ARBEREKETI - GELEMSO - MECHARA ROAD UPGRADING PROJECT

CONTRACT 1 :- ARBEREKETI - GELEMSO (57.5Km)


EMPLOYER CONSULTANT CONTRACTOR
ERA
Khatib&Alami Consulting Engineers(Offshore)S.A.L In JV with CORE Consulting Engineers Plc AL-ASAB GENERAL TRANSPORT & CONTRACTING EST.
Measurement Sheet

BILL 8.0 STRUCTURES:CULVERTS and Retaining Wall


Pay Item 81.02(a)(i) 81.02(a)(ii) 81.02(a)(iii) 81.05(b) 81.09(a) 81.09(c) 82.01(a) 83.01(a) 83.01(b) 84.01(a)(i) 84.01(a)(iii) 84.06 (i) 34.02(a) 87.03(i) 87.05 87.07 87.13(a)(i) 87.14(a)(i) 87.16(a)(i) 87.19(a) 89.01(b)(i) 91.01 (a) 91.01 (b) 91.03 (a)(ii) 93.01

Class A cement
Reinforced
Excavating material Excavating material Installation of mortared stone
Foundation fill Class 30/19 in all Packed riprap, Concrete Bridge Filled Joints- Sealing Joints with Galvanized guardrails on
within the following within the following Backfill to excavations High yield stress Class 15/19 concrete Approch Slab for Two layers of Expantion Joint, masonry walls (1:3 Galvanised gabion
Extra in increment of Compacted granular Formworks to provide all Mild steel bars superstructure parts, (Table 3404/1, class Parapets/Railings Preformed 25*30mm deep-cold Deck drains made Foundation Trench Foundation Trench steel posts, Complete Remark
Chainage successive depth successive depth utilising Imported Hand Laid Rock fill steel bars (Grade in blinding/lean New Bridge of Class elastomeric bearing bitumen felt over Expantion Joints In mortar ratio) for boxes, 80*100 mesh
Structure Type 1 meter fill (Selected granular class of finishes (Grade 300) abutment backwall and 3, critical mass Class C-30/25 expansion joint filler applied polysulphide of structural steel Excavation Backfilling including end and terminal
(Km) ranges0m up to ranges 2.0m up to material 420) concrete 25/19 Concrete abutment/pier cap Structural steel Construction of size (1x1x1)
backfill) walls foundation 50kg) Concrete as per the (20mm thick) sealant unit
2.0m 4.0m angles Retaining Walls,
drawing
Check Dams

m3 m3 m3 m3 m3 m3 m2 ton ton m3 m3 m3 m3 No. m2 m m m m No. m3 m3 m3 m3 m


CULVERT STRUCTURES
Km21+566 Slab Bridge 918.81 916.35 2,304.36 2,208.23 736.35 654.74 207.11 7.50 23.97 329.74 - - - - 7.55 55.66 - - - 4.00 1,423.64 - - - 73.52
Km25+601 RCDG Bridge 2,933.31 1,081.28 2,386.03 2,200.04 492.01 430.94 494.25 14.51 18.75 299.89 15.72 18.72 - 8.00 - 62.00 14.60 14.60 14.60 4.00 910.79 2,387.52 549.27 1,200.00 73.52
Km28+022 RCDG Bridge 4,080.15 1,414.70 2,141.61 2,477.05 1,005.63 685.23 407.48 12.67 19.53 325.92 18.16 20.37 - 8.00 - 61.00 15.14 15.14 15.14 4.00 1,063.33 1,095.42 284.33 1,200.00 73.52
Km40+777 Slab Bridge 1,162.33 1,162.25 2,355.21 2,516.46 1,064.01 630.46 196.81 4.21 18.47 271.61 - - - - 7.12 49.60 - - - 4.00 903.19 - - - 73.52
Km43+557 Slab Bridge 1,184.34 1,184.55 2,060.07 2,585.31 812.42 629.31 224.99 4.16 18.10 268.61 - - - - 7.51 49.64 - - - 4.00 833.79 - - - 73.52
Km53+324 RCDG Bridge 1,213.24 1,213.18 2,510.20 2,784.26 838.42 574.24 634.32 20.37 25.34 358.74 18.23 18.72 - 16.00 - 79.71 21.90 21.90 21.90 8.00 1,071.41 - - - 73.52

Total Design Quantity 11,492.17 6,972.32 13,757.49 14,771.36 4,948.85 3,604.91 2,164.95 63.42 124.16 1,854.50 52.11 57.81 - 32.00 22.18 357.61 51.64 51.64 51.64 28.00 6,206.16 3,482.94 833.59 2,400.00 441.12
Total Paid Quantity 7,393.16 7,228.64 14,334.42 - 4,806.08 5,790.15 1,330.95 55.16 105.80 1,863.86 92.08 - - 32.00 - - - - - - 6,081.80 - - - - -
Difference Quantity 4,099.01 -256.32 -576.93 14,771.36 142.77 -2,185.24 834.00 8.26 18.36 -9.36 -39.97 57.81 - - 22.18 357.61 51.64 51.64 51.64 28.00 124.36 3,482.94 833.59 2,400.00 441.12 -

Financial Progress
Unit rate 90 100 50 110.00 300.00 110.00 120.00 29,000.00 33,000.00 3,800.00 2,700.00 700 350 20000 1,000.00 2,000.00 500.00 1,000.00 500.00 1,000.00 1,500.00 75.00 120 1108 2,000.00
Amount 368,910.88 -25,632.44 -28,846.71 1,624,849.22 42,830.41 -240,376.62 100,080.21 239,620.42 605,988.14 -35,558.09 -107,914.53 40,464.26 - - 22,180.35 715,216.00 25,820.00 51,640.00 25,820.00 28,000.00 186,534.00 261,220.56 100,031.31 2,659,200.00 882,240.00
Total Difference Amount 7,542,317.37

Prepared By (QS)
Signature:-
Date:- 10-Aug-23
ARBEREKETI - GELEMSO - MECHARA ROAD UPGRADING PROJECT
CONTRACT 1 :- ARBEREKETI - GELEMSO (57.5Km)
EMPLOYER CONSULTANT CONTRACTOR
ERA
Khatib&Alami Consulting Engineers(Offshore)S.A.L In JV with CORE Consulting Engineers Plc AL-ASAB GENERAL TRANSPORT & CONTRACTING EST.
Measurement Sheet

BILL 8.0 STRUCTURES:CULVERTS and Retaining Wall


Pay Item 81.02(a)(i) 81.02(a)(ii) 81.02(a)(iii) 81.05(b) 81.09(a) 81.09(c) 82.01(a) 83.01(a) 83.01(b) 84.01(a)(i) 84.01(a)(iii) 84.06 (i) 34.02(a) 87.03(i) 87.05 87.07 87.13(a)(i) 87.14(a)(i) 87.16(a)(i) 87.19(a) 89.01(b)(i) 91.01 (a) 91.01 (b) 91.03 (a)(ii) 93.01

Class A cement
Excavating Reinforced
Excavating material Foundation fill Class 30/19 in all Installation of mortared stone Galvanized
material within the Backfill to Packed riprap, Concrete Bridge Filled Joints- Sealing Joints with
within the following Compacted Formworks to High yield stress superstructure Class 15/19 concrete Approch Slab for Two layers of Expantion Joint, masonry walls (1:3 Galvanised gabion guardrails on steel
following Extra in increment excavations Mild steel bars (Table 3404/1, class Parapets/Railings Preformed 25*30mm deep-cold Deck drains made Foundation Trench Foundation Trench Remark
Chainage successive depth Hand Laid Rock fill granular fill provide all class of steel bars (Grade parts, abutment in blinding/lean New Bridge of Class elastomeric bearing bitumen felt over Expantion Joints In mortar ratio) for boxes, 80*100 posts, Complete
Structure Type successive depth of 1 meter utilising Imported (Grade 300) 3, critical mass Class C-30/25 expansion joint filler applied polysulphide of structural steel Excavation Backfilling
(Km) ranges0m up to (Selected finishes 420) backwall and walls concrete 25/19 Concrete abutment/pier cap Structural steel Construction of mesh size (1x1x1) including end and
ranges 2.0m up to material 50kg) Concrete as per the (20mm thick) sealant
2.0m granular backfill) foundation angles Retaining Walls, terminal unit
4.0m drawing
Check Dams

m3 m3 m3 m3 m3 m3 m2 ton ton m3 m3 m3 m3 No. m2 m m m m No. m3 m3 m3 m3 m


CULVERT STRUCTURES
Km21+566 Slab Bridge 918.86 916.40 2,304.34 658.62 2,182.13 84.18 5.66 18.70 276.58 - - - - - - - - - - 1,353.99 - - - -
Km25+601 RCDG Bridge 1,003.16 1,005.64 2,297.52 976.35 1,192.70 401.07 13.07 17.64 320.67 14.76 - - 8.00 - - - - - - 1,106.31 - - - -
Km28+022 RCDG Bridge 1,695.35 1,693.39 2,718.49 760.25 435.76 217.44 18.10 18.53 386.21 29.17 - - 8.00 - - - - - - 667.20 - - - -
Km40+777 Slab Bridge 1,226.86 1,226.67 2,485.89 925.11 292.14 131.61 4.08 17.85 271.61 13.41 - - - - - - - - - 903.79 - - - -
Km43+557 Slab Bridge 1,249.01 1,249.20 2,172.53 871.36 1,424.11 202.82 4.03 17.54 262.26 12.80 - - - - - - - - - 913.54 - - - -
Km53+324 RCDG Bridge 1,299.92 1,137.34 2,355.65 614.39 263.31 293.83 10.22 15.54 346.53 21.94 - - 16.00 - - - - - - 1,136.97 - - - -
-

Total Paid Quantity 7,393.16 7,228.64 14,334.42 - 4,806.08 5,790.15 1,330.95 55.16 105.80 1,863.86 92.08 - - 32.00 - - - - - - 6,081.80 - - - -

Prepared By (QS)
Signature:-
Date:- 10-Aug-23
ARBEREKETI - GELEMSO - MECHARA ROAD UPGRADING PROJECT
CONTRACT 1 :- ARBEREKETI - GELEMSO (57.5Km)
EMPLOYER
CONSULTANT CONTRACTOR
ERA
Khatib&Alami Consulting Engineers(Offshore)S.A.L In JV with CORE Consulting Engineers Plc AL-ASAB GENERAL TRANSPORT & CONTRACTING EST.
Measurement Sheet

BILL 8.0 STRUCTURES:CULVERTS and Retaining Wall


Pay Item 81.02(a)(i) 81.02(a)(ii) 81.02(a)(iii) 81.05(b) 81.09(a) 81.09(c) 82.01(a) 83.01(a) 83.01(b) 84.01(a)(i) 84.01(a)(iii) 84.06 (i) 34.02(a) 87.03(i) 87.05 87.07 87.13(a)(i) 87.14(a)(i) 87.16(a)(i) 87.19(a) 89.01(b)(i) 91.01 (a) 91.01 (b) 91.03 (a)(ii) 93.01

Class A cement
Excavating Reinforced
Excavating material Foundation fill Class 30/19 in all Installation of mortared stone Galvanized
material within the Backfill to Packed riprap, Concrete Bridge Filled Joints- Sealing Joints with
within the following Compacted Formworks to High yield stress superstructure Class 15/19 concrete Approch Slab for Two layers of Expantion Joint, masonry walls (1:3 Galvanised gabion guardrails on steel
following Extra in increment excavations Mild steel bars (Table 3404/1, class Parapets/Railings Preformed 25*30mm deep-cold Deck drains made Foundation Trench Foundation Trench Remark
Chainage successive depth Hand Laid Rock fill granular fill provide all class of steel bars (Grade parts, abutment in blinding/lean New Bridge of Class elastomeric bearing bitumen felt over Expantion Joints In mortar ratio) for boxes, 80*100 posts, Complete
Structure Type successive depth of 1 meter utilising Imported (Grade 300) 3, critical mass Class C-30/25 expansion joint filler applied polysulphide of structural steel Excavation Backfilling
(Km) ranges0m up to (Selected finishes 420) backwall and walls concrete 25/19 Concrete abutment/pier cap Structural steel Construction of mesh size (1x1x1) including end and
ranges 2.0m up to material 50kg) Concrete as per the (20mm thick) sealant
2.0m granular backfill) foundation angles Retaining Walls, terminal unit
4.0m drawing
Check Dams

m3 m3 m3 m3 m3 m3 m2 ton ton m3 m3 m3 m3 No. m2 m m m m No. m3 m3 m3 m3 m


CULVERT STRUCTURES
Km21+566 Slab Bridge -0.05 -0.05 0.02 2,208.23 77.73 -1,527.39 122.93 1.84 5.27 53.16 - - - - 7.55 55.66 - - - 4.00 69.65 - - - 73.52
Km25+601 RCDG Bridge 1,930.15 75.64 88.51 2,200.04 -484.34 -761.76 93.18 1.44 1.11 -20.78 0.96 18.72 - - - 62.00 14.60 14.60 14.60 4.00 -195.52 2,387.52 549.27 1,200.00 73.52
Km28+022 RCDG Bridge 2,384.80 -278.69 -576.88 2,477.05 245.38 249.47 190.04 -5.43 1.00 -60.29 -11.01 20.37 - - - 61.00 15.14 15.14 15.14 4.00 396.13 1,095.42 284.33 1,200.00 73.52
Km40+777 Slab Bridge -64.53 -64.42 -130.68 2,516.46 138.90 338.32 65.20 0.13 0.62 -0.00 -13.41 - - - 7.12 49.60 - - - 4.00 -0.60 - - - 73.52
Km43+557 Slab Bridge -64.67 -64.65 -112.46 2,585.31 -58.94 -794.80 22.17 0.13 0.56 6.35 -12.80 - - - 7.51 49.64 - - - 4.00 -79.75 - - - 73.52
Km53+324 RCDG Bridge -86.68 75.84 154.55 2,784.26 224.03 310.93 340.49 10.15 9.80 12.21 -3.71 18.72 - - - 79.71 21.90 21.90 21.90 8.00 -65.56 - - - 73.52

Total Difference Quantity 4,099.01 -256.32 -576.93 14,771.36 142.77 -2,185.24 834.00 8.26 18.36 -9.36 -39.97 57.81 - - 22.18 357.61 51.64 51.64 51.64 28.00 124.36 3,482.94 833.59 2,400.00 441.12

Prepared By (QS)
Signature:-
Date:- 10-Aug-23
ARBEREKETI - GELEMSO - MECHARA ROAD UPGRADING PROJECT
CONTRACT 1 :- ARBEREKETI - GELEMSO (57.5Km)
EMPLOYER
CONSULTANT CONTRACTOR
ERA
Khatib&Alami Consulting Engineers(Offshore)S.A.L In JV with CORE Consulting Engineers Plc AL-ASAB GENERAL TRANSPORT & CONTRACTING EST.
Measurement Sheet

BILL 8.0 STRUCTURES:CULVERTS and Retaining Wall


Pay Item 81.02(a)(i) 81.02(a)(ii) 81.02(a)(iii) 81.05(b) 81.09(a) 81.09(c) 82.01(a) 83.01(a) 83.01(b) 84.01(a)(i) 84.01(a)(iii) 84.06 (i) 34.02(a) 87.03(i) 87.05 87.07 87.13(a)(i) 87.14(a)(i) 87.16(a)(i) 87.19(a) 89.01(b)(i) 91.01 (a) 91.01 (b) 91.03 (a)(ii) 93.01

Class A cement
Excavating Reinforced
Excavating material Class 30/19 in all Installation of mortared stone Galvanized
material within the Foundation fill Packed riprap, Concrete Bridge Filled Joints- Sealing Joints with
within the following Backfill to excavations Formworks to High yield stress superstructure Class 15/19 concrete Approch Slab for Two layers of Expantion Joint, masonry walls (1:3 Galvanised gabion guardrails on steel
following Extra in increment Compacted granular Mild steel bars (Table 3404/1, class Parapets/Railings Preformed 25*30mm deep-cold Deck drains made Foundation Trench Foundation Trench Remark
Chainage successive depth utilising Imported Hand Laid Rock fill provide all class of steel bars (Grade parts, abutment in blinding/lean New Bridge of Class elastomeric bearing bitumen felt over Expantion Joints In mortar ratio) for boxes, 80*100 mesh posts, Complete
Structure Type successive depth of 1 meter fill (Selected (Grade 300) 3, critical mass Class C-30/25 expansion joint filler applied polysulphide of structural steel Excavation Backfilling
(Km) ranges0m up to material finishes 420) backwall and walls concrete 25/19 Concrete abutment/pier cap Structural steel Construction of size (1x1x1) including end and
ranges 2.0m up to granular backfill) 50kg) Concrete as per the (20mm thick) sealant
2.0m foundation angles Retaining Walls, terminal unit
4.0m drawing
Check Dams

m3 m3 m3 m3 m3 m3 m2 ton ton m3 m3 m3 m3 No. m2 m m m m No. m3 m3 m3 m3 m


CULVERT STRUCTURES
Km21+566 Slab Bridge -4.78 -4.54 1.03 242,905.34 23,320.04 -168,013.29 14,751.03 53,490.73 173,959.10 201,994.15 - - - - 7,552.20 111,312.00 - - - 4,000.00 104,471.13 - - - 147,040.00
Km25+601 RCDG Bridge 173,713.39 7,564.06 4,425.69 242,004.13 -145,301.60 -83,793.96 11,181.72 41,671.22 36,661.31 -78,971.60 2,594.70 13,103.44 - - - 124,000.00 7,300.00 14,600.00 7,300.00 4,000.00 -293,281.20 179,063.94 65,912.02 1,329,600.00 147,040.00
Km28+022 RCDG Bridge 214,631.57 -27,869.44 -28,844.05 272,476.04 73,613.75 27,441.17 22,804.88 -157,483.46 33,016.01 -229,109.07 -29,730.09 14,257.38 - - - 122,000.00 7,570.00 15,140.00 7,570.00 4,000.00 594,198.39 82,156.62 34,119.29 1,329,600.00 147,040.00
Km40+777 Slab Bridge -5,807.45 -6,442.19 -6,533.90 276,810.62 41,671.12 37,215.69 7,824.05 3,838.59 20,338.23 -7.88 -36,207.00 - - - 7,120.00 99,200.00 - - - 4,000.00 -900.89 - - - 147,040.00
Km43+557 Slab Bridge -5,820.54 -6,464.54 -5,623.00 284,384.42 -17,683.02 -87,428.10 2,660.16 3,633.70 18,456.47 24,143.63 -34,560.00 - - - 7,508.15 99,280.00 - - - 4,000.00 -119,618.86 - - - 147,040.00
Km53+324 RCDG Bridge -7,801.32 7,584.21 7,727.52 306,268.68 67,210.11 34,201.87 40,858.37 294,469.64 323,557.02 46,392.67 -10,012.13 13,103.44 - - - 159,424.00 10,950.00 21,900.00 10,950.00 8,000.00 -98,334.58 - - - 147,040.00
-

Total Difference Amount (ETB) 368,910.88 -25,632.44 -28,846.71 1,624,849.22 42,830.41 -240,376.62 100,080.21 239,620.42 605,988.14 -35,558.09 -107,914.53 40,464.26 - - 22,180.35 715,216.00 25,820.00 51,640.00 25,820.00 28,000.00 186,534.00 261,220.56 100,031.31 2,659,200.00 882,240.00 -

Prepared By (QS)
Signature:-
Date:- 10-Aug-23