A project WBS is
Request 3
3 8 11 11 3 14 14 4 18
D G I
11 8 19 19 8 22 22 8 26
14 7 21 26
0 0 0 3 3 3 4 7 11 3 14 21 5 26 End
Start A B C F H
0 0 3 7 4 11 11 0 14 14 0 21 21 0 26
11 5 16
16 5 21
Path 1 Start -> A -> D-> G -> I-> End = 3+8+3+4=18 weeks
Path 3 Start ->A ->B -> E ->H -> End = 3+4+5+5= 17 weeks
Solution 1 Recruit more people to join project to complete task E earlier than 2 weeks
Solution 2 Force team to work overtime on task E to complete it earlier than 2 weeks
Request 5
After 3 weeks:
Estimate Schedule to complete project EDAC = DAC /SPI = 18/ 0,4= 45 weeks