You are on page 1of 7

Life-Cycle Management of Construction Projects Based

on Virtual Prototyping Technology


H. L. Guo, Ph.D.1; Heng Li2; and Martin Skitmore3

Abstract: Life-cycle management 共LCM兲 has been employed in the management of construction projects for many years in order to
reduce whole life cost, time, risk and improve the service to owners. However, owing to lack of an effective information sharing platform,
Downloaded from ascelibrary.org by Tokyo Univ Seisan Gijutsu on 06/03/15. Copyright ASCE. For personal use only; all rights reserved.

the current LCM of construction projects is not effectively used in the construction industry. Based upon the analysis of the information
flow of LCM, a virtual prototyping 共VP兲-based communication and collaboration information platform is proposed. Following this, the
platform is customized using DASSAULT software. The whole process of implementing the VP-based LCM of projects is analyzed via
the application to a real-life construction project. The advantages of implementing a VP-based LCM are also discussed and, from a simple
case study, it is demonstrated that the VP-based communication and collaboration information platform is an effective tool to support the
LCM of construction projects.
DOI: 10.1061/共ASCE兲0742-597X共2010兲26:1共41兲
CE Database subject headings: Construction management; Life cycles; Information management; Communication.
Author keywords: Construction projects; Life cycle management; Information sharing; Virtual prototyping.

Introduction problems. LCM integrates each phase of project management


from planning to close out, making information sharing and co-
Life-cycle management 共LCM兲 has been introduced into the man- ordination possible between owners, consultants, designers, con-
agement of construction projects in recent years 共Gransberg and tractors, etc. 关International Organisation for Standardisation 共ISO兲
Ellicott 1997; Jaafari 2000兲 and it is believed that LCM can re- 2002; Teresko 2004兴. All parties can communicate and collabo-
duce the life-cycle cost of projects and improve the service to rate with each other in real time. On the one hand, this makes the
owners 共Chalfant 2001; Xie and Simon 2006兲. Construction holistic operation processes consistent so as to ensure a reason-
project management is traditionally separated into several inde- able construction time and cost; on the other hand, it enables the
pendent and contiguous phases, e.g., planning, design, construc- owners’ interests to be protected due to their ideas receiving due
tion, commissioning, etc., and they are implemented respectively attention from the parties involved.
with almost no communication or interaction between partici- The effective implementation of LCM in construction projects
pants in each phase 共Gransberg and Ellicott 1997兲. This leads to relies strongly on a visual communication and collaboration in-
many problems. For example, due to lack of communication and formation platform 共Ameri and Dutta 2004; Garetti 2004兲 as in-
collaboration between designers and constructors, most of designs formation sharing is the key to implementing LCM 共Schilli and
need to be modified or reworked during construction due to its Dai 2006兲. An effective information platform is needed to gather
unfeasibility; otherwise, these changes cannot be effectively sup- project information 共Gross and Fleisch 2004兲 and furnish relevant
ported by design personnel in that after a design is finished and information 共from planning to decommissioning兲 to each partici-
then transferred to constructors, design personnel’s tasks are over pant 共Krause and Kind 1998兲. At the same time, this allows
in the traditional project management method. As a result, time or information to be open, transparent, and otherwise easy to under-
cost overruns often occur and the rights 共e.g., normal completion stand, especially for complex projects. However, no such infor-
time, cost, etc.兲 of owners are unable to be warranted 共Ellicott mation platform exists in the construction industry. Often, many
1994兲. The application of the LCM approach helps to solve these shop drawings and Gantt charts provided by different parties are
needed to conduct the LCM of construction projects as all par-
1
Construction Virtual Prototyping Lab., Dept. of Building and Real ties, including owners, consultants, designers, contractors, etc.,
Estate, Hong Kong Polytechnic Univ., Hung Hom, Kowloon, Hong Kong need them to discuss and make decisions on the planning, design,
共corresponding author兲. E-mail: samuel.guo@polyu.edu.hk procurement, construction, commissioning, and decommissioning
2
Professor, Construction Virtual Prototyping Lab., Dept. of Building of projects. Due to the increasing complexity of projects, a great
and Real Estate, Hong Kong Polytechnic Univ., Hung Hom, Kowloon, deal of information is needed 共Love et al. 2002; Lee et al. 2006兲.
Hong Kong. E-mail: bshengli@polyu.edu.hk
3
This is usually provided in the form of two-dimensional 共2D兲
Professor, Faculty of Built Environment and Engineering, 共dimensions兲 drawings that cannot be easily understood by each
Queensland Univ. of Technology, Gardens Point, Brisbane L404, Austra- party. For example, owners find it difficult to understand the
lia. E-mail: rm.skitmore@qut.edu.au
drawings provided by designers, while designers often cannot
Note. This manuscript was submitted on May 6, 2008; approved on
April 10, 2009; published online on December 15, 2009. Discussion pe- completely master the ideas of owners. As a result, the target of
riod open until June 1, 2010; separate discussions must be submitted for “information sharing” is rarely realized in the current LCM of
individual papers. This paper is part of the Journal of Management in construction projects.
Engineering, Vol. 26, No. 1, January 1, 2010. ©ASCE, ISSN 0742- As a result, some information systems and new technologies
597X/2010/1-41–47/$25.00. have been developed and employed for the LCM of construction

JOURNAL OF MANAGEMENT IN ENGINEERING © ASCE / JANUARY 2010 / 41

J. Manage. Eng. 2010.26:41-47.


projects. A representative prototype system, Integrated Facility
Planning Design
Engineering, developed by the University of Sydney, takes into
consideration the information management of projects 共Jaafari
and Manivong 1998兲, visual management of design 共Chaaya and Construction
Jaafari 1999兲, information management of construction 共Jaafari
et al. 2000兲, dynamic simulation modeling 共Doloi and Jaafari Decommissioning
2000兲, etc. Although the system involves many modules, most of Commissioning
these are simply theoretical models and not applicable to real-life
construction projects. Another representative commercial technol-
Maintenance Utilization
ogy, AUTODESK BLM, is a project LCM based on a BUZZSAW
server, and provides online service to project management.
REVIT, one of software modules embedded in BUZZSAW, can Fig. 1. Life cycle of a construction project
supply a visual design environment and facilitate communication
Downloaded from ascelibrary.org by Tokyo Univ Seisan Gijutsu on 06/03/15. Copyright ASCE. For personal use only; all rights reserved.

and collaborative design, but focuses on the design phase only


and not construction and operation.
As an alternative, this paper describes the use of virtual pro- closure 共Kerzner 2001兲 should be applied to projects. Based on
totyping 共VP兲 for the LCM of construction projects. VP technol- the features of construction projects, the following life-cycle
ogy is a computer-aided design process concerned with the phases are adopted here 共see Fig. 1兲.
construction of a digital mock-up and realistic graphical simula- Note that Planning includes conception design, preliminary
tion to address the broad issues of physical layout, operational evaluation, etc.; design involves initial design and detail design;
concept, functional specifications, and dynamics analysis under utilization refers to the owners’ or tenants’ use or operation of
various virtual operating environments 共Shen et al. 2005; Xiang buildings; and decommissioning consists of demolition and re-
et al. 2004; Pratt 1995兲. Although VP technology has been exten- cycle of buildings or material.
sively and successfully applied to the automobile and aerospace
fields 共Choi and Chan 2004兲, its development and application in
the construction industry 共i.e., construction process simulation兲 Information Flow for the LCM of Construction Projects
has been limited to date. This is due to construction projects being The LCM of construction projects can be described as a manage-
unique in terms of their conditions, requirements, and constraints. ment system for all the processes of a project 共An 2003兲, from
The Construction Virtual Prototyping Laboratory 共CVPL兲 of the planning, design, and construction to the commissioning, utiliza-
Hong Kong Polytechnic University has conducted much research tion, maintenance, and otherwise decommissioning of the project.
into the application of VP to real-life construction projects in Its information flows should therefore involve information con-
Hong Kong, e.g., Huang et al. 共2007兲. This has shown VP tech- cerning all these phases. As shown in Fig. 2, this includes a great
nology to be a useful tool and effective visual communication and deal of information relating to planning, design, construction,
collaboration platform for owners, consultants, designers, con- commissioning, utilization, maintenance, and decommissioning.
tractors, subcontractors, or other participants in the design, con- The information is integrated into the VP-based communication
struction, and management of construction projects. and collaboration information platform.
Based upon CVPL research, the VP technology is presented as The information flow has both a forward influence and a back-
a key technique to establishing a visual communication and col- ward impact, that is, the information of a phase both influences,
laboration information platform for the LCM of construction and is influenced by, its successive phases. When a decision is
projects 共building projects兲. Its theoretical structure is elaborated made, its impact on predecessors or successors, even the whole
and the implementation process of VP-based LCM is examined life cycle, must be taken into account. This is explained in detail
into through a real-life construction project in Hong Kong—the in the next section.
Tseung Kwan O 共TKO兲 Sports Ground.

VP-Based Information Platform for Construction Planning


Project LCM Building type
Building area, etc

Decommissioning Design
LCM of Construction Projects Demolishing Architecture
Recycle, etc Structure
LCM has been developed as a business approach for managing BS, etc
the total life cycle of products and services 共Garetti 2004; Kovacs
et al. 2006兲. It has been discussed and applied widely in the
manufacturing industry 共Hayes and Wheelwright 1979a,b; Maintenance Construction
Labuschagne and Brent 2005兲. Its potential application in the con- Warranty Time
Operational guide Resources
struction industry has also been examined in recent years and Safety, etc Sequence, etc
various project life-cycle approaches have been discussed, e.g., Utilization
control-oriented models, quality-oriented models, risk-oriented Warranty Commissioning
Document review
models, etc., 共Bonnal et al. 2002兲. In addition, it has been noted Operational guide
Safety, etc Technical review, etc
that, owing to the different characteristics of projects or indus-
tries, the phases of project life cycle are different from each Legend Forward information flow Backward information flow
other. As a result, it has been proposed that the available life-cycle
phases of conceptual, planning, testing, implementation and Fig. 2. Information flow of LCM of construction projects

42 / JOURNAL OF MANAGEMENT IN ENGINEERING © ASCE / JANUARY 2010

J. Manage. Eng. 2010.26:41-47.


Owners Consultants Owner
Designer
Conception Rough design
VP-based communication VP technology Pro modeler
Designers and collaboration Subcontractors
information platform Initial design Rough digital
1
Main model module model
Contractors Other parties Owner, consultant,
3D model Response Pro modeler Designer designer
No
Process simulation module Yes Feasibility?

Planning information No
Initial digital Owner, consultant
Design information 1 Approved?
model
Construction information Designer Yes
Pro modeler
Downloaded from ascelibrary.org by Tokyo Univ Seisan Gijutsu on 06/03/15. Copyright ASCE. For personal use only; all rights reserved.

Commissioning information
Detailed design
Utilization information Owner, consultant,
designer, constructor,
Maintenance information maintainer No
Detailed
Decommissioning information 1 Constructability?
digital model
Constructor Yes
Pro modeler
Fig. 3. Model of VP-based communication and collaboration infor-
V-Construction
mation platform Owner, consultant,
designer, constructor No
Construction
2 Constructability?
simulation
Yes
VP-Based Information Platform for LCM
2 A-Construction
3
Based on LCM model of a construction project and its informa-
Constructor
tion flows, the theoretical model of a VP-based LCM communi- No Yes
cation and collaboration platform is developed as shown in Fig. 3. 4 Commissioning Problems?
The information platform provides a virtual environment that in-
cludes two main modules, i.e., a main model module and process No Yes
1 Utilization Problems?
simulation module. The main model module is used to build the
digital mock-up of the project, the so-called main model, which
consists of static information from the life-cycle phases of the 2 Maintenance

project, e.g., planning, design; and the process simulation module


focuses on the dynamic information of projects, e.g., the construc- Decommissioning
tion process and methods, and space analysis. In this way, all the
1 2 3
information concerning the life-cycle phases is integrated into the
platform. Comm-
Main Process
Through the platform, all project participants share the rel- issioning 4
model simulation document
evant information presented above and communicate with each
other in real time. The main model is a three-dimensional 共3D兲
digital model, which visually shows all the static information Fig. 4. Operational flowchart of the VP-based information platform
needed for a project. Each participant can understand it easily,
and therefore the model allows all participants to conveniently
communicate and collaborate with each other. On the other hand, ods are available for maintenance and demolition. This will also
the process module offers a virtual environment to all parties to provide a 3D instruction for maintenance and demolition in the
“try before actually building.” As we know, often the construction future.
process is complex and irreversible and before actual construction Fig. 4 shows the operational flowchart of the VP-based infor-
is commenced, the construction schedule and methods must be mation platform. Note that V-Construction means virtual con-
checked and approved by owners or consultants in order to ensure struction; A-Construction means actual construction; and the Pro
a smooth construction process. Despite this, rework is inevitable modeler means the process modeler—which may be looked upon
as the traditional construction statement cannot be prepared in as a new career involving the use of VP technology for the prod-
enough detail and many problems cannot be anticipated prior to uct and process modeling of construction projects.
actual construction. The process simulation module assists own- Beginning with the owner’s conception, a construction project
ers, consultants, even constructors to understand, discuss, and is commenced. In the planning phase, with the consultant’s guid-
modify the construction methods before actual construction so as ance, the designer develops a rough design from which the pro-
to reduce rework or risks. It can also help with the maintenance cess modeler builds an initial digital model. This enables the
and demolition of a building. From the point of view of LCM, the owner, consultant and designer to check the rough design together
design of the building not only takes into consideration its con- and modify the design and model until it is feasible. This is fol-
struction, but also considers its maintenance and demolition in lowed by the design phase, in which the rough design is devel-
order to reduce the life-cycle cost and risks. That is the design oped into an initial and detailed design by the designers. The
should fit to maintenance and demolition as well as construction. relevant digital model is established by the process modeler and is
The maintenance and demolition processes and methods of the used to check the constructability of design by the owner, con-
building can be tried and tested by using the information platform sultant, designer, and constructor. They work together to solve
to ensure that the design and maintenance and demolition meth- any problems using the digital model. Especially, based on the

JOURNAL OF MANAGEMENT IN ENGINEERING © ASCE / JANUARY 2010 / 43

J. Manage. Eng. 2010.26:41-47.


Owner, Consultant, Architect, Structure engineer, BS engineer, Contractor, Subcontractor,
Finishing engineer, Property manager, Demolishing manager, etc

VP technology-DASSAULT SYSTEMES Planning


PROCESS ENGINEER
3D models Decommissioning Design
CATIA V5

DELMIA V5 Simulation Maintenance Construction

Utilization Commissioning
PPR HUB
Fig. 6. Planning the TKO sports ground project

3D model database Process simulation database


Downloaded from ascelibrary.org by Tokyo Univ Seisan Gijutsu on 06/03/15. Copyright ASCE. For personal use only; all rights reserved.

Fig. 5. VP-based LCM information platform customized section provides a detailed description of the process of imple-
menting the LCM for construction projects via the VP-based in-
formation platform.

platform, owner’s concerns not only ensure that owner’s ideas can
be realized in the design, but also make the design more feasible Process of Implementing VP-Based LCM
and efficient than before through eliminating some unfeasible
ideas in time. For the construction phase, construction methods
Planning
and construction schedule provided by the contractor or subcon-
tractor are transferred into a virtual simulation process, and the At the beginning of the planning phase of a construction project,
process simulation will be continuously updated as long as con- the LCM can be implemented through the VP-based information
struction methods or schedule are changed and approved. The platform. The owners describe their conception of the construc-
owner, consultants, and contractor work together using the virtual tion project, the consultant/designer can easily communicate with
process until a feasible construction method or sequence of work owners and rapidly and accurately get their opinions on the basis
is obtained. When this is satisfactorily competed, the simulation of the information platform. Also many ideas can be easily tried
results are applied to instructing the actual construction work. In with a very low cost using VP technology until a suitable concep-
the remaining phases, the digital model and process simulation is tion is created. As an example, Fig. 6 shows the final layout of
used with the VP technology to explain the design and construc- the TKO sports ground project in Hong Kong. This is the rough
tion and help identify and solve further problems. In addition, digital model of the project, including a spectator stand, a main
previous phases may be revisited and reinvestigated as needed. soccer field, and a subsidiary soccer field, which are built and
It can be seen from Fig. 4 that the VP technology plays an analyzed using PROCESS ENGINEER and CATIA V5. Through
important role in the LCM of a construction project. Both the the digital model, the owner and consultant discussed the general
main model and process simulation arising from the VP provide planning of the sports ground and modified it until it satisfied the
an effective communication and collaboration information plat- owner’s needs. It can be seen that the planning model is very
form for all participants for each phase of the project. During the clear and easily understood, especially for the design of the spec-
process of LCM, the planning/design/construction methods may tator stand.
be changed according to the needs of all parties until the final LCM is not a fixed process but an iterative one. Unlike tradi-
LCM method is defined tional project management, some changes continuously occur in
the holistic process of LCM so as to meet the requirement of
all parties. For instance, when some problems appear in the con-
Customization of VP-Based Information Platform
struction or design phase, the conception of projects needs to be
The VP technology developed by CVPL is mainly based on soft- reinvestigated and changed many times. The platform also can
ware from Dassault Systemes Corp. Thus the VP-based LCM provide a virtual environment for convenient and rapid reinvesti-
information platform is also customized using the software, i.e., gation or modification. Otherwise it can make these changes
PROCESS ENGINEER, CATIA V5, and DELMIA V5. Its theo- easily understood by the owner as sometimes owners cannot un-
retical model is shown in Fig. 5. derstand shop drawings or their changes. After the visual planning
The holistic platform is supported by PPR HUB, which is finished, the relevant information may be saved to guide the
integrates process, product, and resources modules. PROCESS design.
ENGINEER helps the owner/consultant test their ideas in a vir-
tual platform or environment and assists in planning decisions;
Design
CATIA V5 allows the owner, architect, structure engineer, BS
engineer, finishing engineer, contractor, or other users to create Following the visual planning, designers, i.e., architect, structure
and check the design of a building, including a digital mock-up engineer, and BS&EM engineer, may conduct collaborative de-
of the building, temporary works and construction equipments; sign via the visual platform and this forms the digital mock-up of
and DELMIA V5 provides a virtual environment for the contrac- the project, namely, the Main Model, using CATIA V5. Fig. 7
tor or subcontractor to define and simulate construction processes shows the main model of the TKO project built by CVPL and
and evaluate different construction methods so as to check prob- which underpins the following phases. When the design of the
lems, e.g., collisions between machine and building, safety, time architecture, structure, and building services is separately con-
waste. All of these form the LCM information platform and all ducted in the traditional method, conflicts between these separate
the digital models are provided by CATIA V5. The following designs often occur. The collaborative design process identifies

44 / JOURNAL OF MANAGEMENT IN ENGINEERING © ASCE / JANUARY 2010

J. Manage. Eng. 2010.26:41-47.


Fig. 9. Simulation of roof truss installation in the TKO project

the rework of construction, lowers the construction cost and time,


Fig. 7. Main model of TKO sports ground project and improves the quality of projects. The holistic simulation pro-
cess is conducted using DELMIA V5.
Downloaded from ascelibrary.org by Tokyo Univ Seisan Gijutsu on 06/03/15. Copyright ASCE. For personal use only; all rights reserved.

By using the simulation, owners, or consultants may conve-


these conflicts, for example, between a pile cap and an under- niently communicate with contractors or subcontractors and know
ground pipe in the TKO project 共see Fig. 8兲, and enables them to enough about the construction process and methods for the con-
be modified as soon as possible. struction statements to be efficiently approved. For traditional
At the same time, the constructor 共e.g., a consultant or a LCM or project management approaches, it is very difficult for
project engineer兲 involved in the phase identifies the constructa- owners or consultants to know about the construction process
bility of the design so that the process of construction can be and therefore much more time is spent on the approval of con-
smooth. Rework therefore is reduced or eliminated further to re- struction statements. Additionally, the final simulation can capture
duce the whole life-cycle cost and time. The owner and consultant and save much knowledge for future projects and support future
also have early knowledge of the design and are able to offer their maintenance.
comments, so that the design is easily and rapidly approved.
Although many design errors and constructability issues are Commissioning
identified before construction, some problems still occur in the
process of actual construction. These also need the support of the All documents arising from above several phases help in commis-
platform to analyze the design. Thus the main model of the sioning the construction project. In addition to technical docu-
project is an important information entity of the VP-based LCM mentation, the VP-based information platform supplies visual
information platform. It provides a great deal of information for documents to support the commissioning process. As with the
the construction, commissioning, and maintenance of the project. design/construction phase, the owner and tenant can understand
the whole project using these visual documents before or after
project delivery. This facilitates the commissioning process and
Construction saves time.
In the construction phase, the focus of the LCM is on construction As an example, the performance evaluation of the design of
methods, construction techniques, the utilization and allocation of the spectator stand in the TKO project is presented as follows.
resources in order to control construction time, cost, and quality. As the spectator stand of a sports ground, it must ensure that the
Different projects require different construction methods, that is, audiences’ sightline is not hindered. In practice, traditional meth-
the construction method for the project is usually unique. Con- ods area available to test the sightline, but these are not very
tractors or subcontractors can use the VP-based information plat- accurate. In this project, the VP technology is used and the per-
form to freely simulate and discuss the process of construction to formance is shown easily and clearly 共see Fig. 10兲. This is a test
decide the optimal construction method, construction sequence, result at a key point, showing that the handrail has little influence
and resource leveling and test new construction techniques before on sightline. Therefore, when the project is delivered, a useful
actual construction is commenced. Fig. 9 shows the optimization video can be provided to assist the contractor and client in ex-
process of roof truss installation method in the TKO project iden- plaining this.
tified as a result of many iterations in the platform. The platform
can also be adopted to simulate the planning of construction, Utilization
make the whole process smooth in the virtual environment, and
provide working guides for workmen. This reduces or eliminates After commissioning, the platform provides a digital mock-up
for the owners or tenants to organize the operation/utilization
of a building. Conventionally, owners or tenants only have a con-
ception about the project but know little of the characteristics of

Fig. 8. Conflict between pile cap and pipe in the TKO project Fig. 10. Performance evaluation of audiences’ sightline

JOURNAL OF MANAGEMENT IN ENGINEERING © ASCE / JANUARY 2010 / 45

J. Manage. Eng. 2010.26:41-47.


Table 1. Contribution of VP Technology to the LCM of Construction Projects
Time Cost Service
Phase of LCM VP technology saving saving improvement
Planning Initial main model Much Little More
Design Main model More More Much
Construction Main model and process simulation More More Much
Commissioning Main model and process simulation Much Little Much
Utilization Main model and process simulation Much Little More
Maintenance Main model and process simulation More much More
Decommissioning Main model and process simulation More More Less
Note: Less, Little, Much, and More denote the degree of contribution of VP technology to the LCM of construction projects and the degree from Less to
More increases.
Downloaded from ascelibrary.org by Tokyo Univ Seisan Gijutsu on 06/03/15. Copyright ASCE. For personal use only; all rights reserved.

the final product 共the building兲. They do not know how to operate Decommissioning
or utilize some devices in the building. The digital mock-up sup-
plies them with a visual document to help them do this. To some At the end of the building’s useful life, the main model can be
extent, this saves time and money, which can be spent on teaching used to inform its demolition. At that time, based on the main
or learning. Also the service to the owner is improved. Note that model some key structures can be identified, the procedure for
the digital mock-up 共main model兲 is often created in the design demolition determined, and the material or components to be re-
phase and it is updated with the change of the design at the time utilized identified and protected. This will reduce the risk and cost
these operations are considered. of demolishing the building and is not possible with traditional
The main model of the buildings established using the VP methods.
technology also offers a management platform for property man- Additionally, many demolishing methods can been tried and
agement. At present, many buildings have been managed via em- checked in the VP-based platform until a suitable method is
ploying management information systems, and most of them found. This also makes the demolition process smooth and safe,
adopt the plan, elevation, or section of a building to manage in- and reduces time and cost. From the view point of the LCM, these
habitants or assist in fire control. However, only professionals can have been taken into account in the design and construction
understand all of these drawings. Although some of management phase.
information systems introduce 3D models of buildings, the rel- This section presents the process of implementing LCM for
evant model needs to be postdeveloped, which is time-and-cost construction projects using the VP-based communication and col-
waste. Thus it is useful and economical to construct and apply the laboration platform. The following section will discuss the perfor-
main model using the VP-based LCM approach to the manage- mance of the implementation of VP-based LCM.
ment of buildings. This not only reduces management costs but
also ensures adequate safety.
Discussion
Maintenance
Advantages of Implementing a VP-Based LCM
The main model of the building provides visual information for
maintainers to maintain or change some parts of building or de- From the analysis of the implementation of the VP-based LCM,
vices. This is especially important for some nontypical buildings, it is clear that the VP technology makes a surprising contribution
e.g., sports grounds. The drawings related to the building are in to the LCM of construction projects. VP-based LCM appears to
such great quantity that they are difficult to preserve. Often after have a great number of advantages, e.g., reducing the risk, time,
5–10 years, they are lost or destroyed. When maintaining the and cost of operating a project and improving the service level to
building, relevant drawings are not available. Although some of owners/tenants during the whole life cycle. The detailed advan-
electronic drawings, e.g., CAD drawings, are currently stored in tages of the VP-based information platform in different phases of
computers, these 2D drawings are usually difficult to be under- life cycle of projects are summarized in Table 1. It is obvious that
stood by maintainers. The 3D main model can help maintainers the VP technology makes an important improvement to the LCM
do this conveniently and clearly. Also, the main model includes of projects, especially in the design and construction phases,
much manufactures’ information, for example name, telephone, while from experiences, the time and cost of implementing the
address, etc., and the information of devices or material, e.g., VP technology is much less than the time and cost savings. Such
name, type, etc. This information integrated with the main model a level of performance is impossible to be realized in the tradi-
can aid maintainers to select relevant material, devices, etc. Main- tional LCM of construction projects.
tainers only need to click on an item to get its relevant informa-
tion and therefore it is easy to use the platform. Case Study of Cost and Time Saving
Furthermore, for some projects difficult to be maintained or in the Construction Phase
modified, maintenance solutions can be tested via the VP technol-
ogy. This informs maintainers on how to conduct maintenance in As a simple case study of the use of VP-based LCM, the cost and
the future and can lower maintenance costs and risks. Note that time saving in the construction phase is summarized for several
all information can be easily managed by owner’s own staffs in real-life construction projects in Hong Kong and Macau 共see
the system and therefore it is convenient for the owner to use this Table 2兲. All data are collected from relevant contractors, that is,
information. these data are empirical. In some cases the situation is unclear due

46 / JOURNAL OF MANAGEMENT IN ENGINEERING © ASCE / JANUARY 2010

J. Manage. Eng. 2010.26:41-47.


Table 2. Cost and Time Savings in the Construction Phases of Real-Life Proc., 17th Int. Symp. on Automation and Robotics in Construction
Projects in Hong Kong (ISARC 2000), National Taiwan Univ., Taipei, Taiwan, 739–744.
Project name Cost saving Time saving Ellicott, M. A. 共1994兲. “Best-value contracting.” Proc., Area Engineer’s
Conf., TransAtlantic Division, U.S. Army Corps of Engineers, Texas.
Kwai Chung public housing Unclear About 17% Garetti, M. 共2004兲. “PLM: A new business model to foster product inno-
HKCC Unclear Unclear vation.” Proc., Int. IMS Forum 2004: Global Challenges in Manufac-
Ho Tung Lau About 12% About 5% turing, Vol. 2, Villa-Erba-Cernobbio, Italy, 917–924.
Venetian Macau Hotel About 5% Unclear Gransberg, D. D., and Ellicott, M. A. 共1997兲. “Life cycle project man-
TKO Sports Ground About 250HKD About 1 month agement.” AACE international transactions, American Association of
Cost Engineers, Chicago, 288–292.
Gross, S., and Fleisch, E. 共2004兲. “Maintenance improvement by unique
to lack of data. From the data provided in Table 2, although not product information enabled by ubiquitous computing.” Proc., 11th
including all data from the holistic life cycles of projects, it is IFAC Symp. on Information Control Problems in Manufacturing,
Downloaded from ascelibrary.org by Tokyo Univ Seisan Gijutsu on 06/03/15. Copyright ASCE. For personal use only; all rights reserved.

clear that the VP technology can make the LCM much useful and Salvador, Brazil, 65–70.
effective. Hayes, R. H., and Wheelwright, S. C. 共1979a兲. “Link manufacturing pro-
cess and product lifecycles: Focusing on the process gives a new
dimension to strategy.” Harvard Bus. Rev., 57, 133–140.
Conclusions Hayes, R. H., and Wheelwright, S. C. 共1979b兲. “The dynamics of
process-product life cycles.” Harvard Bus. Rev., 57, 127–136.
LCM has been a needed feature of the construction industry for Huang, T., Kong, C. W., Guo, H. L., Baldwin, A., and Li, H. 共2007兲. “A
many years, but has not been successful in its application as yet. virtual prototyping system for simulating construction processes.”
This is because it lacks an effective communication and collabo- Autom. Constr., 16共5兲, 576–585.
International Organisation for Standardisation 共ISO兲. 共2002兲. “Systems
ration information platform to support information sharing be-
engineering: System life cycle processes.” ISO/IEC 15288:2002 Stan-
tween different parties. This paper describes a new information
dard, 具http://www.iso.org典 共Mar. 18, 2008兲.
sharing platform using VP technology via analyzing the informa- Jaafari, A. 共2000兲. “Life-cycle project management: A proposed theoret-
tion flow of LCM of construction projects and customizing the ical model for development and implementation of capital projects.”
platform using DASSAULT software. The process of implement- Proj. Manage. J., 31共1兲, 44–52.
ing LCM of projects is presented on the basis of the VP-based Jaafari, A., and Manivong, K. 共1998兲. “Towards a smart project manage-
information platform. The advantages of implementing VP-based ment information system.” Int. J. Proj. Manage., 16共4兲, 249–265.
LCM are further discussed and it is shown that the VP technology Jaafari, A., Manivong, K. K., and Chaaya, M. 共2000兲. “The story of
can provide useful support to implementing the LCM of construc- VIRCON in simulation and teaching professional construction man-
tion projects. However, VP-based LCM of construction projects is agement.” Proc., Int. Conf. on Construction Information Technology,
still in its infancy and much further research is still needed. For Hong Kong Polytechnic Univ., Hong Kong, 515–532.
example, the delivery approach 共e.g., design-build兲 of a project Kerzner, H. 共2001兲. Project management: A systems approach to plan-
has an impact on the implementation of VP-based LCM since it ning, scheduling and controlling, Wiley, New York.
affects the participants during different phases; although this Kovacs, G., Kopacsi, S., Haidegger, G., and Michelini, R. 共2006兲.
paper presents the advantages of the VP-based LCM platform for “Ambient intelligence in product life-cycle management.” Eng. Appl.
Artif. Intell., 19共8兲, 953–965.
the construction phase, these data are empirical, and a quantitative
Krause, F. L., and Kind, C. 共1998兲. “Strategic planning of information
method is needed to quantitatively analyze the advantages of the
technological infrastructures for life cycle management.” Annals of
platform. These all need to be further studied. the ClRP, 47共1兲, 129–132.
Labuschagne, C., and Brent, A. C. 共2005兲. “Sustainable project life cycle
management: The need to integrate life cycles in the manufacturing
References sector.” Int. J. Proj. Manage., 23共2兲, 159–168.
Lee, S. H., Pena-Mora, F., and Park, M. 共2006兲. “Dynamic planning and
Ameri, F., and Dutta, D. 共2004兲. “Product lifecycle management control methodology for strategic and operational construction project
needs, concepts and components.” Technical Rep. No. PLM-TR3– management.” Autom. Construct., 15共1兲, 84–97.
2004, Product Lifecycle Management Alliance, Michigan, 具http:// Love, P. E. D., Holt, G. D., Shen, L. Y., Li, H., and Irani, Z. 共2002兲.
www.plmdc.engin.umich.edu典 共Oct. 12, 2007兲. “Using systems dynamics to better understand change and rework in
An, X. H. 共2003兲. “Lifecycle management for construction project based construction project management systems.” Int. J. Proj. Manage.,
on IT.” Intelligent building and urban informatization, Vol. 4, Intelli- 20共6兲, 425–436.
gent Building & City Information, Beijing, 70–72. Pratt, M. J. 共1995兲. “Virtual prototyping and product models in mechani-
Bonnal, P., Gourc, D., and Lacoste, G. 共2002兲. “The life cycle of technical cal engineering.” Virtual prototyping-virtual environments and the
projects.” Proj. Manage. J., 33共1兲, 12–19. product design process, Chapman & Hall, London, 113–128.
Chaaya, M., and Jaafari, A. 共1999兲. “Integrated design management Schilli, B., and Dai, F. 共2006兲. “Collaborative life cycle management
within a life cycle project management paradigm.” Proc., 2nd Int. between suppliers and OEM.” Comput. Ind. Eng., 57共8–9兲, 725–731.
Conf. on Construction Process Re-Engineering, Australian Center for Shen, Q., Gausemeier, J., Bauch, J., and Radkowski, R. 共2005兲. “A co-
Construction Innovation, Sydney, Australia, 279–289. operative virtual prototyping system for mechatronic solution ele-
Chalfant, R. V. 共2001兲. “The benefits of life-cycle management.” Iron Age ments based assembly.” Adv. Eng. Inf., 19共2兲, 169–177.
New Steel, 17共1兲, 31. Teresko, J. 共2004兲. “The PLM revolution.” Ind. Week, 253共2兲, 32–36.
Choi, S. H., and Chan, A. M. M. 共2004兲. “A virtual prototyping Xiang, W., Fok, S. C., and Thimm, G. 共2004兲. “Agent-based composable
system for rapid product development.” Comput. Aided Des., 36共5兲, simulation for virtual prototyping of fluid power system.” Comput.
401–412. Ind. Eng., 54共3兲, 237–251.
Doloi, H., and Jaafari, A. 共2000兲. “Application of simulation tool for Xie, X., and Simon, M. 共2006兲. “Simulation for product life cycle man-
strategic decision evaluation for life cycle project management.” agement.” Int. J. Manuf. Technol. Manage., 17共4兲, 486–495.

JOURNAL OF MANAGEMENT IN ENGINEERING © ASCE / JANUARY 2010 / 47

J. Manage. Eng. 2010.26:41-47.

You might also like