Professional Documents
Culture Documents
Procurement and
Construction (EPC)
Best Practice Guidelines
India edition
India is the fifth largest solar nation globally with over 45 GW of installed solar capacity. This is due to grow
rapidly in following years as the country looks to achieve an ambitious goal of 450 GW of renewable energy
power generation capacity by 2050. Key to India becoming a solar success story will be showing that PV
power plants can provide a reliable, cost-effective, and sustainable alternative to traditional power generation
sources. Putting the best processes in place and getting the fundamentals right during the project design,
engineering, procurement, and construction phases is key to improving the competitiveness and reliability
of solar PV technology.
To address the need for industry-wide best practices for EPC, SolarPower Europe joined forces with NSEFI,
supported by the EU-India Clean Energy and Climate Partnership (CECP), to develop the Indian edition of the
EPC Best Practice Guidelines. A joint Indian-European EPC working group was launched in September 2021,
assembling 31 leading solar experts from India and Europe. The kick-off meeting was followed by a series
of online working meetings, in which we updated the first edition of SolarPower Europe’s EPC Best Practice
Guidelines to reflect the market and business conditions in India. The result is a guide that we hope will help
Indian solar stakeholders improve the quality of the EPC segment. This document is aimed at EPC service
providers, and other parties involved in the construction of solar power plants, such as Asset Owners and
investors, lenders, technical advisors, and other service providers. It will help to establish common standards
and increase transparency in the sector.
In the Indian edition, all the chapters of the original have been thoroughly reviewed and revised with a focus
on the unique aspects of the country. The recommendations have been updated with reference to the Indian
Grid Code, with key detailed requirements therein. The Environment, Health & Safety chapter has been adapted
to include key national legislation on occupational health & safety to ensure that EPC service providers are
aware of their obligations towards their staff. The guidelines give details on where to acquire the relevant
environmental consents for solar PV projects. It also highlights key aspects of the finance architecture in
India, detailing what bonds and bank guarantees EPC service providers need to issue. Similarly, the guidelines
have been adapted to include the relevant Indian standards governing component quality, and more detailed
best practice recommendations on the handover of monitoring software to O&M service providers.
We encourage all solar operators in India to consider these Guidelines and to reach out to NSEFI with any
questions or suggestions.
Vice-Chairs of the SolarPower Lifecycle Quality Workstream: Timo Moeller, NovaSource Power Services; Alden Lee, ABO Wind
Coordinator of the SolarPower Europe Lifecycle Quality Workstream: Benjamin Clarke, SolarPower Europe
Contact: info@solarpowereurope.org
Contributors: Alok Kumar, Renew Power | Ankit Sharma, Efinity Global | Ankur Pathak, Mahindra Susten | Aravinth Rengaraj, Enel | Ayush Shukla, NSEFI
| Benjamin Clarke, SolarPower Europe | Bhupesh Trivedi, Navitas Solar | Brijesh Gupta, AMPL | C.K. Sridhara, TÜV Rheinland | Dan Sokolov, SolarPower
Europe | Edwin Koekkoek, EU Delegation to India | Harry Finnigan, Statkraft | Hiten G. Parekh, SunEdison | Jitendrya Mishra, Enel | Kotha Naresh, Enel
| Kulpreet Guglani, Livguard | K.V. Nachiappan, SwelectK. Sundaravel, Enel | Mohammad Aamir, Enel | Manohar Das, ib vogt | Manoj Gupta, Fortum |
Máté Heisz, SolarPower Europe | Patricio Sanchez, PI Berlin | Praveen Vaishnav, Renew Power | Rajesh Shrivastava, Aditya Birla Group | Rakesh Shah,
Greenko | Ralph Gottschalg, Fraunhofer CSP | R.K. Sharma, Refex Energy | Shally Gupta, NSEFI | Surajit Chanda, Aditya Birla Group | Tusshar Sharma,
NSEFI | Vaibhav Singh, PwC India | Vivek Kodesia, Eden Renewables | Wolfgang Rosenberg, TCO Solar
Supported by: EU-India Clean Energy & Climate Partnership and PwC India
Acknowledgements: SolarPower Europe would like to extend a special thanks to all the working group members that contributed their knowledge and
experience to this report, and to EU-India Clean Energy & Climate Partnership for supporting this project. This would never have been possible without their
continuous support.
Project information: The Indian edition of the EPC Best Practice Guidelines reflects the experience and views of a considerable share of the Indian and
European EPC industry today. It is based on the first edition of SolarPower Europe’s EPC Best Practice Guidelines and has been adjusted to the Indian
context in a joint effort between SolarPower Europe and NSEFI. The development of the Indian edition was supported by the EU-India Clean Energy and
Climate Partnership and their implementing partner PwC India.
Disclaimer: This publication has been produced with the assistance of the European Union. The contents of this publication are the sole responsibility of
the authors (SolarPower Europe and NSEFI) and can in no way be taken to reflect the views of the European Union or the EU Delegation. It is provided to
recipients for general information only. Nothing in it should be interpreted as an offer or recommendation of any products, services or financial products.
This report does not constitute technical, investment, legal, tax or any other advice. Recipients should consult with their own technical, financial, legal,
tax or other advisors as needed. This report is based on sources believed to be accurate. However, SolarPower Europe does not warrant the accuracy
or completeness of any information contained in this report. SolarPower Europe assumes no obligation to update any information contained herein.
SolarPower Europe will not be held liable for any direct or indirect damage incurred by the use of the information provided and will not provide any
indemnities.
Design:
Images: Freepik.com
ISBN: 9789464518627
•C
entral agencies like NTPC Limited, Solar •
Technical Advisors and Engineers: Individuals
Energy Corporation of India Limited (SECI) or teams of experts that provide specialised
services (e.g., detailed information, advice,
• The state Distribution utility, or specific technical consulting). Their role is important as
authorities for renewable energy in a Feed-in they ensure that procedures and practices are
Tariff (FiT) scheme robust enough – according to standards and
best practices – to maintain high performance
•E
xchange, energy traders, or direct sellers in a levels from a PV plant. Technical advisors can
direct marketing scheme represent different stakeholders (e.g., investors
and lenders) but often an independent engineer
•E
nd customers in schemes that support is employed in an attempt to minimise the risk of
autonomy in energy supply bias towards any party
• O&M service provider: The entity responsible for The boundaries between these stakeholders might
the O&M activities as defined in the O&M contract. be blurred depending on the specific risk attitude
In some cases, this role can be subdivided into: and business model of each player. For instance,
certain Owners and investors have reached scale,
• Technical Asset Manager, serving as an allowing them to develop their own in-house Asset
interface between some of the technical O&M Management practice; certain O&M service providers
activities and the Asset Owner. This person is have strengthened their monitoring/performance/
responsible for providing high-level services engineering teams to provide Technical Asset
such as performance reporting to the Asset Management (TAM) services; certain utilities have
Owner, managing contracts, and managing integrated vertically and become EPC service
invoicing and the warranty agreement providers as well as developers, Owners and
operators of their own assets; corporate off-takers
•O
perations service provider is responsible have shown increasing interest in owning and
for the monitoring, supervision, and control managing the operational data of the sites they
of a PV power plant alongside maintenance purchase electricity from.
coordination
•M
aintenance service provider carries out
1.3. How to benefit from this
maintenance
document
• Project Developer: The Project Developer is
These Guidelines include the main considerations for
the entity responsible for project initiation, site
successful and professional EPC service provision.
selection, customer identification, preliminary
Although they have not been tailored to individual
studies, applications for permits, securing
stakeholders, the purpose of the Guidelines is similar
financing and selecting an EPC service provider.
for all: understanding the mandatory requirements
Project developers may own the project in
and the necessity of professional EPC services, as
the early development stages or even longer.
well as incorporating recommendations into service
Their role can sometimes include elements of
packages for more effective EPC services. Any of the
Engineering and Procurement. However, this
directly relevant stakeholders (as described above)
is not the case in SolarPower Europe’s suite of
can benefit from this work, tailor it to their needs
guidelines
without lowering the bar and know what to ask for,
System commissioning closes the construction phase of the solar power plant and begins
the commercial operation period. Commissioning includes performance and reliability
Commissioning
tests to make sure that the solar power plant is built according to international standards,
best industry practice, and complies with the Owner’s requirements and grid specifications.
In the Construction phase, the solar power plant is installed based on installation manuals
provided by suppliers. Construction works involve civil works (mounting structures) and
Construction electro-mechanical works (modules, inverters, etc.) and supervisory and monitoring
equipment. Some parts of the construction may be subcontracted by the EPC service
provider.
An agreement with specific terms between an Asset Owner and a service provider. This
Contractual agreement defines the scope of the services to be provided, the management and interfaces
Framework of those services, and the responsibilities of each party. Liquidated damages and bonus
schemes are also part of the contractual commitments.
Technical and functional specifications for both software and hardware systems used to
Data and monitoring
collect, transmit and store production, performance, and environmental data for power
requirements
plant management.
A DC box (or Generator Connection Box) is used in PV power plants to connect the individual
Direct Current (DC)
solar module strands of a photovoltaic array in parallel, and to connect larger wire cross
box
sections to the inverter.
Decrease in the efficiency of a solar plant with the passage of time. Usually, at least 80%
Degradation of the original output is expected within a 20-year period. Most financial assessments
assume a 0.3-0.5% yearly ageing factor.
Phase in the lifecycle of a project that includes its initiation, site selection, customer
identification, preliminary studies, applications for permits, securing financing and
Development (Project selecting the Engineering, Procurement, and Construction (EPC) service provider. Project
development) developers may own the project in the early development stages or even longer. The term
“Project development” sometimes includes elements of Engineering and Procurement.
However, this is not the case in these guidelines.
A Distribution Station is the final stage in the delivery of electric power. Distribution
Distribution station substations connect to the transmission system and lower the transmission voltage to
medium voltage ranging between 2 kV and 35 kV with the use of transformers.
A management system that records, manages, and stores documents required for O&M
and AM. These include previous and current versions of technical plant and equipment
Documentation documentation and drawings, maintenance manuals, photos, reports, reviews, and
Management System approvals. DMS also define proper document formats and the processes for information
(DMS) exchange. Due to the increasing complexity of documents and to enable advanced
analytics, electronic DMS with the ability to handle meta-tags and searchable, editable
documentation are becoming best practice.
Environment, Health EH&S indicates the policies and guidelines formulated to ensure environmental protection,
& Safety (EH&S) and occupational health and safety at work and on site. It applies to staff and visitors and
is covered in national laws and regulations.
A legal term, often used in contracts, good industry practice is synonymous with best
practice throughout these guidelines. The term refers to practices, methods, techniques,
standards, codes, specifications, acts, skills, and equipment that go beyond the established
minimum acceptable baseline in the international solar power industry (including in the
Good industry
construction and installation of solar power facilities). They are adhered to by high-quality
practice
service providers and are designed to help accomplish the desired result of a decision or
action (or lack thereof), in line with applicable laws and permits. Good industry practices
are reliable and safe, economically efficient, protect the environment and are done with the
degree of skill, diligence and prudence that would ordinarily be expected.
Grid code compliance Equipment, procedures, and actions required by a grid operator to comply with grid safety,
requirements power quality and operating specifications.
An Inverter is a type of electrical converter which converts the variable direct current
(DC) output of a photovoltaic power plant into a utility frequency alternating current (AC).
Inverter
Afterwards it feeds into a commercial electrical grid or is used by a local, off-grid electrical
network.
The solar radiation incident on a solar panel over time, relative to its area. It is usually
Irradiation expressed in watt-hours per m². It plays an important role in the determination of the
optimal inclination angle of PV modules and the profitability of a PV system.
The smallest environmentally protected, essentially planar assembly of solar cells and
Module ancillary parts, such as interconnections, terminals (and protective devices such as diodes)
intended to generate direct current power under unconcentrated sunlight.
The digital platform used for the overall management of PV plants or a PV plant portfolio. It
allows for centralised monitoring of the functioning, energy generation and reference data
of a PV plant and its components. Ideally, this would be performed through a real-time
Monitoring System
monitoring module that retrieved data from local Supervisory Control & Data Acquisition
(SCADA) systems. It also includes operational modules such as ticket dispatching,
analytics, and reporting. The centralised monitoring module receives data for 24 hours a
day, all year from in-plant SCADA systems, purpose-built sensors for measuring irradiation
and temperature and other sources such as meteorological information.
Structures used to fix solar panels to surfaces like rooves, building facades, or the ground.
In the case of utility-scale solar PV plants, there are three main ways of securing mounting
structures:
O&M includes all the services that ensure maximum efficiency and the smooth running
Operation and
of a PV plant. The services include monitoring and supervision, predictive, preventive,
Maintenance (O&M)
and corrective maintenance, performance analysis and improvement, power generation
forecasting, and site security management.
Operators, technicians, engineers, and managers employed for the execution of the O&M
Personnel & training activities and training plans/programmes to train them on relevant PV plant related aspects
and to keep them continuously updated on their respective roles.
The Procurement phase covers the selection and purchase of components such as PV
modules and inverters, and the identification and mitigation of risks through suitable
Procurement
inspection, testing and qualification mechanisms. It also involves supplier onboarding, and
inspections and tests until the end of the procurement process.
Quality Management is the process through which an organisation ensures Quality. Its four
Quality Management
pillars are Quality Control & Assurance, Quality Review, Quality Improvement and Quality
(QM)
Planning.
The effect of uncertainty on objectives. The major categories of PV risk include, but are not
Risk limited to, financial risks, country and regulatory risks, contractual risks, commercial risks,
technical risks, and reputational risk.
The practice of identifying and analysing the risks to which solar power systems and
Risk management operations are vulnerable and taking steps to mitigate them. The different risk management
methods are risk avoidance, risk reduction, risk control, risk transfer. A risk that cannot be
mitigated is called residual risk.
A company with its own rights, assets, and liabilities, created for building, owning, and
Special Purpose
operating one or more solar power plants. An SPV can also be referred to as an SPE (special
Vehicle (SPV)
purpose entity) or as a project company.
Substations transform voltage from high to low or the reverse. A substation is a part of
an electrical generation, transmission, and distribution system. A substation may include
Substation
transformers to change voltage levels between high transmission voltages and lower
distribution voltages or at the interconnection of two different transmission voltages.
A turnkey EPC contract is a contract in which the EPC service provider delivers the entire
solar power plant to the investor so that construction and commissioning are completed,
Turnkey EPC contract
and the solar power plant is ready, available to operate and feed generated electricity into
a grid distribution system.
Documentation
Product lifetime
Quality Quality Review: Quality Quality Quality Control Quality Control Quality Control Quality Control
Planning Audit Improvement Review:
Monitoring
From Site Selection, Engineering, Procurement, ensure the availability of local technical support,
Delivery, Construction, Operation and even the the interoperability of different parts, and should
End-of-Life Phase, QM must pervade the project optimise the power plant’s design within the legal
management approach. Moreover, QM actions framework and local technical requirements.
should always be flanked by good documentation.
In the Engineering Phase a PV project is planned
Quality Planning is particularly important during the and designed. The focus here should be on selecting
Engineering Phase. The planning process should the proper components in the design based on
Risk analysis
Risk taking
& cover
Measurement
Risk identification & reporting
Strategic • Operational • Project
Risk
Risk transfer avoidance Risk reporting
Insurance, SPV,
Contract
Risk measurement
Impact • Likelihood Risk
mitigation
Control
and process
Risk evaluation improvement
Controls: Quality, Financial, System
Risk management
A project’s equity can be significantly compromised Country risk refers to the risk of investing or lending
if a PV power plant does not perform. This is because, in a country. For example, financial factors such as
across a project’s lifetime, the development and currency controls, devaluation or regulatory changes,
the EPC phases carry the highest risk. Financial or stability factors such as mass riots, civil war and
risk involves market modelling, credit, liquidity, other potential events contribute to companies’
operational and other risks (e.g., reputational, operational risks. This term is also sometimes
legal, IT, to name a few). In many projects, the referred to as political risk. A differentiated country
financial modelling already poses an inherent risk, risk classification is offered by various institutions
particularly when optimistic assumptions are taken, e. g. OECD, S&P, Moody’s, Fitch, World Bank, and
and insufficient sensitivity scenarios, without other institutions.
critical influencing factors, are used. For the EPC
part of a financial risk assessment, it is important to In India, SECI is a major off taker for power from solar
have an understanding of (however, not limited to) PV projects (occasionally other state intermediaries
the following risks: market risks (particularly price with higher credit ratings will be involved). SECI and
and currency fluctuations from time of engineering/ these intermediary agencies provide much-needed
design through Commercial Operation Date (COD) support in reducing the financial risks, especially
and cash related transaction risks, for example, how if projects are developed under the Build-Own-
a pre-payment can effectively be secured against Operate format. Similarly, as India is a politically
future deliveries. Examples of risk mitigation stable country, many of the challenges above do
measures include performance bonds backed by not occur or are often quickly resolved to safeguard
internationally accepted financial institutions and relationships with investors.
escrow accounts. Another important aspect of
financial risk analysis relates to solvency of the However, there are some regulatory risks involved,
parties involved in the project and their individual particularly around which technical standards
business habits. Especially when it comes to a projects are meant to follow. Service providers
first-time interaction with a new business partner, seeking connection to the grid, must make sure they
business habits, including their value set, can have are aware of which technical standards apply in the
a significant impact on the financial stability of a state they are operating in, particularly as these can
project. There are several background checks that vary between states. Solar PV projects are required
can help reveal the reliability of a new partner, such to meet grid standards for voltage imbalance &
as references and financial health (credit) checks. fluctuation, metering, harmonic and DC injection
and flicker, DC side overloading to receive optimal
One important point of consideration for financial output, etc.
risks is bankability. It is important to note that
different banks have different standards of Any changes to technical standards, equipment
assessing a project and its underlying risk. Two used, updates to codes of practice for safety,
factors are vital from an EPC perspective: Firstly, it is substation grounding, insulation level and insulation
essential to make sure that your own bank accepts coordination, protection relays, connection schemes,
any bonds issued by banks of your business partner. or the introduction of new technologies after the
Secondly, it is important to understand the technical EPC contract has been signed all pose significant
requirements of the lending bank (often only for the risks. This makes it imperative that EPC service
long term) of the buyer of the PV power plant and to providers and Asset Owners clarify all obligations
adhere to these. and responsibilities in the EPC contract to avoid any
uninvited risk.
• Establish, implement and maintain an effective There are several basic environmental authorisations
integrated EH&S management system including, but not limited to:
• Ensure that intrinsically safe design is achieved In India, decisions on which environmental permits,
by monitoring progress and preparation of final or authorisations/consents must be obtained are
results and systematic review of the design made by the Central Pollution Control Board (CPCB)
process, if necessary and obtained from the local State Pollution Control
Board (SPCB). The CPCB classifies industries into
• Manage risks in the design, procurement, four categories:
construction, installation, commissioning,
operation and maintenance activities i. Red
ii. Orange
• Ensure appropriate levels of skills for all staff iii. Green
engaged in carrying out critical EH&S activities iv. White
and provide training where necessary
As per the “Revised Classification of Industrial
• Check for any potential EH&S impacts in the Sectors under Red, Orange, Green and White
project area and ensure that these are minimised categories”-2017 on Water (Prevention and Control
of Pollution) Act, 1974 and Air (Prevention and
• Ensure that a complete inventory of all waste and Control of Pollution), Act, 1981. The entry at Sr. no.
discharges is maintained and that all waste is 35 under “White category” includes the below:
disposed of in an environmentally and regulatory
acceptable way
Based on the latest available (2019) figures reported On this basis, we identify certain future R&D
on the growth of solar PV installations, we can pathways and challenges to be addressed, to
estimate that about 1-1.2 million solar PV modules support the development, growth, and bankability
are installed every day around the world. With this of second life solar PV and circular solar PV O&M
in mind and with an estimated average annual business:
failure rate of 0.2% in the field, we may anticipate
today ~8 million solar PV modules to fail every year, • Industrialisation and qualification of new solar
corresponding to a weight of 144 kt of potential PV module designs-for-circularity: including
annual solar PV waste from solar PV failures only. “repair-friendly” solar PV components, modular
Adding also other solar PV waste sources and designs, and deployment of repair technology
streams, such as the decommissioning of solar PV solutions in upscaled re-manufacturing lines
modules due to end of service lifetime, repowering,
insurance claims, etc., the cumulative solar PV • Identification and tracking solutions (e.g., RFID)
waste is expected to reach up to 8 Mt by 2030. at solar PV components/modules/system level,
to facilitate reverse logistics, sorting/inventory
Reported field experiences show that, most solar of solar PV and warehouse operations
PV modules with diagnosed/classified failures
that are decommissioned, follow a linear End of • (Automated) detection, diagnostics, and
Life (EoL) management approach: they enter the classification (incl. recommendation) of repair or
waste stream and are either disposed as waste re-use operations in solar PV asset management
(the majority of the time) or recycled. Currently less tools for solar PV plants
than 10% of decommissioned modules are recycled.
However, experts from the IEA PVPS Task 13 and the • Standardisation/technical specifications for on-
CIRCUSOL project estimate that 45%-65% of them, site quality control and sorting, as well as off-site
can be diverted from the disposal/recycling path, design qualification and type approval protocols,
towards repair and second life solar PV (re-use) or, towards solar PV reuse-repurposing-recycling
as aforementioned, revamping.
• Synergies of solar PV Asset Owners and O&M
To ensure the technical-economical bankability service providers, with innovators in supply chain
of solar PV re-use and second life solar PV, within / reverse logistics technologies, also leveraging
the O&M framework and the overall solar PV value AI/machine learning aided logistics, sorting,
chain, it is important to: warehouse operations, inventory management
for circular solar PV economy
Specific Health and Safety Agreement This register records the training, qualifications,
experience, and competencies of your employees
The Site-Specific Health and Safety Agreement is working on a particular site. It must be fully
an agreement between businesses working on a completed before any work starts on the site and
The purpose of training is to develop expertise. Some 6.3. Leadership and Project
personnel may have undertaken proprietary training Management
or education that exceeds training and experience
requirements for certifications. Internal training can, Management provides personnel with the essential
therefore, be used in some cases as a substitute for building blocks to process information that is directly
the certifications. applicable to the tasks they perform. Optimising
decision making within a team and amongst those
There can be national or local requirements for on- in leadership positions requires clear objectives,
site work, including EH&S compliance training and purpose, and the drivers that affect these.
conditions for reporting and investigating incidents.
Licenses can vary, in line with permitting, local Project management tracks deadlines, budgets, and
rules and regulations. For more information on quality, to achieve planned results. Hence the Project
the regulations and permits governing occupation Manager sets goals for individuals and teams and
health & safety and environmental protection, please drives performance management.
refer to chapter 5. Environment, Health & Safety.
Training in Project Management can provide
Formal education and training are important guidance, explain core principles, and give direction
preconditions for expertise. Several fields require on what constitutes good practice. Formal education
• Finally, the project must be handed over to the 7.1.2. Technical quality
EPC service provider without losing important
information. Chapter 7.3. Handover from project One of the overarching engineering KPIs is expected
developer to EPC service provider discusses this performance ratio (PR) / expected yield, which is
critical procedure an input parameter into the business plan. Multiple
7.2. Selection of an
EPC service provider
QR should be > 1, preferably >1.1.
The following criteria (also called “ex-ante KPIs”),
among others, help to assess EPC service providers:
financial stability, expertise, prices, and procurement Solvency is a company’s ability to meet its debt
performance. obligations on an ongoing basis, not just over the
short term. The debt-to-equity ratio (D/E) indicates
the relative proportion of shareholders’ equity and
7.2.1. Financial stability debt used to finance a company’s assets. The lower
the D/E ratio, the more of a company’s operations
Investors need financial security for their are being financed by shareholders who do not
investments. Not all risks can be covered by charge interest, but more importantly, may enable
securities, and consequently, this means that the the company to raise debt capital in case needed. On
selection of an EPC service provider merits care. the flipside, a decreasing D/E indicates increasing
financial solidity of the company.
It is important to get as close as possible to the present-
day financial situation of the company. Credit ratings A good indicator of a company’s operating efficiency
(seen in relation to the Indian market) and audited is reflected by its Return on Sales (ROS, also called
statements from the last 2-3 years typically provide EBIT margin):
the most solid and indisputable financial information.
However, these usually only reflect information that is
at least six months old by the time they are published.
Furthermore, account definitions can vary from country
to country, making comparisons difficult. Where EBIT = Earnings Before Interest
and Tax and its Return on Capital Employed
An alternative to this is a bank guarantee where the (ROCE):
investor moves the evaluation over to a bank partner.
This does not necessarily give a better evaluation
of the financial viability than one’s own evaluation,
but it gives the financial insurance of a bank. This Where CE = Capital Employed =
obviously comes with a cost. The mere demand for a Total assets – Current liabilities
bank guarantee can be prohibitive for some projects
and can eliminate smaller, competent EPC service
providers from participating, even though they are
financially solid for their size.
A good KPI for evaluating a company’s profitability Another sign of expertise is the quality approach
is its Net Profit Margin (NPM): of the EPC service provider. Apart from potential
verifications at the manufacturer’s production
site, non-mandatory quality checks during the
construction phase are recommended (for more
information, see Chapter 9. Procurement). The extent
of checks needs to be adapted to the size of the
A low NPM means a higher risk of the company project.
running into difficulties quickly if operating cost or
competition increases. A larger net margin indicates As part of the expertise, it should be made sure
its higher potential to invest capital into growth (but that the EPC service provider has a proper quality
should be seen in relation to fixed costs). management procedure in place.
Investment decision/
Financial closure
•Y ield assessment
RfP/tender based on solar
pre-qualification resource
• Technical concept • ( P50-P90 values)
design based on •S caled plan of all Construction
custom requirements requirements in RfP •P
rovision
•P lan for feasibility •B OM definition acceptance
study parameters & quantities certificate
However, more detailed versions of the basic As the project advances, the developer will acquire
design concept may be produced to facilitate early more information, provided that the following
development permitting milestones or bidding in studies are performed: site assessment, solar
tender procedures, depending on the concrete case resource analysis, environmental studies, permitting
requirements. requirements and interconnection assessment.
HIGH
PARTNERSHIP MAKE
BUY PARTNERSHIP
LOW
Expected quality
Gap 5
Quite often, ambiguity in contracts leads to on technical, financial, legal, and social regulation
variations in the delivery of a product. This makes and standards should be assessed. This requires
identification of issues and follow-up actions cooperation from suppliers along all these lines.
unnecessarily difficult. The diversity among PV When selecting a supplier, TIER-ratings give an
modules is a pitfall, as some combinations have not overview of the track record of the manufacturer,
been tested or come from different production lines. but only provide limited information on the quality
Furthermore, production in various factories also of a product. Therefore, selecting products just
requires sampling to reflect the source of products on their TIER rating is insufficient. Consequently,
for third-party verification testing. the selection must be based on product testing
accompanied by factory audits and a documentation
The criteria and recommendations in the rest of this review.
chapter should be applied as a minimum to ensure A technical rating of products can be based on
product quality and extended service life at reduced accessible product data and quality assurance
operating costs. information provided by the manufacturer. It can
be used as preselection criteria as a part of an
overall quality review process for PV power plants.
9.2. Management of suppliers The rating or scoring system of suppliers should
start before the sourcing phase. A rating may be
9.2.1 Selection of suppliers based on a questionnaire, which should include the
product-related data as well as quality assurance
Prior to signing a contract with a supplier, the EPC information, including:
service provider should determine the ability of
the supplier to consistently deliver products and • Technical Specifications
services that can meet the requirements in sufficient • Bill of Materials
quantities. Alongside this, suppliers’ performance • Certificates
Visual Inspection S3
EXAMPLE:
Sampling for a 50 MW PV Plant with 400 Wp of each of the 2 BOMs, sampling rate S 3 for
modules and two different BOMs. 62,500 modules comes to the same sampling
Total number of modules: 125,000 rate. Hence 32 modules would be chosen per
BOM.
Performance characterization testing:
G I level would lead to a sample size of 200 Induced degradation and reliability testing:
modules 2 modules per BOM per test would mean 4
modules per chosen test sequence are to be
Qualification testing: selected.
S 1 level would lead to a sample size of 8
modules; considering 1/2 of the modules are of Testing can mostly be organized pre-shipment
each of the 2 BOMs, sampling rate S 1 for 62,500 at a test centre close to production. Sampling
modules comes to the same sampling rate. should always be random or organized by
Hence 8 modules would be chosen per BOM. an independent third party. Post-shipment
testing can make sense, if pre-shipment was
S 3 level would lead to a sample size of 32 not possible, timelines did not allow it, or
modules; considering 1/2 of the modules are transportation damages are to be assessed.
Parameter Specification
Cell/ Module Technology Multi-crystalline or Mono-crystalline
Module Efficiency 17% for Multi-crystalline
19% for Mono-crystalline
Rated power at STC No negative tolerance is allowed
Temperature co-efficient of power Not less than -0.40%/°C
Application Class as per IEC 61730 Class A
In India, modules must be tested in labs accredited by the National Accreditation Board for Testing and
Calibration Laboratories (NABL). Please see below for a list of NABL-accredited labs.
IS Number :- IS 61730 Part: 1 Year: 04 - Photovoltaic Module safety qualification Part-1-Requirements for construction
IS Number :- IS 61730 Part: 2 Year: 04 - Photovoltaic Module safety qualification Part-2-Requirements for testing
The inverter specifications above are required for all frequently than LCD and piezoelectric keypad
tenders in the country. Solar inverter manufacturers operator interface/display)
are obliged to meet tendering requirements, such
as the minimum requirement for an LCD display • LCD displays are outdated across all electronic
on the front panel of inverters. However, to make equipment/appliances as these are being
assessments and monitoring of energy generation remotely monitored and controlled
easier, newer models of solar string inverters
come with LED indicators along with Bluetooth + Further, the inverter supplier should be of adequate
mobile application features for display parameters/ experience as below
information.
• The inverter supplier should have supplied
This feature has been adopted by all major minimum 5 GW capacity globally or 500 MW in
manufacturers and is being adapted in some tenders India in the past 5 years (as on last date of the bid
while manufacturers are also adopting to this submission)
feature in their newer string inverter models due to
the improved user experience and other advantages: • The inverter supplier shall be Class-I local supplier
as per MNRE Order on Public Procurement
• Improved daytime visibility through the mobile (Preference to Make in India) to provide for
application when sunlight in abundance Purchase Preference (linked with local content)
in respect of Renewable Energy (RE) Sector dated
• Able to display a larger number of parameters 9th February 2021 and subsequent amendments
(more than LCD for data display on Inverters)
When planning a system, it is critical to match the
• Safer than LCD displays as they minimize operating characteristics of the inverter (efficiency,
unnecessary exposure to high-voltage electrical load-related derating, voltage window) to the real
equipment operating conditions. As per MNRE the Pass criteria
for Solar Inverters should be as per IS 16169 and
• Less strenuous O&M requirement as they are IS 16221 Part II, wherever applicable. The following
less prone to failures and require replacing less tests are required.
Power conditioning unit: Power Conditioning Unit Sufficient diligence needs to be exercised when it
(PCU) shall comply with IEC 62116 Ed. 2 Utility- comes to:
interconnected photovoltaic inverters – Test. The
specifications are as follows: • Specific requirements for inverters, including
compliance with IEC 61196, IEC 16221, IEC
• The rated/ name plate AC capacity of the PCU 60068-2, and IEC 160000 for India
shall be AC power output of the PCU at 50°C • Performance characterisation testing (INV File
generation for energy yield simulations)
• Maximum power point tracker (MPPT) shall be • Product qualification testing
integrated in the PCU to maximize • Product reliability testing according to
appropriate standards
• Energy drawn from the Solar PV array. The
MPPT voltage window shall be sufficient to
accommodate the output voltage of the PV array 9.5.3. Mounting structure (fixed tilt)
at extreme temperatures on-site
Racking systems hold valuable modules in place and
• The PCU output shall always follow the grid in ensure stability of the installation of the PV system.
terms of voltage and frequency. The operating Mounting components consist of various metal
voltage and frequency range of the PCU shall be parts with different coatings or materials, such as
sufficient to accommodate the permitted grid aluminium, alloy, stainless steel, or galvanised steel.
voltage and frequency variation Corrosion can occur due to the constant and long-
term exposure of these materials to each other, to soil
After erection on-site, transformer(s) are subject to other tests like (i) Measurement of voltage ratio, (ii) Check
of vector group, (iii) Magnetic balance test, (iv) Measurement of insulation resistance, and (v) Breakdown
voltage test on transformer oil.
A proper schedule and preparation of several The site survey aims at checking that there are
activities around the construction are important no physical and geographical constraints or
and should preferably be organised according to inconsistencies with the assumptions and technical
common project management techniques. This details defined in the Execution design (see Chapter
includes clear definition of objectives, activities, 8. Engineering).
and responsibilities (who does what?), time plans
and milestones (when?), cost planning, and quality The survey is also necessary for checking the actual
assurance. To achieve this, an effective and efficient status of the site and for planning the preliminary
communication, documentation and reporting flow activities necessary to prepare the site for the
between the Asset Owner, the EPC service provider mobilisation of personnel and equipment and the
and the subcontractors is necessary. This will help start of the main construction activities.
encourage accountability, potential construction
defects are promptly identified, high standards While the effective mobilisation of the EPC service
upheld, and monitoring the EPC service provider’s provider and their subcontractors usually takes place
performance is easier. once contracts enter into force (in general when a
notice to proceed is issued by the Asset Owner), the
The overall construction activity can be divided into execution of certain early works, sometimes also
two phases: firstly, the preparatory phase, related called preliminary works, is a project strategy that is
to the preliminary activities and secondly, the becoming more frequent.
construction implementation phase, including site
preparation, civil, mechanical, and electrical works With reference to construction activities set-up, the
necessary to complete the plant and bring it to the key topics to be investigated during the site survey are:
production phase.
• Mapping of the construction site (allotment and
boundaries, topography, etc.)
10.1. Construction
• Definition of the area for temporary facilities and
preparatory phase
storage/warehouse
The construction preparatory phase includes those
• Identification and mapping (geolocalisation)
planning and preparatory activities that ensure
of interferences to be considered during
the smooth realisation of the power plant. For this
construction, for which drones can be used
purpose, it is important that the construction project
is correctly set up according to project management
• Assessment of critical elements for construction
principles: the Asset Owner and the EPC service
and identification of mitigating actions (technical
provider define project organisation and objectives,
risks, rests of bombs, hazardous waste, but also
arrange main parts of the project in a work-breakdown
archaeological discoveries)
The identification of the stakeholders and their Construction Planning ensures that all construction
needs and expectations requires suitable knowledge activities are properly planned, scheduled, monitored,
of the relationships that exist between the different and that the right personnel are available (workload
actors that are present and active in a given context. management). This avoids delays resulting from a
For this purpose, all subjects that could influence or lack of resources or materials.
be influenced by the project must be considered.
A key success factor is the definition of a robust
It is important that the identification of the and detailed project plan that will ensure work
stakeholders is not limited to local and administrative is completed successfully and within a project’s
authorities but should also consider people and authorised scope.
organisations that are relevant for local communities,
as they represent their interests and identity. A project’s scope of work is formalised in the
Work Breakdown Structure (WBS) by the project
management team. The WBS represents a common
10.1.3. Construction plan preparation framework for carrying out any other project
management activity. Only the activities or the
The construction plan preparation starts with products identified in the WBS fall inside a project’s
resource planning and the mobilisation plan which scope and therefore can be planned and controlled.
includes the following information and documents:
A well-defined WBS:
• Construction site organisation chart: Document • Provides complete definition of the project
drawn up by all subcontractors (civil and electro- scope at different levels
mechanical) involved in a project which indicates • Allocates tasks and responsibilities
all the expected positions, the staff residence • Defines a numbering system, which is used as
times and the expected hours. reference in project plans, reports, and technical
documentation
• List of site vehicles and equipment: Document • Provides an input to integrate cost and
created by all subcontractors involved in a schedule data
project which lists the vehicles and equipment
a. Standard Penetration Tests: This is carried out in d. Geology of the project site: If field investigations
accordance with IS2131-1981 SPT. The number reveal loamy, red soil this can suggest the
of blows required to drive a 50mm diameter split presence of rocks that also require investigating
spoon sampler to a depth of 30 cm, using a 65Kg
hammer, is recorded as “N” value. The results of e. Laboratory tests: These tests should be
all the penetration tests performed in each of the conducted in accordance with IS-2720
bore holes are shown in their respective bore logs. i. In situ density and water content
The test is halted if, (i) 50 blows are required for ii. Atterberg Limits
any 15cm penetration, (ii) 100 blows are required iii. Grain size analysis
for 30 cm penetration, or (iii) 10 successive blows iv. Shear test
produce no advance. In any of these cases, the
N-value is recorded as a “refusal” At the end of construction, areas impacted by civil
works must be restored to their initial conditions.
b. Electrical Resistivity Tomography (ERT): The
Electrical Resistivity Tomography method is a Water is used to clean PV modules and must be
geophysical technique used in geo-technical selected carefully to ensure excessive mounting
studies. In this method, a known current is sent structure corrosion is avoided. Below are a series of
into the ground through a pair of electrodes viz. tests that can be performed to determine this:
10.2.5. Grid connection The plan should include the following minimum
requirements:
Utility scale PV plants need to be connected to the • Definition of a start-up team
network, usually managed by the Transmission • Definition of the project functional units and
System Operator (TSO). In India, both the state and related sub-units
central networks work in tandem for transmission of • Definition of the plant sections that can be put
electricity across the country. The State Transmission into production in sequence
Utility (STU) and Central Transmission Utilities (CTU) • Definition of the schedule and procedures for
manage the grid with Load Dispatch Centres. STUs carrying out the preparatory tests for the start-up
are often referred to as transmission companies for each functional unit and plant section
Provisional
Owner Final Intermediate Acceptance
Takeover Acceptance Acceptance Testing Certificate
Testing (12 months)
(12 months)
Final Intermediate
Acceptance Acceptance
Certificate Certificate
During the pre-commissioning phase, the following Usually, a detailed checklist covering all
tests should be performed, as a minimum components and parts is used to make sure that
requirement: nothing is missing or incomplete. The works are
thoroughly checked through the following items:
• Mechanical integrity of the modules with visual
inspection and the correct wiring. Thermographic • Inverters
analysis (via drones) can be added at this stage • Modules
as a best practice • Foundations
• Verification of the nominal power of the installed • PV Module Mounting Structures
system carried out as the sum of the nominal • LV and MV Cabling
power at STC of all the installed modules • Transformers
• Verification of the correct operation of all • Protection, distribution centres and switch gear
auxiliary services (fire system, rodent protection, at the substation
forced ventilation of transformers, temperature • Combiner boxes
sensors, UPS systems and related storage • Civil works
systems, lighting systems, etc.) • Low and medium voltage installation works
• Control of all input signals to the SCADA system • Monitoring and security systems
• Verification of all power supplies of the auxiliary
services of the cabins These final checks should also include meter testing. The
• Commissioning of UPS systems and related meter should have one port for downloading metered
storage systems, SCADA system and of weather data through a Common Meter Reading Instrument
stations and environmental sensors (CMRI) and another port for remote communication.
• Verification of IP addresses on all equipment India has specific requirements for meters:
• Setting of all alarm thresholds on the equipment
For more information on Indian grid code • Training of the O&M service provider’s teams
requirements, please refer to section 11.2.1. has been performed and relevant O&M manuals
Commissioning activities. issued
Once the PR criteria and any other requirements To ensure a smooth and efficient handover to
have been met, the PAC is issued. The project operation activities, the Asset Owner should be
reaches the handover phase, which is the start of involved well in advance and participate in the
the operational phase and O&M activities. commissioning phase and performance tests. It
is also a best practice to involve the operations
function of the Asset Owner during the development
11.3.2. Other tests and engineering phase, so that an O&M perspective
can also be taken into consideration.
In some contracts, complementary tests can be
performed at the Provisional Acceptance stage. Comprehensive and detailed as-built documentation
These tests can reflect the requirements of the (see Annex E), manuals and procedures (see Annex C
energy off taker with the Power Purchase Agreement of SolarPower Europe’s O&M Best Practice Guidelines
(PPA), whether or not the system functions, or simply – India edition) should be part of the training
be used as additional quality assurance measures. activities. For more information on the Handover to
a specialised O&M service provider, please refer to
To prove the project’s ability to perform to its Chapter 12. Handover to O&M service provider.
maximum capacity, a Reliability Test can be
The EPC service provider shall provide the following cannot choose counterparts and renegotiate
documents as per the timelines mentioned below. conditions easily. Therefore, the transfer of
A detailed checklist of all the documents to be contracts needs some time; three months is a
submitted by the contractor shall be mutually reasonable period. In some cases, a contract needs
finalised. to be terminated and a new service provider needs
to be found.
In addition to the documentation package described
above it is important to give full visibility to the O&M It is best practice for contracts to include a clause
work done during the warranty period. Therefore, the about this kind of transfer from the beginning. This
following list of information should also be handed over: helps avoid degradation of contract conditions as a
result of the handover. A common inspection with
• Maintenance reports done by the the new contract parties should allow for better
EPC service provider understanding of the current situation and help
• Hourly production data of each define priorities for the coming period.
inverter and meter
• Hourly irradiation values measured on site
• Description of any force majeure event that 12.3. Access to monitoring and
occurred, such as thefts, grid failures or
communication systems
outages, equipment replaced under warranty
• Output of any measurement test conducted
Adequate time for the transfer of Monitoring
and communication systems should be factored
into any handover. Common problems include
12.2. Transfer of existing contracts passwords not being given to the new O&M service
provider and proprietary code in the Programmable
Contracts require special handling during handovers. Logic Controllers (PLC). Another problem may be the
They may have been executed with subcontractors use of the EPC service provider’s communication
such as local field electricians, companies who infrastructure for certain functionalities. For
take care of the vegetation, specialised support example, the use of the EPC service provider’s
companies, internet service providers etc. Virtual Private Network (VPN to give secure access
Further examples include service contracts with to network devices.
manufacturers of inverters or security systems.
The transfer of contracts is critical because the The most problematic point is probably the existence
obligations and responsibilities therein are also of proprietary PLC codes. Even if the EPC service
transferred. Furthermore, the new service provider provider agrees to give access to this code (which is
Ensuring a smooth handover of monitoring and To ensure an accurate and complete inspection on-
communication systems is vital for the long-term site, the EPC service provider and the Asset Owner
efficacy of a solar PV power plant. An O&M service should allow the O&M service provider sufficient
provider needs to be able to tell instantly from time to perform all the detailed checks that are
monitoring software what state any component is requested. This means that the handover inspection
in and determine deterioration trends to improve may last several days, depending upon the size
the amount of predictive maintenance that they and characteristics of the plant. As best practice,
carry out. O&M and EPC service providers should plan the
inspection well in advance, agreeing upon a written
As a best practice, the EPC service provider should schedule for the activities to be performed on-site,
facilitate the complete list of status and error with an indication of the role that the personnel of
codes produced by the device together with the each party will have during the visit.
detailed description of their meaning and possible
impact on the function of the device. Additionally, a The inspection should at least cover the following
standardisation of status and error codes through aspects.
inverters and dataloggers within a same brand should
A. Site Information (including description of plant access, surroundings, vegetation inside and
outside the fencing, etc.)
B. Document check list (as per Annex E of these guidelines, and Annex C of SolarPower Europe’s
O&M Best Practice Guidelines – India edition)
For each of the above component the following table shall be included
YES NO
System corresponding to what is specified in the as-built documentation
System installed correctly
The system status is sufficient
For each plant component or plant section requiring an intervention, the following information
should be included in the Punch List:
Any other additional information and recommendations for teams involved in future activities could
be added as an additional note to this report.
12.6. Set up of strategic spare lead to this list being updated following discussion
with manufacturers, amongst others.
parts warehouse
Table 15 – Minimum list of spare parts
Spare parts management is a key activity to ensure a
(non-exhaustive)
high level of availability and minimise downtime and
is typically included in the O&M service provider’s Examples for a minimum list of spare parts
scope of work. The starting point of this process is No. Spare part
the setup of a strategic spare parts warehouse. A
detailed description of this process can be found in 1 Fuses for all equipment (e.g., inverters,
Chapter 9. Spare parts management of SolarPower combiner boxes etc) and fuse kits
Europe’s O&M Best Practice Guidelines – India edition. 2 Modules
Below is a summary of it.
3 Inverter spares (e.g., power stacks, circuit
breakers, contactor, switches, controller board
The EPC service provider should buy spare parts
etc.)
together with all the other components for the
installation of the power plant as this ensures 4 Uninterruptible Power Supply (UPS)
maximum efficiency. Typically, the initial spare parts 5 Voltage terminations (MV)
should last at least for two years from Commercial
6 Power plant controller spares
Operation Date (COD). The volume should be in
line with the requirements of the Asset Owner and 7 SCADA and data communication spares
O&M service provider, as the O&M service provider 8 Transformer and switchgear spares
might recommend additional spares that they
9 Weather station sensors
deem necessary to meet contractual obligations
(e.g., availability guarantees). Generally, it is not 10 Motors and gearboxes for trackers
economically feasible to stock spare parts for every 11 Harnesses and cables
possible failure in the plant. Therefore, the O&M
12 Screws and other supplies and tools
service provider, together with the Asset Owner,
should define the stocking level of specific spare 13 Specified DC connectors (male and female
parts that make economic sense (Cost-Benefit should be from the same manufacturer)
Analysis). For a minimum list of spare parts, see the 14 Structures components
table below. This list is not exhaustive and system
15 Security equipment (e.g., cameras)
requirements and technology developments can
Figure 6. Key Performance Indicators in different project phases relevant for EPC
The value of this KPI depends of course on the 13.3.1. Performance Ratio
definition of quality checks, their number, and
distribution over the project period. Non-conformities The main KPI to evaluate overall plant performance
may include: is the Performance Ratio (PR). PR describes the
efficiency of the energy conversion system of a PV
• Deviations from execution plans plant. When calculating PR, one must bear in mind
• Construction defects that the efficiency of PV modules also depends
• Deviations from norms, standards, grid code, on temperature. For a detailed explanation and
and industrial best practice (the documents formulas, please refer to section 11.2.4. Temperature-
to be considered should be listed in the tender corrected Performance Ratio of SolarPower Europe’s
document) O&M Best Practice Guidelines – India edition.
• Deviations from permits
Tracking certain quality aspects separately, like 13.3.2. Overall project performance
conformity with EH&S protocols, is recommended.
In this case we would count non-conformities in KPIs regarding overall project performance are, in
EH&S and only compare it to the number of all EH&S most cases, identical to the Project performance
checks. KPIs described in section 13.1. Project performance
KPIs, with i being the concluding milestone of the
Since the importance of different quality aspects project.
may differ, it is a best practice to assign a weighting
factor for each conformity check. Other aspects of
project quality may be examined, for example: 13.3.3. Warranty KPIs
• The number of change requests (indicates the Additional ex-post KPIs after FAC measure the
quality of project development and preparation) handling of warranty claims by the EPC service
• KPIs describing the quality of communication provider, for example
between the stakeholders (surveys)
• The completeness of required documents for the • Number of broken components / Total number of
O&M phase (see Annex C of SolarPower Europe’s components
O&M Best Practice Guidelines – India edition) • Number of broken components replaced in
warranty procedure / Total number of broken
This list should be completed according to the components
necessities of the specific project.
Box: Split EPC contracts Figure 7 - Full-wrap contract vs split EPC contract
with umbrella agreement
The EPC contract may be construed either as
a full-wrap contract or a split contract. In the
SPV
latter case, the supply and installation of the
components are carried out by different service
providers. In this case, the Asset Owner (SPV)
EPC service
enters into different contracts for the supply provider
and installation of the components. The choice
of executing a full-wrap or a split EPC contract is
up to the Asset Owner, who must evaluate how to Component Sub-Contractor Sub-Contractor
Supplier No.1 No.2
allocate the risks associated with the individual
activities. The Asset Owner’s choice should
comply, as much as possible, with the Lenders’
SPV
requests and interests, who tend to prefer a
single reference point for the construction of
the project. As previously stated, the contract
structures are one of the bankability criteria to
be respected to ensure that the SPV receives the Umbrella
Agreement
necessary funds for covering the construction
and operating costs. Component Component Service
Supplier Installator Supplier
To avoid disputes in the case of a split contract • Termination: The termination of one of the
and an umbrella agreement, the following areas contracts should not have an impact on the
should be covered: other agreements and should not lead to
chain resolutions
• Scope of works: It is important that no “gaps”
arise between the scopes of work in each For a turnkey approach a full-wrap contract is the
single agreement, as it is not unusual that preferred option due to the single point of liability
technical inconsistencies may occur between principle. Lenders frequently prefer to have one
different agreements. Such mismatches financially robust party to take full responsibility
may be mitigated by defining the project in respect to all aspects of the construction
specification in the main contract (usually works regarding time, budget, costs, and
the installation agreement) and by defining technical and performance requirements.
14.1. Interface between the and other regulated bodies. In this respect, the
EPC service provider is responsible for maintaining
EPC contract and the regulatory
the vast majority, if not all, of said permits and
framework approvals. In fact, even if they are not responsible for
obtaining the construction permits (zoning permits,
The EPC service provider’s activities are also defined nihil obstat from public authorities, environmental
by the applicable regulatory requirements and impact assessment decree) which are procured by
permits obtained by the developer. developers in the pre-construction phase, the service
The construction of a PV plant requires a myriad provider must make sure that such authorisations
of permits and approvals from public authorities will remain in full force for the entire EPC contract’s
EPC contracts are usually drafted including a fixed A standard EPC contract will provide for the issuance
price clause which binds the parties to the total of the following bonds on the service provider’s side
price agreed thereunder. However, occasionally to secure all its obligations thereunder. In India, EPC
external factors, outside of anyone’s control can have service providers issue bank guarantees:
Additional resources:
BloombergNEF (2020), PV Module Tier 1 List Methodology,
Web: https://data.bloomberglp.com/professional/sites/24/BNEF-PV-Module-Tier-1-List-Methodology.pdf
International Centre for Sustainable Carbon (2021), India Pursues Ambitious Solar Goals Despite
Pandemic’s Impact, 14 July 2021. https://www.sustainable-carbon.org/india-pursues-ambitious-solar-
goals-despite-pandemics-impact/
SolarPower Europe (2020), Global Market Outlook for Solar Power 2020-2024,
Web: https://www.solarpowereurope.org/global-market-outlook-2020-2024/
World Bank Group (2020), General EHS guidelines references and sources.
Web: https://www.ifc.org/wps/wcm/connect/topics_ext_content/ifc_external_corporate_site/
sustainability-at-ifc/policies-standards/ehs-guidelines
International standards
See Annex A.
Minor (e.g. first aid) Very Low Low Moderate Moderate Moderate
Superficial
Very Low Very Low Low Low Moderate
(e.g. no treatment required)
ELIMINATE:
MINIMISE:
ID
Document(s) Title Description/Comment Submission Requirement
Level-#
Proposed aggregation and layout of the:
• PV Array sections
• Inverter Stations
• Substation
• Cable routes
Service provider’s Before
• Access roads Minimum
B-1 Specification(s), Construction
• Laydown areas requirement
Site layout Stage
• Meteorological stations
• Site tracks
• Pits
• Construction area
• Permanent and temporary buildings.
As Project documentation the service provider
shall provide a list of:
Before
Service provider’s • Standards relevant to the Works
B-2 Construction Best practice
Specification(s) • Equipment suppliers of Project major
Stage
components
• Sub-contractors
Service provider’s Before
Functional description and conceptual design Minimum
B-3 Specification(s), Construction
specification requirement
Amenities Building Stage
ID
Document(s) Title Description/Comment Submission Requirement
Level-#
In time required
The service provider shall supply a
to allow Employer
completed performance standard
Grid Connection review in accordance
template stating the proposed Minimum
C-3 Performance with the EPC Contract
level of compliance to each access requirement
Standard Template but no less than 4
standard in accordance with the
weeks prior to start of
utility
relevant work.
• Design calculations
• Demonstration of suitability of
all structural components in
PV Mounting
extreme wind conditions and over
Structures, Civil / 2 months after contract Minimum
C-8 the design life
Structural Design award requirement
• Detailed foundation
Report
specifications and design
• Borehole logs and geotechnical
test results
In time required to
PV Mounting 3 Party and manufacturer Report
rd
allow Employer review
Structure, 3rd party confirming the suitability of the in accordance with the Minimum
C-9
structural design PV Mounting Structure for the site EPC Contract but no less requirement
report conditions. than 8 weeks prior to
start of relevant work.
Electrical Works,
Cable Route Layout and associated
Cable route layout 2 months after Minimum
C-18 design drawings
and associated contract award requirement
design drawings
Electrical
Full specification and design drawings 4 weeks before
Works, Detailed Minimum
C-19 of all elements of the Electrical System commencement of the
specifications and requirement
relevant works
design drawings
Electrical Works,
Final optimisation of power cable 2 months after contract Minimum
C-20 Electrical System
conductor size. award requirement
optimisation report
Electrical Works,
Reactive Plant
Voltage regulation and reactive power 2 months after Contract Minimum
C-26 voltage regulation
flow control design report award requirement
& reactive power
control design report
Factory Acceptance
Copies of test certificates for all
Tests, Certificates
C-40 routine factory tests applied to all Prior to delivery to Site Best practice
and Reports,
major items included in the Works
Electrical Works
ID Document(s)
Description/Comment Submission Requirement
Level-# Title
Grid Connection Update to all required grid connection Prior to Practical Minimum
D-1
Documentation documentation Completion requirement
All licenses, software keys, hardware keys
Software Prior to Practical Minimum
D-2 (dongles) and the like for all software
Licenses Completion requirement
included in the Works.
Training programme required to support the
Training
off-site and in-field training of the Principal‘s Prior to Practical
D-3 Package and Best practice
personnel including hard and electronic Completion
Programme
copies of all training material.
Final - Fully indexed and linked - comprising
overview of the Solar Farm, specifications Prior to Practical
Minimum
D-4 O & M Manuals and all details for the safe and effective use, Completion
requirement
operation and maintenance of the complete
Solar Farm.
Safety Report The service provider shall update and submit 4 weeks Prior
D-5 (or Safety in the final Safety Report for all Permanent to Practical Best practice
Design) Works Completion
3rd Party Civil/Structural Chartered
Engineer’s Certificate confirming the
Civil Works, suitability of the PV Array Mounting
4 weeks Prior
3rd party civil/ Structure and all Civil Works, that they are in
to Practical
D-6 structural accordance with the As-built drawings and Best practice
Completion of the
design documentations and as required under the
relevant Section
certificate Applicable Laws, Regulations and Standards
in respect of the entire Solar Farm and site
building electrical works.
Electrical Updates to Electrical Design Report
4 weeks Prior
Works, Updated (submitted under Level B documents),
D-7 to Practical Best practice
Electrical following any design changes during
Completion
Design Report construction