SDP Coverage Requirement
Overview
• To resolve outdoor coverage at SDP worker quarters using Cel-Fi solution as coverage extender
• Celcom LTE signals are marginal due to the plantation rural locations

Scope Summary
• To install 8m pole in Sime Darby Workers Quarters Area as suggested in Technical Proposal
• To install Parabolic Antenna on top of the pole
• To install 3 units of YAGI antenna
• To install Solar panel & Lithium-ion battery for power
• To install and commission Cel-fi GO X
• To install and commission android box for remote monitoring
• To install enclosure for equipment protection
• To fine tune and adjust settings & antenna positions for optimum results
Standard SDP Cel-Fi GO X Installation
High Gain
Nextcell
Parabolic
Donor
Antenna

Mesh Wire

Directional
Celcom Server Antenna
Donor Site

LMR400
Coaxial
3-way Cable
splitter
Solar Panel
Worker
quarters

Worker
quarters Li Ion
Battery

Android
Cel-Fi GO X
Nextcell
Cel-Fi GO X implementation for SDP Sg. Samak (Main Quarters)
Installation of Antennas, Cel-fi GO X and the rest of pole segments
Nextcell
Cel-Fi GO X implementation for SDP Sg. Samak (Main Quarters)
Wave app Status and Bands Selection
Cel-Fi GO X implementation for SDP Sg. Samak (Main Quarters) Nextcell
Coverage Walk test results (Input from Celcom - to be inserted by Celcom)

Without Cel-Fi GO X Post Installation