PMD 913 - Module 4 - Earned Value Management
PMD 913 - Module 4 - Earned Value Management
April 2015
Introduction
Earned Value Analysis (EVA) or Earned Value
Management (EVM) is a project management
technique for measuring project progress in an
objective manner.
EVM has the ability to combine measurements of
scope, schedule, and cost in a single integrated
system.
EVM provides an early warning system for project
performance.
Performance Schedule
Measures SV>0 & SPI>1 SV=0 & SPI=1 SV<0 & SPI<1
Ahead of
CV>0 & Schedule
On Schedule Behind Schedule
CPI>1 Under Budget Under Budget
Under Budget
Ahead of
CV=0 & On Schedule Behind Schedule
Cost CPI=1
Schedule
On Budget On Budget
On Budget
Ahead of
CV<0 & Schedule
On Schedule Behind Schedule
CPI<1 Over Budget Over Budget
Over Budget
Schedule Forecasting
Time Estimate at Completion (EACT) provides a rough estimate
when the project will be completed
EACT = Planned Project Duration / SPI
EACT can provide differing results from schedule updating???