Professional Documents
Culture Documents
+
L10: Budgeting and Cost Control
-
Instructor(s)
Olivier de Weck
Lecture 10
Project
Preparation Project Project
Planning Monitoring
Project
Control
Enterprise has
chosen what product Project
or system to develop Adaptation Project
Completion
Next
Project Project
Learning
- ESD.36J SPM 2
+
-
Outline
Tracking of Resource Consumption and Progress
Creating Measurable Plans
Schedule, Cost Tracking – “easy”
Scope/Progress Tracking – “hard”
Risk Tracking - how? (dedicated lecture to risk management)
Industrial Practice
“Earned Value Management” (EVM)
Role of Metrics in Project Management
Process-related metrics
Product-related metrics
- ESD.36J SPM 3
+
-
Discussion Point
- ESD.36J SPM 4
+
-
Project Tracking Challenges
CPM/PERT, DSM, SD- our project planning tools are
intended to help us establish a credible baseline for
planned schedule, project and product cost- tracking
should then be easy, right? But…
Timely data suited to direct use for project tracking is
difficult to access
Competing agendas in project resource organizations make
the already difficult task of technical progress assessment
even harder
Fitting the data into the proper context for project
assessment requires time and judgment
The fidelity of tracking can be no better than the
corresponding plan- detailed and realistic planning
requires significant effort
- ESD.36J SPM 5
+
-
Source Notes
Many following examples and methods draw upon
DOD/aerospace practices
Methods originated in industry
Initial application found to be resource-intensive
DOD applied due to project size and complexity
Commercial practices are converging with defense
(movement in both directions) as IT infrastructure
enables data acquisition and analyses
Practices are coming full circle
Stage-gate processes require tracking metrics
Tailoring for your organization and project is essential
- ESD.36J SPM 6
+
-
Creating Measurable Plans
1. DEFINE THE WORK
BUDGET BASE
$$ Mgmt Reserve
3. ALLOCATE BUDGETS
100
40
60
15
25
30
30
TIME
Source: USAF www.acq.osd.mil/evm
- ESD.36J SPM 7
+
-
Planning Resolution & Timing
Work Packages Planning Packages
Detailed, short-span tasks, or Future work that has not been
material items, required to detail planned as work packages.
accomplish the objectives, They are always scheduled to
typically in the near term occur in the future.
(include costs & completion
criteria)
Task 1
Work Packages Task 2
Task 3
Task 4
Planning Packages Task 5
-
Mapping Work to Resources
SOFTWARE
INTEGRATION
PROGRAM
SELECTED
PSWBS
ELEMENTS Product Master
Development Planning
ELEMENTS
Work
Packages
Operations
Hardware LAN Control Control BCWS
Engineering Applications Account Account BCWP
ACWP
BAC Planning
EAC Packages
-
Project Planning & Control Context
Preparation
develop a realistic plan of
organize the work and
Planning the teams the work scope, the
budget, and the schedule
Close out
- ESD.36J SPM 10
+
-
Data Sources for Project Tracking
Project cost is usually tracked in development
organization finance system
Data should be tracked on a ‘per task, per resource’ basis
to be most useful
As outsourcing becomes a major strategy, similar costs must
be gathered from suppliers
Reporting requirements need to be contractually specified
Work completion is usually measured by milestone,
but requires detailed planning and ‘costed’ tasks-
this is often the most problematic measurement
‘Percent complete’ measurements are notoriously unreliable
Milestone-based reporting is least ambiguous, but requires
substantial planning effort
- ESD.36J SPM 11
+
-
Earned Value Management
- ESD.36J SPM 12
+
-
Implementation Spectrum
ANSI/EIA-748-1998
Core EV Principles Tailored Applications (32 criteria)
- ESD.36J SPM 13
+
-
3+2=5 Key Elements
BCW S B u d g e te d C o s t o f W o rk S c h e d u le d
Planned Value
BCW P B u d g e te d C o s t o f W o rk P e rfo rm e d
Earned Value
ACW P A c tu a l C o s t o f W o rk P e rfo rm e d
Actual Cost
BAC B u d g e t a t C o m p le tio n
- ESD.36J SPM 14
+
-
Schedule Variance
BC WS
of the work I scheduled to have done,
BUDGET BASED
- ESD.36J SPM 15
+
-
Cost Variance
PERFORMANCE BASED
BC WP
of the work I actually performed,
how much did I budget for it to cost?
- ESD.36J SPM 16
+
-
Variance at Completion (VAC)
- ESD.36J SPM 17
+
-
5 Basic Questions/Parameters
QUESTION ANSWER ACRONYM
- ESD.36J SPM 18
+
-
Concept Question 1
- ESD.36J SPM 19
+
-
Earned Value Data Elements
6000 Time Now
5000
4000 CBB
MR
3000 BAC
(PMB)
2000
BCWS
ACWP
1000 BCWP
0
Jan Mar May Jul Sep Nov Jan Mar May
-
EV Data Elements- Variances
6000 Time Now
5000
4000 CBB
MR
3000 BAC
(PMB)
2000
BCWS
ACWP
1000 BCWP
Cost Variance Schedule Variance
0
Jan Mar May Jul Sep Nov Jan Mar May
Schedule Slip
-
EV Data Elements- Projections
6000 Time Now
EAC
5000
ETC
VAC
4000 CBB
MR
3000 BAC
(PMB)
2000 Projected
Program
BCWS
ACWP Delay
1000 BCWP
Cost Variance Schedule Variance
0
Jan Mar May Jul Sep Nov Jan Mar May
Schedule Slip
-
Data Analysis Relationships
Term Symbol Formula Checklist Actions
BCWP Ratio of work accomplished in terms of
Percent Complete % Done BAC the total amount of work to do.
Cost Performance Ratio of work accomplished against
Index or CPI BCWP money spent (Efficiency Rating:
Performance Factor or PF ACWP Work Done for Resources Expended)
To Complete Ratio of work remaining against money
Performance Index TCPI BAC - BCWP remaining (Efficiency which must be
or or VF EAC - ACWP achieved to complete the remaining work
Verification Factor with the expected remaining money)
Ratio of work accomplished against what
Schedule SPI BCWP should have been done (Efficiency Rating:
Performance Index BCWS Work done as compared to what should
have been done)
Estimate At Calculation of the estimate to complete
EAC ETC + ACWP plus the money spent
Completion
Estimate To ETC BAC - BCWP Calculation of the budgeted work
Complete CPI remaining against the performance factor
-
Risk Indicators
pr
n
ay
b
ar
Fe
Ja
A
M
M
- ESD.36J SPM 24
+
-
Concept Question 2
- ESD.36J SPM 25
+
-
Risk Indicators “corrupted”
Email excerpt from one of my NASA sponsored projects:
….they passed on to us new EVM color coding guidelines from the Chief
Engineer. We all frantically updated our charts. The failure to communicate
was that I did not pass these new guideline to the PI's and COTR's before I
left. In my defense, I only got a paper copy of the rules. So it was not
straight forward to transfer. The main change is that being higher
then 1.1 on your CPI or SPI is bad and colored that way. So you
need to cover that in your comments. The new standards for CPI/SPI's
are:
0.9 <= CPI/SPI <= 1.1 GREEN
0.8 <= CPI/SPI < 0.9 YELLOW
1.1 < CPI/SPI <= 1.2 YELLOW
CPI/SPI < 0.8 or CPI/SPI > 1.2 RED
We will use these for the next Monthly reports.
- ESD.36J SPM 26
+
-
Planning ‘Granularity’
To use EVMS with a reasonable amount of
management resources, plan at the
appropriate level of detail
Avoid ‘% complete’ estimation
Plan work packages with short duration,
estimated package cost, and clear deliverable
Assign ‘earned value’ at discrete levels, e.g.:
Zero value until work package start
50% value while executing
Full value when deliverable is complete
- ESD.36J SPM 27
+
-
Management Reserve
Calculate total project management reserve required
based on
statistical modeling
past experience
Total Funds
4000
3500 Management Reserve
BAC
3000
2500
Schedule
2000 Reserve
BCWS
1500
1000
500
0
Jan Mar May Jul Sep Nov Jan Mar May
- ESD.36J SPM 28
+
-
Project Control & Leverage
Management reserve (cost and schedule) are
important project management tools
Amounts based on statistical analyses, past
experiences typically in the 10-30% range
Reserves should be planned and validated with
the overall project plan
The project manager owns management
reserve and unallocated budget/schedule
Release of Management Reserve should be part of
a formal, risk-driven process
Requests for reserve allocation should follow a
quantitative template
- ESD.36J SPM 29
+
-
Formulation of Project Metrics
May be marginal, absolute, probabilistic
= X% improvement in ________
= X value of _______
= X value of _______ with 90% confidence
Tradition is metric based on benefit/performance
(with cost*, schedule and risk assessed later)
Current practice is metric based on
benefit/performance and cost
“Ideal” would be metrics which include
benefit/performance, schedule, cost and risk
-
Metric Tracking
Example:
Metric Value
target
Expected
Development
Crisis
Add
Resources Time
- ESD.36J SPM 31
+
-
Problems with Metrics
- ESD.36J SPM 32
+
Earned Value Management
- ‘GOLD CARD’
Please see https://acc.dau.mil/gc
-
Summary
- ESD.36J SPM 34
MIT OpenCourseWare
http://ocw.mit.edu
ESD. 6\VWHP3URMHFW0DQDJHPHQW
Fall 2012
For inforation about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms.