Professional Documents
Culture Documents
445
446 lisaka
INTRODUCTION
In order to create the transverse joint, this research developed a new vibration
joint cutting machine, and executed test works concerning limit time for joint
cutting, direction of joint cutting, kind of joint filling, an insertion method of joint
filling, and so on. In this paper the test methods and results are described.
Fig. I shows the outline of the joint cutting machine, and Table I shows the
specification. Table 2 shows the mixture proportion of concrete used for the
Concrete Technology 447
test, and Fig. 2 shows the test places for joint cutting according to the elapsed
time.
The proctor penetration resistance test was conducted after specimens were
subjected to wet screening using a 5 nun sieve, divided into two layers and
crammed into a mold (15cm dia. x 15cm). Each layer was compacted for 20
seconds by a vibrator. The specimens intended for a strength test were prepared
by using concrete subjected to wet screening with a 40 mm sieve divided into
three layers, placed into a mold( 15cm dia. x 30cm). Each layer was compected
by vibratOr for 30 seconds.
Table 3 shows the test result using the above described method. From this
result, it is presumed that the time which allows joint cutting is within about four
hours after mixing of the concrete was completed.
Fig. 3 shows the relationship between the proctor penetration resistance value
and time. It indicates that the penetration resistance value which allows joint
cutting is 13.73 MPa or less. Fig. 4 shows the relationship between
compressive strength and joint cutting time. It indicates that the compressive
strength which allows joint cutting is O.OS MPa.
DlSCUSSION
From the above described tests on joint cutting the following parameters arc
discussed.
In the case of a single sheet of galvanized iron, the tip hook portion of the
galvanized iron sheet was cut after a lapse of one hour and could not be inserted.
On the other hand, when it was made twofold for execution, it could be inserted at
a predetermined height even after a lapse of two hours (Photo. I).
found that the following method to form joints after concrete is leveled would be
to insert joint filler before compaction by a vibration roller. This is because the
concrete was soft before compaction, and the joint formation time became shorter
making the operation easier.
By hooking a galvanized iron sheet twofold after leveling the concrete, the
sheet embrace the joint cutting blade. There by easily create a joint without
disturbing the concrete. In this manner the construction speed was also
increased.
CONCLUSIONS
It was found that the limit time for joint formation is about four hours after
completion of the concrete mixture. Also, the joint cutting blade should be
preferably set in the operating direction. It was found better where the tip end of
a galvanized iron sheet as joint filling is bent twofold. It is allowed the sheet to
embrace a joint cutting blade when inserted at the start of the joint cutting
operation.
REFERENCE
Reclaimpower of blade
9: 53 14: 25 272
The joint cutting was performed three times The joint opening thickness was The portion of the joint
Condition (2m in length x 3times=6m), but twice among about I em, with few filling-up,etc., was disturbed.
of these three times, the joint filling(plywood) and was substantilly completely The portion around the
I
joint could not be inserted because of filling-up. created. same to left joint was disturbed.
I
cutting The remaining one time was also to such a The joint was some what disturbed,
degree that two sheets, among five sheets, but this was the limit for which the
a number of sheets of joint material required, joint cutting was allowed.
can be inserted.
C")
=
=
-
...
Condition It was in a state in which concrete has The crack was partly seen, but it was Until lapsed time of two hours, a guide The portion around the n
of surface protruded within a range of 30om around the a smaller amount as compared with angle was used during execution of works, joint was disturbed. CD
of concrete joint, causing crack. CD
lapsed time of one hour. but after a lapse of three hours, the guide
-1
angle was removed for joint cutting. In this CD
n
case, the protuberance or crack was reduced. :::r
=
=
=
~-
=
<
-'="
c.n
452 lisaka
@
@
2.100
~
=
-
I
--i
=
co
0
@
s. 0
0
""
::::l c..;
co
s. I I '
''
'
0
;::.
C")
~-
::::l
= c:")
0
3Q) § ::I
...n
C")
~
co -=
=
--i
=
n
::r
::I
0
0
=
<
-'="
C"'
~
~
U'l
~
(surface) ;;·
=
~
=
cr> @ @ @ ® ® (j) §
80
'"
§
(section)
1'7'7!<1±1
Fig. 2-The specification of joint cutting test places
Concrete Technology 455
20.58
'@'
a..
6
mean em era ure 16.1
concrE te t mp rah re 1~oc
oc
v
~
Q)
c: >
~g
.Pj!l
~-~ ./
v I
I
I
I
I
I
I
I
v
Q)(f) I
~~ 6.86 ------ ----- - - - ------ ---- ---- T I
I
- 1----- --
~ /:
I
I
e
a.. 3.43
I
I
-,--
I--' l7"
!-------
I
I
I
llmltt malo !Joint uttlng I
0 47 77 107137167197227257287
Age (minute)
Fig. 4-The relation between compressive strength and joint cutting time
0.20
'@'
0..
-E,
~
0.15 ------ - - - ----- - ----
lZ
c:
~ 0.10 t_ __
comp esslve str ngth at
limI tlmeforlt lnt cuttlna
----- -----
/
I --
-~
0
()
~
a. 0.05
E ,/
tz1 I
- ------
I llmlttlm~ or
I
I
I
1 lnl cuttlna
I
~
0 0 1 2 3 4 5 6
Age (hour)
456 lisaka