Types of affected buildings Maximum noise level permitted for construction
sites (reckoned as an equivalent continuous noise
level over a period of 12 hours) in decibel (A)
7 am ? 7 pm 7 pm ? 7 am
Hospitals, schools,
60 50
institutions of higher
learning, homes for the
aged, sick etc
Buildings other than the
75 65
above
Part II
The maximum permissible noise levels for construction sites
under Part I are subject to the overall maximum permissible
noise levels for any 5 minutes period as follows:
Types of affected Maximum noise level permitted for construction sites
buildings (reckoned as an equivalent continuous noise level over a
period of 5 minutes) in decibel (A)
7 am ? 7 pm 7 pm ? 7 am
Hospitals, schools,
75 55
institutions of
higher learning,
homes for the
aged, sick etc
Buildings other
90 70
than the above
Part I
7 am ? 7 pm 7 pm ? 7 am
The maximum permissible noise levels for construction sites under Part I are
subject to the overall maximum permissible noise levels for any one-hour
period as follows:
7 am ? 7 pm 7 pm ? 10 pm 10pm ? 7am
(a) Hospitals, - - -
schools,
institutions of
higher learning,
homes for the
aged, sick etc
(b) Residential - 65 55
buildings located
less than 150m
from the
construction site
where the noise is
being emitted
(c) Buildings - - -
(other than those
in paragraphs (a)
and (b) above
Part III
The maximum permissible noise levels for construction sites under Part I are
subject to the overall maximum permissible noise levels for any 5-minute
period as follows:
7 am ? 7 pm 7 pm ? 10 pm 10pm ? 7am
(a) Hospitals, 75 55 55
schools,
institutions of
higher learning,
homes for the
aged, sick etc
(b) Residential 90 70 60
buildings located
less than 150m
from the
construction site
where the noise is
being emitted
(c) Buildings 90 70 70
(other than those
in paragraphs (a)
and (b) above