Notes/Assumptions
rate per m2; recovery factor 30% based on 3 times usage
Materials
Plywood 25mm thick size 1.20m x 2.40m cost RM65/piece
Therefore 1m2 of formwork is RM65/1.20m x 2.40m 22.57
Assume every 1m2 of formwork requires 0.03m3 support
0.03m3 x RM200/m3 6.00
Assume every 1m2 of formwork requires 0.75kg nails
0.75kg x RM5/kg 3.75
32.32
Add
Wastage 10% 3.23
35.55
Deduct
Recovery factor 30% 10.67
24.88
Labour
Applying linseed/timber oil 0.10 hours
Repair and clean up 0.10 hours
0.20 hours x RM5/hr 1.00
Cost of linseed/timber oil, materials for repair and clean, say 1.00
46.29
Plants/Machineries
N/A 0.00
46.29
Add
Overheads & Profit 20% 39.38
85.67 /m2