You are on page 1of 7

EENG 95A

LAB 1: SYNCHRONIZATION OF
ALTERNATOR WITH INFINITE BUSBAR

CONDITIONS FOR SYNCHRONIZATION


Equality of Voltage
- Terminal voltage of both systems
should be the same STEPS:
- By voltmeter 1. Make connections
Phase Sequence 2. Start one alternator to rated voltage
- Phase sequence should be equal and close bus bar switch
- By any synchronization method 3. Start 2nd machine to equal speed with
Equality of Frequency the running alternator
- Frequency should be the same 4. Synchronize the 2nd machine using a
- By any synchronizing method synchronization method
OBSERVATIONS:
SYNCHRONIZING METHODS 1. Adjust 2nd machine (Vg) and bus bar
 Using incandescent lamp (Vs) until Vg=Vs
 Synchroscope 2. Adjust speed of 2nd machine until
o Shows correct instant of closing synchroscope needle creeps
the synchronizing switch with a 3. Close synchronizing switch
pointer that rotates on a dial

USING INCANDESCENT LAMP


a. Synchronizing lamps
- 3 lamps connected to bus bar
- If speed is unequal, then frequency is
different creating phase difference in
voltages
- Lamps will flicker, darken, or brighten
- Synchronization is done when it is dark
- Synchronization is achieved when the
lamps darken or brighten
simultaneously
- DRAWBACKS
o Lamps darken at about 1/3 of
rated voltage causing faulty
synchronization to be done
o Not possible to know how much
faster/slower the machine is
o Not applicable to high voltage
alternators
 Uses step down
transformer when
needed
b. Synchronizing by synchroscope
- Pointer indicates if machine is too fast
or too slow
- Machine is slow = anticlockwise
- Machine is fast = clockwise
LAB 2: DIRECT AXIS REACTANCE (Xd) 7. Get max and min value of armature
AND QUADRATURE AXIS REACTANCE voltage and current
(Xq) OF SYNCHRONOUS MACHINE 8. Find voltage per phase (V p=V 1 / √ 3)
(for salient pole synchronous machine) Maximum lagging current test for
determination of Xq
WHY MEASURE Xq AND Xd? 1. Run synchronous machine as
- 3-phase dead short circuit at terminals alternator with help of DC machine and
of synchronous generator, it gives high synchronize it with bus bar
transient and steady state flow current 2. Turn off DC supply to motor to run
- Current limited by sub-transient synchronous machine as synchronous
reactance in a short time decreases motor
transient value limited by transient 3. Reduce excitation to zero
reactance 4. Reverse field connection with DPDT
- Steady state value limited by switch
synchronous reactance 5. Slowly increase excitation in negative
No load voltage direction until machine shows sign of
Sub-transient Reactance =
oc falling out of step
No load voltage - Note field and line current
Transient Reactance =
ob Static test for determination of sub-
No load voltage transient reactance
Synchronous Reactance =
oa 1. Apply single-phase voltage to rotor of
- Where: synchronous machine at standstill
o a = steady state peak current - Field is short circuited by
o b = transient period peak ammeter
current 2. Rotate rotor manually so 2 positions of
o c = sub-transient period peak flux linking are apparent from induced
current field current
DETERMINATION OF Xd AND Xq 3. Let armature voltage and current of
1. Slip Test min induced field current be Vq and Iq
2. Maximum Lagging Current Test for 4. Let armature voltage and current of
Determination of Xq max induced field current be Vd and Id
3. Static Test for Determination of Sub- 5. Record readings for different applied
transient Reactance voltages

Slip Test
1. Check phase sequence and voltage
synchronous machine and bus bar
2. Remove field excitation
3. Connect RYB of machine to RYB of
bus bar with 3-phase VARIAC Slip Test
4. Start DC motor near to synchronous
speed
5. Apply small voltage with AC supply
o Voltmeter should fluctuate and
remain in rated value if slip is
small and rotation is correct
o Armature current also fluctuates Static Test
6. Increase AC voltage to make max STEPS:
current near equal to rated full load 1. Set output to 0
current of armature 2. Switch on DC supply
- Run dc motor close to alternator
synchronous speed but slower
3. Turn on AC supply
- Observe voltage and current
4. Adjust speed of DC motor to get max
swings on ammeter and voltmeter
5. Note max and min readings of voltage
and current
6. Do the same with different VARIAC
outputs
7. Adjust DC motor speed a little higher
than synchronous speed and take
similar readings above

CALCULATION OF Xd AND Xq SLIP TEST


V maxphase
- Z d=
I min
V max
- V maxphase =
√3
- X d=√ Z d−R2a
2

Vminphase
- Z q=
I max
V min
- V minphase =
√3
- X q=√ Z q −R2a
2

Typical Values:
Ra =0.75 ohms
X d=11 ohms
X q=8 ohms

CALCULATION OF Xd AND Xq STATIC


TEST (was not done in observation table)
-
Z d = {{V} rsub {max}} over {2* {I} rsub {min}
2}¿
- X d = sqrt {{Z} rsub {d} rsup { 2 ¿−R a
-
Z q = {{V} rsub {min}} over {2* {I} rsub {max}
2} ¿
- X q = sqrt {{Z} rsub {q} rsup { 2 ¿−R a
LAB 3: POSITIVE SEQUENCE, NEGATIVE i. Connect high resistance
SEQUENCE AND ZERO SEQUENCE in field circuit with full
REACTANCES OF AN ALTERNATOR applied voltage
d. Apply 3-phase short circuit at
A balanced 3-phase system only contains synchronous machine terminal
positive sequence current with connected ammeter
Negative sequence and zero sequence is e. Measure short circuit current
only found in unbalanced systems
DETERMINATION OF NEGATIVE
If system is unbalanced, all three can be SEQUENCE REACTANCE (X2)
found in the system - Obtained by running machine at rated
speed with low excitation
Vector sum of positive and negative - Negative sequence impedance (Z2)
sequence currents is zero V OS
- Z 2=
3∗I SC
In 3-phase 4-wire unbalanced system, zero - X 2 =Z 2 sinθ
1 o Where:
sequence current =
3∗neutral current

If there is no neutral leg, zero sequence


 θ=cos
−1
( P
V SC I SC)
current is zero 1. Make connections
- This means that delta connections has 2. Run machine at rated speed
no zero sequence reactance 3. Short circuit 2 phases of alternator
4. Connect voltage coil of wattmeter and
Magnitude of negative sequence current voltmeter at open phase
cannot exceed positive sequence current, if 5. Gradually increase excitation so short
that happens, resultant is reversed circuit current does not exceed rated
value
DETERMINATION OF POSITIVE 6. Note reading of voltage, current, and
SEQUENCE REACTANCE (X1) power
- Positive sequence reactance of
synchronous machine = direct axis DETERMINATION OF ZERO SEQUENCE
synchronous reactance at steady state REACTANCE (X0)
condition - Machine is driven at rated speed
- Positive sequence impedance - Connect all 3 phases in parallel
o Impedance by machine to the 1. Connect armature winding in parallel
flow of positive sequence 2. Run machine at rated speed
currents 3. Apply low voltage from VARIAC and
E measure voltage (V0) and current (I0)
o X1= taken by armature windings
I SC
3∗Z 0
1. Open Circuit Test - X 0=
a. Run machine at rated speed I0
b. Connect voltmeter and ammeter
as open circuit diagram]
c. Note readings
2. Short Circuit Test
a. Short circuit diagram
b. Run machine at rated speed
c. Apply low voltage to field circuit
so exciting current is small
LAB 4: DIELECTRIC STRENGTH OF LAB 5: EFFECT OF DIFFERENT SHAPE
TRANSFORMER COIL OF ELECTRODES ON DIELECTRIC
BREAKDOWN
Portable Testing Set
- Designed for periodical testing of BLOCK DIAGRAM
insulating oils from plants on site to
test dielectric strength of new oils
PROCEDURE
1. Place high voltage transformer unit
about 7 (?) away from control unit
2. Control unit is connected to supply
voltage
- Make sure that earth
connections are effective
3. Multiple point control switch is set at its
lowest point
4. Push button on control unit is pressed MEASUREMENT OF HIGH ALTERNATING
firmly for at least 5 seconds VOLTAGE
- If no breakdown, release button - Measurement is done with
with no delay sphere gaps
- Breakdown – indicated by  It measures peak value
continuous discharge across of voltage
the gap - Breakdown of spark gap occurs
 Bubbling oil in cell within a few microseconds once
indicates sudden voltage applied voltage exceeds static
drop breakdown discharge voltage
FROM SIMULATION: - Breakdown in gases will occur
 Usual breakdown is at 31.8 kV on peak low frequency AC
 At 29 kV, voltage increase is slowed votlages
down ARRANGEMENT OF SPHERE GAPS
 Oil/fluid should be changed after 3 1. Horizontal Arrangment
breakdowns  Used for sphere with diameters
<50 cm
 Used for lower voltage range
2. Vertical Arrangement
 Larger spheres
 Measure voltage with reference
to earth potential only
PROCEDURE:
1. Place high voltage transformer unit
about 7 (?) away from control unit
2. Control unit is connected to supply
voltage
 Make sure that earth
connections are effective
3. Multiple point control switch is set at its
lowest point
4. Push button on control unit is pressed
firmly for at least 5 seconds
 If no breakdown, release button
with no delay
 Breakdown – indicated by LAB 6: THE GAS ACTUATED BUCCHOLZ
continuous discharge across RELAY FOR OIL FILLED TRANSFORMER
the gap
Buchholz Relay
FROM SIMULATION: - Gas actuated relay
 Highest breakdown voltage is - Important protective device for oil
spherical immersed transformer
 Lowest breakdown voltage is pointed - Operates based on oil or gas pressure
 Electrodes does not require - Has hinged float and mercury switch
replacement when used (?) for both alarm and trip circuit
- Detects 2 faults; minor and major fault
- Minor Faults – alarm circuit will be
actuated to switch on buzzer
o Faults in core laminations
o Overheating windings
o Bad connections
o Low oil levels
- Major Faults – trip circuit will close due
to enormous amount of gas bubbles
o Internal short circuit between
phase and earth
o Phase to phase fault
o Insulation breakdown
- When oil level decreases, float switch
moves down to touch the contact
- For major faults, gases generated in
transformer bank rush to conservator
tank through Buchholz relay
o This reduces oil level which
affects the float switch
- If pressure is high in transformer tank,
trip circuit will activate

Valve V1 - Buchholz Relay to transformer


tank
Valve V2 - Conservator to Buchholz Relay
Valve V3 - Reservoir to transformer tank
Valve V4 - Oil release in the Buchholz Relay
(left side)
Valve V5 - Air release in the Buchholz Relay
(right side)

PROCEDURE:
1. Keep all front panel switches off
2. If pressure is present in relay, release
it by using air release and hand valve
of reservoir
3. Main power supply is connected at
back side of Buchholz relay
4. Close all valve except conservator
valve
5. Fill oil using foot pump by opening air
release valve little
6. Switch on power supply
7. Switch on buzzer toggle switch
8. Open Buchholz relay valve slightly and
decrease oil level manually below
particular level by carefully seeing oil
level in Buchholz relay.
- Alarm contact will be closed and
buzzer will operate in control
panel
9. When it alarms, close Buchholz relay
valve
10. Release Buchholz relay and reservoir
valve and collect oil to reservoir then
repeat steps 2-8
11. When done, open all valves except oil
release and air release valve to
release air pressure.

FROM SIMULATION:
Minor Faults
- When level is >100 c. cm., buzzer will
alarm
Major Faults
- When level is >300 c. cm., trip circuit
will bling

You might also like