Professional Documents
Culture Documents
➢Burst event
• Latest Event Time (TL): The allowable occurrence time or the latest
event time is by which an event must occur to keep the project on
schedule
• Denoted by L2
• Earliest Start Time (EST): The earliest start time of an activity is the
earliest time by which an activity can commence
• Equal to TE
• For the activity 2-3, EST id E2
• Earliest Finish Time (EFT): Earliest time it can finish the task
• EFT=EST+ Duration of the project
• Latest Finish Time (LFT): is the latest time by which an activity can be
finished without delaying the completion of the project.
• LFT=Latest expected time of head event
• For activity 2-3, LFT=L3
• Latest start time (LST): Latest time by which an activity can be started
without delaying the completion of the project
• LST=LFT-duration of the project
Slack and Float
• Slack: denotes the flexibility range within which an event can occur
• It is the difference between earliest event time and latest event time
• L2-E2
• Float: The range within which activity start time or its finish time may
fluctuate without affecting the completion of the project.
• Total Float: The time spent by which the starting or finishing of an
activity can be delayed without delaying the completion of the
project
• Total float=LFT-EFT or LST-EST
• Free Float: Difference between earliest finish time and earliest start
time of its successor activity
• Free float = EST(Successor)-EFT (Present activity)
• Independent float : It is amount of time an activity could be delayed if
preceding activities finish at their latest and subsequent activiy start
at their earliest.
• Free float – Tail event slack
• When the project begins, the building of the internal components for the device (activity A)
and the modifications that are necessary for the floor and roof (activity B) can be started.
The construction of the collection stack (activity C) can begin once the internal components
are completed and pouring of the new concrete floor and installation of the frame (activity
D) can be completed as soon as the roof and floor have been modified.
General foundry example
• After the collection stack has been constructed, the high temperature
burner can be build (activity e), and the installation of the pollution
control system (activity F) can begin. The air pollution device can be
installed (activity G) after the high temperature burner has been built,
the concrete floor has been poured, and the frame has been installed.
Finally, after the control system and pollution device have been
installed, the system can be inspected and tested (activity H). (Source:
Quantitative Analysis for Management by Render et al. pp. 479)
Table
ACTIVITY Description
A - 2
B - 3
C A 2
• A) Construct CPM Network
D B 4
• B) Determine Critical Path
E C 4
• C) Compute Total Float
• and Free Float for F C 3
• non-critical activities G D, E 5
H F, G 2
CPM
• A) Network Architecture
C (2)
A (2) 3 4 F (3)
H (2)
E (4)
1 6 7
D (4)
B (3)
G (5)
2 5
CPM
• Determination of Critical Path
• 9 15 14
• ii) Phase I – det. Earliest start times (ES) of all nodes – Forward Pass
• Phase II – Det. Latest completion times (LC) of all nodes – Backward Pass
•
Critical Path in Network Analysis
• The notations used are
• Node 1: ES1 = 0
• Node 2: ES2= maxi=1 [ ES1 + D12] = max [ES1 + D12] = 0+2 = 2
• Node 3: ES3= maxi=1 [ ESi + Di3] = max [ES1 + D13] = 0+3 = 3
• Critical Path 2 4
• 1. ESi = LCi 2 4
0 C (2) 13
• 2. ESj = LCj 0 A (2) 2 4 F (3) 13
• 3. ESj – ESi = 1 E (4) 6
H (2)
7
15
15
• LCj – LCi = Dij B (3) D (4)
G (5)
3 5
3 8 Critical Path:
4 8 A-C-E-G-H
• One start node and one end node. One end node ensures that all
activities between the start and end node have been completed in
that time.
• The activities that fall on critical path are called critical activities
• The activity which does not lie on the critical path is called non-critical
activity.
• This non-critical activity may have some slack time the duration in the
activity can be extended without compromising with the
overall completion time of the project. Slack time can be a time in
which the start time of the project can be delayed without affecting
the completion of the project.
CPM
• Determination of Total float and free floats
• Total Floats (Slack Time): the amount of time that a task can be delayed without
affecting the completion date of the project
• TFij = LCj – ESi – Dij
• = LCj – (ESi + Dij)
• = LCj – ECij - Earliest completion time of the activity
• TFij = LSij – ESi
• LSij is the latest start of the activity i,j
• LSij = LCj – Dij
• Free floats: It is the amount of time that the activity completion time can be
delayed without affecting the earlies start time of the immediate successor
activities in the network.
• FFij = ESj – ESi – Dij
• = ESj – (ESi + Dij)
• = ESj - ECij
CPM
Activity (I,j) Duration (Dij) Total Float Free Float
(TFij) (FFij)
• Total float and Free floats
1-2 (A) 2 0 0
1-3 3 1 0
2-4 (C) 2 0 0
Critical Path:
A-C-E-G-H 3-5 4 1 1
4-5 (E) 4 0 0
4-6 3 6 6
FF <=TF
5-6 (G) 5 0 0
6-7 (H) 2 0 0
Application of CPM Technique (Managerial
Function)
• Planning: Planning is the most important project management tool, in
which the logic sequence of the jobs or activities to be performed, is
formalised. Gross requirement of materials, equipment and
manpower are also determined in this phase.
• Scheduling: is the determination time required for executing each
operation and the time order in which operation has to be carried out
to meet the plan objectives. It is the mechanical process of
formalising the planed functions, assigning the starting and
completion date to each activity of the project in such a manner that
the whole project proceeds in a logical sequence and in an orderly
and systematic manner
• Resource allocation: Allocation of resources is performed to achieve
the desired objectives. The resources means, labour, finance,
equipment, space. When these resources are limited, a systematic
method for allocation of resources become necessary.
• Controlling: is the process in which difference or deviation between
the plan and actual performances are reviewed after the project has
started. The analysis and correction of these deviations form the basic
aspect of control. In CPM, controlling is required not in respect of
physical progress of work, but also in respect of cost.
PERT
Time estimates
• Time is the most essential and basic variable
• A probabilistic approach is followed for time estimation
• 3 Time estimates are made for each activity
• Optimistic time estimates (to): shortest possible time in which an activity
can be completed, under ideal conditions. The time estimate represents
the time in which an activity or job can be completed if everything goes
well with no problems or adverse conditions
• Pessimistic time estimate (tp): it is the maximum time required to
complete the activity. The time estimate represents the time it might take
to complete a particular activity if everything went wrong and abnormal
situations prevailed.
• Most likely time (tm): it is the time which the activity will take most
frequently if performed a number of times. The time estimate lies
between the optimistic and pessimistic time estimates. Time estimate
reflects a situation where conditions are normal, things are usual and
there is nothing exciting.
Steps involved in PERT calculation
• Identify the events and activities and prepare a suitable network for
the given problem.
• Events are numbered in ascending order from left to right
• Obtain the various time estimates for each activity. They are most
likely (tm), the pessimistic (tp), and optimistic (to) estimates.
• Compute the expected time (te) for each activity
te = to+4 tm + tp
6
• Using the expected activity time estimate, determine the earliest event time (TE)
and the latest event time (TL) for each event
• Compute the float for each activity. The activity with zero floats are
the critical activities. Determine the critical path through the critical
activities.
• Find the total duration of the project by adding the duration of all the
critical activities
• Find variance of the time estimates of all activities.
𝑡𝑝 −𝑡0 2
• Variance of an activity=
6
• Variance of the project duration (𝜎 2 ) =
𝑠𝑢𝑚 𝑜𝑓 𝑣𝑎𝑟𝑖𝑎𝑛𝑐𝑒𝑠 𝑜𝑓 𝑡𝑖𝑚𝑒 𝑒𝑠𝑡𝑖𝑚𝑎𝑡𝑒𝑠 𝑜𝑓 𝑎𝑙𝑙 𝑐𝑟𝑖𝑡𝑖𝑐𝑎𝑙 𝑎𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠
• Find the probability of finishing the project on some fixed target by
using the table of normal distribution. The value of Z is obtained by
the equation
• Z=Due date- Expected date of completion
𝜎
Where 𝜎 = 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑑𝑒𝑣𝑖𝑎𝑡𝑖𝑜𝑛𝑛 𝑜𝑓 𝑡ℎ𝑒 𝑐𝑟𝑖𝑡𝑖𝑐𝑎𝑙 𝑝𝑎𝑡ℎ
= (𝑠𝑢𝑚 𝑜𝑓 𝑣𝑎𝑟𝑖𝑎𝑛𝑐𝑒𝑠 𝑜𝑓 𝑡ℎ𝑒 𝑎𝑐𝑡𝑖𝑣𝑖𝑡𝑦
Application of PERT
• Project planning: To identify all the important events/activities which are
essential for completion of the project
• Time estimation: Estimates of the time required to perform each network
activity are made by incorporating the time required for completing each
of the activities in the network.
• Scheduling: The scheduling computation gives the earliest and the latest
allowable start and finish time for each activity. Also to identify the critical
path through the network.
• Resource allocation: The feasibility of each schedule must be checked
concerning manpower and equipment requirements
• Project control: When the network plan and the schedule have been
developed to a satisfactory extent, they are prepared to final form for use
in the field. The project is controlled by checking progress against the
schedule, assigning and scheduling manpower and equipment, and
analysing the effects of delays
PERT and CPM
• In PERT, emphasis is given on events while in CPM emphasis is given to
activities
• In CPM, time estimates for the completion of activities are with a fair
degree of accuracy while in PERT- time estimates are not so accurate and
definite
• In CPM, cost optimization is given prime importance. The time duration for
completion depends on cost optimization. In PERT, it is assumed that cost
varies directly with time. Time is the controlling factor
• PERT is a probabilistic model with uncertainty in activity duration while
CPM is a deterministic model with well-known activity times based on past
experience
• PERT is used for repetitive jobs while CPM is for non-repetitive jobs
• PERT is used for planning and scheduling research programs while CPM is
used for construction and business problems
Importance of CPM and PERT
• Helps the management to concentrate their attention to the critical
activities and their completion in time
• Provides the best way of planning and scheduling a project
• Gives complete information about duration, slackness etc of activities
• Suggests areas for increasing efficiency and reduction of costs
• Helps to formulate new schedules when the existing schedules
cannot be met
• Minimises delay in completion of the project
Disadvantages of network techniques
• The realistic time estimates are not obtained
• It is not easy to develop a clear logical network in some cases
• The level of network details cannot be detrmined properly in some
cases. The level of details varies from planner to planner and depends
on the judgement and experience
• Trained personnel in the network methodology is necessary but it is
lacking in many managements