Professional Documents
Culture Documents
College of Architecture
Submitted to:
Submitted by:
ARC 214
Part 1: General
2. The contractor will set up and complete all work required to accept and
Part 2: Materials
3. CHB
Page 2|9
Exercise 5: Masonry Specifications
Specification.
▪ Sand
5. Reinforcing Steel
Part 3: Execution
Installation
1. Ensure that the surfaces supporting the masonry work are clear of dirt and
other harmful materials and that they are completed with the correct lines
Page 3|9
Exercise 5: Masonry Specifications
2. The drawings will specify the horizontal and vertical spacing between
anchors that secure the masonry wall to the structural frame. You might
3. Assemble floors, walls, and other masonry structures using cavity and
that the edges are crisp, clean, and undamaged. Cut pieces as needed to
fit adjacent work and to create continuous patterns. If at all feasible, use
6. Install units with cut surfaces and, if at all possible, with concealed cut
edges.
7. Units shall be placed while the mortar is soft and plastic. Any unit disturbed
to the extent that the initial bond is broken after initial positioning shall be
allowances.
9. Avoid letting mortar droplets or other debris harm sills, ledges, and offsets
during building. Utilize covers laid on the ground and over the wall surface
to shield the base of walls from rain-splattered mud and mortar. Lost grout
Page 4|9
Exercise 5: Masonry Specifications
on face materials. When building, take care to avoid damaging door jambs
and corners.
10. Mortar should not be spread too far ahead of units, as it will stiffen and
loose plasticity, especially in hot weather. Mortar that has stiffened should
not be used. ASTM C270 requires that mortar be used within 2 ½ hours of
initial mixing.
and every (3) CHB layers horizontally for rebars using 9m length steel
reinforcement.
2. Reinforcement shall be clean and free from loose, rust, scales, and any
3. When a foundation dowel does not connect with the vertical core to be
2. Plan your wall layout in advance to ensure that surface bond patterns are
movement-type joints, offsets, and returns are all located precisely. Less-
Page 5|9
Exercise 5: Masonry Specifications
3. Lay-up walls with precise course spacing and coordination with other
4. Fill the space between hollow metal frames and masonry with mortar,
beneath bearing plates, beams, lintels, posts, and similar things, unless
otherwise specified.
of 10mm conforming to the current masonry codes standard for mortar joint
2. Install solid masonry units and fully-grouted hollow CMU with a filled bed
and head joint. Apply enough mortar to fill head joints and shove into place.
Make strike joints flush on surfaces that will be plastered, covered with
4. Remove any mortar that is protruding into the grouting cells or voids. Do
not allow mortar droppings to clog weep holes. Mortar should not be used
5. Remove any masonry components that were disturbed during the laying
process; clean and reset in fresh mortar. Avoid pounding jamb corners to
Construction Stability
1. Provide and install bracing that will ensure stability of masonry during
construction.
2. Allow 16 hours after completing masonry columns and walls to place floor
sections.
professional Engineer.
6. Formwork shall not be removed until the reinforced masonry member has
cured enough to support its own weight and additional loads during
construction.
7. Allow at least the following time after completion of the member to remove
shores or forms, if proper curing conditions were attained during the curing
period:
Page 7|9
Exercise 5: Masonry Specifications
Grouting
reinforcement.
2. Do not place grout until entire height of masonry to be grouted has attained
should be poured to within 1-1/2 inches of the initial pour's top course. Prior
to grouting, lay the masonry units and the reinforcement for the second
pour section once the grouted masonry has cured. If more pours are
Cleaning
1. When mortar is thoroughly set and cured, clean masonry by removing large
chisels.
2. Use a sample wall panel to test cleaning techniques; for comparison, leave
Page 8|9
Exercise 5: Masonry Specifications
masking agent to shield nearby stone and non-masonry surfaces from the
cleaner.
5. Ensure that the unit masonry work is free of damage and deterioration at
*End of Section*
Page 9|9