Nama Barang Type Jml Harga (Rp) Total (Rp)
PC Server INTEL 1 9,000,000 9,000,000
Printer LX-310 EPSON 1 3,500,000 3,500,000
PC for Admin INTEL 1 4,000,000 4,000,000
Total Rp 16,500,000.00
Software
Nama Barang Type Jml Harga (Rp) Total (Rp)
Parking-Point 1.0 Type M EMS 1 40,000,000 40,000,000
Total Rp 40,000,000.00
Pekerjaan Sipil
Nama Barang Type Jml Harga (Rp) Total (Rp)
Dudukan Barrier - 2 500,000 1,000,000
Pemasangan Kabel Loop Barrier - 2 500,000 1,000,000
Pemasangan Kabel Loop Dispenser - 2 500,000 1,000,000
Instalasi Jaringan Data with BELDEN meter 200 30,000 6,000,000
Instalasi Jaringan Power meter 100 20,000 2,000,000
Equipment Instalasi - 1 10,000,000 10,000,000
Biaya Instalasi Tukang (2hari) - 7 400,000 2,800,000
Total Rp 23,800,000.00
Training & Set Up Fee (luar kota) Untuk 2 Orang selama 1 Minggu 8,000,000
Total Biaya Rp 153,800,000.00