Sawn formwork to sides of columns

Notes/Assumptions
rate per m2; recovery factor 30% based on 3 times usage

Materials
Plywood 25mm thick size 1.20m x 2.40m cost RM65/piece
Therefore 1m2 of formwork is RM65/1.20m x 2.40m 22.57
Assume every 1m2 of formwork requires 0.03m3 support
0.03m3 x RM200/m3 6.00
Assume every 1m2 of formwork requires 0.75kg nails
0.75kg x RM5/kg 3.75

32.32
Add
Wastage 10% 3.23

35.55
Deduct
Recovery factor 30% 10.67

24.88

Therefore, the cost of using once is RM24.88/3 times 8.29

Labour
Applying linseed/timber oil 0.10 hours
Repair and clean up 0.10 hours
0.20 hours x RM5/hr 1.00

Cost of linseed/timber oil, materials for repair and clean, say 1.00

Carpenter to construct, fix and take down 1m2 of formwork


Construct 1.20 hours
Fixing 1.60 hours
Take down 0.80 hours
3.60 hours x RM10/hr 36.00 38.00

46.29

Plants/Machineries
N/A 0.00

46.29
Add
Overheads & Profit 20% 39.38

85.67 /m2