Professional Documents
Culture Documents
I/23695/2024
To
Chief Engineer Distribution South/Central/North/North Malabar, Chief Engineer
(IT,CR&CAPS),Deputy Chief Engineers,Electrical Circles
Sir/ Madam,
Sub: Implementation of Uniform labour data and Cost data 2024 for Distribution
works based on DSR 2018-Clarifications-reg
Ref: Queries from the field offices via Email/Phone/Whatsapp
I/23695/2024
issued based on pre revised rates and Administrative and technical sanction based
remittance was made before 08.02.2024 . on pre revised rate will be incorporated in
SAMAGRA within one week)
In cases of works for which
Administrative sanction and Technical Option to select Revised / Pre revised rate
5 sanction was issued based on pre revised will be incorporated in the SAMAGRA
rate and if technical sanction revision is software.
required.
Cases in which Administrative
sanction,Technical sanction and work
6 order are as per pre revised rate but No revision of AS/TS required.
material issue is done as per purchase
rate (Invoice rate)
The option for incorporating pre revised rates in software will be enabled and shall be
active for one month.Hence all Section officers are requested to process the Work bills for
the works done before 08.02.2024 within one month.After one month, this provision shall
be closed and there will be no extension further.
The Chief Engineer (IT,CR&CAPS) shall make necessary arrangement for incorporating
the option for including pre revised cost data rates in software for a period of one month
from the date of enabling the option and with due intimation to field officers.
Yours faithfully
SURENDRA P
DIRECTOR