDI = LFDJ - LTI - LTJ


12
THE CRITICAL PATH METHOD
HAND-OUT MAGISTER TEKNIK SIPIL
COMPOUND RELATIONSHIP

10 14 20 26 28

START
PAVING

FINISH
PAVING

START
STRIPING
LT=4

FINISH
STRIPING

LT
DISC.

6 2

14 26
FINISH
PAVING

12
10 14 26 28
START FINISH
PAVING STRIPING
4 2

14 20

START
STRIPING

SINGLE RELATIONSHIP
MODEL
20 FTF 28
10 26 14 STS 22
LT=4
PAVE STRIPE
PARKING PARKING

16 LT=2 8

OVERLAPPING MODEL
13
THE CRITICAL PATH METHOD
HAND-OUT MAGISTER TEKNIK SIPIL
14
THE CRITICAL PATH METHOD
HAND-OUT MAGISTER TEKNIK SIPIL

You might also like