WAREHOUSE - ESTIMATION WORKS

Project : - Proposed Warehouse


Our scope : Fabrication, supply & Installation of steel structure (As per the client drgs.)
Client : Mr. Mahmood Ashoor
Painting : Two coats of painting for primary steel.
Secondary steel shall be pre-galvanized.
*NOTE :- Any type of civil works / Roof & wall sheeting / Authority approvals - excluded from our scope.

S.NO ITEM DESCRIPTION LENGTH QTY UNIT WT. TOTAL WT.


mm Nos Kg/m Kgs.
1 Main cols. - HEA 300 11000 28 88.3 27196.40
2 Base plate - 25thx300 450 28 58.9 742.14
3 Wind cols. - IPE 300 11400 4 42.2 1924.32
4 Wind cols. - IPE 300 12300 2 42.2 1038.12
5 Base plate - 25thx300 450 6 58.9 159.03
0.00
6 Main Rafter - IPE 400 11400 28 66.3 21162.96
7 Rafter Knee support - IPE 400 650 14 66.3 603.33
8 Column Knee support - IPE 400 850 14 66.3 788.97
9 Opening column, IPE 270 4000 8 36.1 1155.20
10 Opening Beam, IPE 270 7500 4 36.1 1083.00

11 Wall bracing, CHS 114.3X4 7850 80 10.9 6845.20 << Roof framing
12 Roof bracing, CHS 114.3X4 8000 40 10.9 3488.00
13 Roof bracing, CHS 114.3X4 7600 20 10.9 1656.80
14 Roof struts, CHS 114.3X4 99000 5 10.9 5395.50

15 Purlins, C 202x2.7 TH 99500 20 7.19 14308.10


16 sleeves, C 202x2.7 TH 835 280 7.19 1681.02
17 Sagrods , 12 dia 1350 235 0.9 285.53
18 Flange braces, L50X50X5 950 560 3.77 2005.64
19 Cleats, pl 6thx100 280 280 4.71 369.26

20 Girts, C 202x2.7 TH 99500 22 7.19 15738.91 << Wall framing


21 sleeves, C 202x2.7 TH 835 310 7.19 1861.13
22 Sagrods , 12 dia 1350 280 0.9 340.20
23 Flange braces, L50X50X5 950 620 3.77 2220.53
24 Cleats, pl 6thx100 280 310 4.71 408.83
25 Wall struts, CHS 114.3X4 9900 6 10.9 647.46

26 Connections & bolts (7%) 7917.39


Total Steel wt. = 121,022.97 Kgs.

RM=3.5
COSTING : - P=1
1 Steel Wt. (121 MT.) 786,500.00 F =1
SI=1.0
Landing cost= 786,500.00 aed 6.5

Profit (40%) as advised by Mr. Farhan = 1,101,100.00 aed