You are on page 1of 6

Control and Regulation of Electrodes in an

Electric Furnace from a FMEA


Blanca Rodríguez**, Joaquín Santos*, Miguel Strefezza*, Leonardo Contreras*
*Universidad Simón Bolívar, Departamento de Procesos y Sistemas. Sartenejas, Baruta, Edo Miranda, CP1080
Venezuela (Tel:+58-212-906-3319; e-mail: jsantos@ usb.ve; strefeza@usb.ve; leocon@usb.ve)
**Siderúrgica del Orinoco Alfredo Maneiro, Puerto Ordaz, Venezuela (e-mail:
brodriguez@sidor.com)

Abstract: Some steelmakers companies use Electrical Arc Furnaces (also well-known as Fusion Furnaces) for
the liquid steel fabrication, Sidor is one of them. The efficiency in the furnace will depend on how it is operated
and also on the regulation processes during the calibration adjustment of the electrodes when they are moving
up and down. The correct calibration control loops for the electrodes movement, helps to reduce its wear away,
also reduce the wearing down of the refractory material and help to improve the use of the electrical energy.
The overall contribution of these three aspects is to reduce manufacturing costs. From a maintenance
perspective and starting with a FMEA (Failure Mode and Effects Analysis), a new regulation approach was
developed to obtain a better control of the Sidor Furnace named 1, this was achieved establishing a regulation
according to profiles and load regulation, from alternating electric current to impedance factor.
Keywords: Control, electrodes, furnace, FMEA, maintenance, melting.

valve, see Fig. 1. Every electrode has its own PLC dedicated to
1. INTRODUCTION
create the regulation of the close loops circuit controlling each
An electrical arc furnace (EAF) is a furnace that heats charged one of the electrodes move up and down automatically for
material by means of an electric arc and produces the fusion or regulation of the arc. When a stable regulation is achieved
melting process transforming the received electrical energy, into during the up/down process, this contributes to diminish the
heat (Astigarra 1995). The electrical energy comes from a electrodes wear, also the refractory material will wear in a
network of high voltage alternating current that arrives into a uniform way, which extends its useful life in service. The
main transformer and from there goes to the secondary one and stability generates three more benefits, extend the life of
ended up feeding the electrodes. Three electrodes are arranged refrigeration panels, reduce electrode broken rate during
upon the refractory-lined vessel containing the charge and water- operation and save electrical energy consumption.
cooled, and covered with a retractable roof, through which the
electrodes enter the furnace. The electrical arc between Current Transformer Yokogawa
electrodes jumps going through the load, all this causes that each A
Level 2
electrode in an alternative mode became cathode and anode., the Measurement
mA ABB PC Regulation

charge material is directly exposed to the electric arc, and the transformer Voltage transformer

current in the furnace terminals passes through the charged * * V


PLC-Modicon

material. 3
mA ABB

Rack PLC – Room


2 1
Carry
In order to guarantee the operation of a system is necessary to electrode
mast
Level 1 – PLC

Rack PLC – Room


have their components working correctly (Smitth, 2001), using
this approach a model to regulate and set up the electrical arc
furnace was considered. The methodology of Failure Mode and Servo-valve
Effects Analysis (FMEA) was used to support the model. This
methodology help to verify any component on the system that * The same arrangement
In
Out
may fail through any one of the failure mode established. The For electrodes 2 and 3
Circuit

development was done taken the Electrical Furnace 1 as pilot Hydraulic


cylinder

plant. Also it is necessary to understand how combining, the


electrodes regulation system, controlling the hydraulic power Figure1. Functional diagram of the electrode regulation system
system that move the electrodes, and understanding the influence
of the refractory material, it is possible to contribute with the 2. MAINTENANCE MODEL FOR THE ELECTRODES
furnace performance. The tilting process of the furnace, as well REGULATION
as the opening and closing of the roof, and the up/down
movement of the electrodes, all are done using a hydraulic
power system. The electrodes are automatically raised and The FMEA is applied to the components and system showed in
lowered by a positioning system, which use hydraulic cylinders. figure 1. First step is to gather the related technical information
The control is done with PLCs acting on the hydraulic servo- about systems and components, from this point the equipments
are arranged in systems, set., subsets and components, the next
step is to classify the equipment in four type of categories: • Over duty failure or over load failure
hydraulics, mechanics, electrics and electronic. Every
component is identified with a potential and effect failure mode,
subsequently the severity and potential consequences are Table 2. Components with tendency to fail
established, identifying potential causes, determining occurrence ZONE: Cylinders to up/down electrodes F1,F2,F3
SYSTEM Electrodes movement regulation
and calculating criticality (Crespo, 1995). Combining criticality SET Hydraulic power station
value with failure severity a flowchart is developed to be used as COMPONENTS FAILURE CRITICALI FREQUENC C* INDE
MODE TY Y F X
a tool for taking decisions, see Fig. 2. In figure 2, criticality 1 do (C) (F)
not stop production, criticality 2 it is not fixable but is not FIXATION BASE LOSE RESTRAIN 3 2 6 3
DEFORMATION 5 1 5 4
affecting the production, criticality 3 affects the production, 4 1 4 5
criticality 4 stop production or will affect it; criticality 5 stop HYDRAULIC OIL LEAK 1 1 1 8
CYLINDER ROD SCRATCH 1 1 1 8
production. DEFORMATION 4 1 4 5
HOSES AND LEAKS 1 1 1 8
FITTINGS WEAR OUT 1 1 1 8

The intention to group the failure modes is to identify and


analyze all possible failure modes in order to show unusual
failures which can happen unnoticed in certain occasions. The
potential consequences when a failure appears, is analyzed
through brainstorming sections with the team work.

The consequences are evaluated in occurrence terms; this one is


defined as the probability that a cause in individual happens
resulting in a failure mode during the operational life of the
system or equipment. The table 3 shows how are the evaluation
criterion and the occurrence classification. Those cases where
intermediate values are obtained, the immediate one superior is
assumes. When the failure probability was not known, an
occurrence with value 10 was taken.

Table 3. Criterion of evaluation and classification for the


Figure 2. Procedure to determine failure severity. occurrence of the failure mode.
ZONE: Cylinders to up/down electrodes F1,F2,F3
The failure frequency is associated with two sources of SYSTEM Electrodes movement regulation
information, one is the manufacturer information upon suggested SET
COMPONENTS FAILURE
Hydraulic power station
CRITICALITY FREQUENCY C*F INDEX
replacement before a failure occurrence and the other comes MODE (C) (F)
FIXATION BASE LOSE 3 2 6 3
from the historical data collected, considering interruption times RESTRAIN 5 1 5 4
and MTBF (medium time between failure) statistical analysis. A DEFORMATION 4 1 4 5
HYDRAULIC OIL LEAK 1 1 1 8
guide to establish a criterion to ponder the frequency failure is CYLINDER ROD SCRATCH 1 1 1 8
DEFORMATION 4 1 4 5
shows in Table 1. HOSES AND LEAKS 1 1 1 8
FITTINGS WEAR OUT 1 1 1 8
Table 1. Guide to ponder frequency failure
CLASS PERIOD GRADE Beside the classification of the occurrence is also necessary to
VERY HIGH LESS THAN A MONTH 5 value the risk. The first step to analyze the risk is to quantify the
HIGH BETWEEN ONE AND THREE MONTHS 4
MEDIUM BETWEEN THREE AND SIX MONTHS 3 severity of the effects. The effects are quantified in a certain
LOW MORE THAN SIX MONTHS 2 scale and for this model the scale goes from 1 to 10, being level
NEGLIGIBLE MORE THAN A YEAR 1
10 the most severe and level 1 the less severe. It is assumed that
In order to determine in a greater scope which component or all the effects will take place when the failure mode happens;
equipment are susceptible of a failure with a high impact in the therefore the most severe effect has precedence when the
system operation, an analysis is done. The most susceptible potential risk is evaluated. The table 4 shows the evaluation
equipment to failure will be directly related to the criticality and criterion and the severity classification proposed in this model to
the failure frequency. An example resulting from this type of value the failure effects.
analysis is showed in table 2.
In order to determine severity it must be taken into account, if
The failure modes were established in five categories: the failure mode interrupts or not the operation, if it hits the
quality of the product, if it happens with previous warning or
• Total failure not, and something very important: how it has impact in the safe
• Partial failure operation of the equipment, the safety of the operators and the
• Intermittent failure impact on the environment (ILAFA, 1988), (SIDOR, 2003),
• Failure occurrence before expected (MMI, 1986).
Table 4. Criterion of assessment and classification level for the 1999), (Granela, 2000), (Huerta, 2001). This number can be
severity of the failure effects. expressed as:
Effect Effect severity for the FEMA design Level
PRN =S*O*D (1)
Dangerous The failure affects the safety operation of the 10 Where: S = Severity
without process, occurred without a warning, and can cause O = Occurrence
warning injuries to the operator. D = Detection
Dangerous The failure affects the safety operation of the 9
with warning process, occurred with a warning and can cause
injuries to the operator. Table 6 shows the application of FEMA to one device of the
Very high The failure affects the safety operation of the 8 electrodes regulation system, the servo valve that commands the
process, and occurred with a warning. cylinder movement of the carry electrode mast. In table 6 the
High It does not affect the operation but it works with a 7 PRN of each one of the failure mode observed, facilitate the user
smaller performance to the design or to the plant
requirement.
how to identify the failure modes with greater risks.
Moderate Minor interruptions on the process, with some 6
functions diminished The priority risk number point out the most serious risks and
Low Minor interruptions on the process. 5 lead to the remedial action, also give a course of the aspects that
Very low Process interruptions and very some anomalies 4 are due to review. The PRN scale for this model goes from 1 to
regarding aspect, noise, vibration, etc.
Minor Process interruptions and very few anomalies 3 1000. The data value average obtained was 106 and three groups
regarding aspect, noise, vibration, etc. were created: low (105 or less), average (106 to 500) and high
Very minor Without interruptions but some anomalies regarding 2 (501 or higher).
aspect, noise, vibration, etc.
None The failure effect has not effect. 1
3. CONTROLING THE ELECTRODE MOVEMENT
After having the failure effects defined by levels, it is necessary The electrodes have three independent controllers type PID for
the evaluation criterion and the classification for detecting the each elevation system with the purpose of controlling the
failure mode or failure cause. The table 5 shows this. electrical arc. The control is made through the reading of the
variables of current and tension on the secondary one of the
Table 5. Criterion to evaluate and classified failure cause transformer.
Detection Criterion for detection of the failure mode or failure cause Level
Almost They are not known ways to detect the failure mode or the failure 10 The automatic control movement is done in two forms: the first
impossible cause. is controlling electrical current and the second is controlling by
Very Very remote possibility that with the actual checking and 9
remote controls, it will be possible to detect the failure mode or the calculated impedance, both techniques have advantages. The
failure cause. first is used when the fusion process is in liquid state, in this
Remote Remote possibility that with the actual checking and controls, it 8 stage is advisable to place directly as a control variable the
will be possible to detect the failure mode or the failure cause.
Very low Very low possibility that with the actual checking and controls, it 7 electrical current, since the electrodes have less disturbance with
will be possible to detect the failure mode or the failure cause. the contact surface. The regulation by impedance is advisable to
Low Low possibility that with the actual checking and controls, it will 6
be possible to detect the failure mode or the failure cause. use during the first stage of fusion, since this is very unstable
Moderate Moderate possibility that with the actual checking and controls, it 5 due to the fact of this is the beginning of melting the scrap-metal
will be possible to detect failure mode or failure cause. and a more greater precision is needed to have, then the control
Moderately Moderately high possibility that with the actual checking and 4
high controls, it will be able to detect the failure mode or the failure variable is the impedance, this one is calculating in each cycle of
cause. the PLC making the controller adjustment to this variable.
High High possibility that with the actual checking and controls, it will 3
be able to detect the failure mode or the failure cause.
Very high Very high possibility that wit the actual checking and controls, it 2 A control technique was developed combining two types of
will be possible to detect the failure mode or the failure cause. regulation:
Almost Almost total certainty that with the actual checking and controls, 1
total it will be able possible to detect the failure mode or the failure
certainty cause. • Regulation by impedance: which is used in the first stage of
the fusion or after some interruption on the furnace operation
After the effects and severity have been determined, the occurred. The impedance is calculated in each cycle of the PLC
following step is to identify the causes of the failure mode. The (20mseg) through the reading of electrical current and tension in
identification must begin with the failure modes producing the the transformer.
more severe effects and the causes are specific things in terms of
which it must be corrected or be controlled. With the FEMA, is • The regulation by electrical current: This is activated
assumed that the systems have suitable engineering design considering that the solid load of the furnace has been fused and
(Mannesman, 1971), (Elonka, 1986). is in “flat bath”. It is Also used when being selected the
regulation by impedance in anyone of the three phases, a
The maintenance model using FEMA will need the priority risk discrepancy greater to twenty (20) percent is obtained in the
number (PRN) which is the mathematical product of the impact tension of the secondary one with respect to the theoretical, the
of a group of effects (severity), the probability of causing the Table 6 values, were calculated according to the TAPs (on-load
associated fault with those effects (occurrence) and the ability to tap changer) position during the transformer operation. When the
detect the fault before this gets to happen (detection) (Pérez et al,
Table 6. Example of FEMA applied to servo valve phase 1
EQUIPMENT SAP FUNCTION POTENTIAL FAILURE ACTUAL EVALUATION FIT AND REFINING
DESCRIPTION NUMBER FAILURE MODE FAILURE FAILURE HECKING O S D PRN
EFFECT CAUSE
82224 To transform or to 1. External leaks 1. Under yield in 1.Misalignment in 1. Leaks 8 3 1 24 1. Fitting
SERVO VALVE PHASE 1 change the the fluid connectors, inspections. 2 10 9 180 adjustment
analogous entrance proportion breakage of 7 4 1 28 even without
signal into a pipes 1 4 1 4 leak
hydraulic 2. Internal leaks 2. Does not stay in 2.Wearing down 2. Displacement 2 8 8 128 2. Change of
exit (flow or the set point in the verification 2 10 10 200 servo valve
pressure). In order hydraulic block of the servo 3.Adjustment of
to give to a high one the hydraulic
degree of 3. Mechanical set 3. Does not stay in 3. Out of setting 3. Verification set point
exactitude or point moved the set point of the 4.Adjusment of
precision in the mechanical the electronic
movement of the set point of set point
arms carrying the the servo 5. Change the
electrodes. valve fluid filter on
4. Electronic set 4. Does not stay in 4. Out of setting 4. Verification the servo
point moved the set point of the entrance
electronic set 6. Take the
point of the viscosity of
servo valve the fluid
5. Dirt in the 5. The internal 5. insufficient 5. Verification corresponding
nozzles system spool with filtration of the of the filter one to use in
displacement hydraulic fluid condition the servo
problems valve
6. The internal 6. Problems in 6. viscosity of the 6. periodic
spool does the route of hydraulic fluid control of the
not move the internal below the hydraulic
spool specified fluid
viscosity

discrepancy disappears the regulation became again by this was done due to the fact this action move the system
impedance. towards the instability so it was decided not to use it. The control
became a PI controller; these parameters are subject to changes
The use of each technique is going to depend on the load profile and will depend on the performance of the furnace since the
done to the furnace. In Sidor two type of load were conditions change, as consequence of mechanical replacement or
predetermined: one is 100% of HRD (direct reduction iron) and the alignment of a new electrode carrier. In cases where changes
the other is 80% of HRD and 20% of scrap iron. The table 7 occurred due to maintenance activities, it is necessary to check
shows the selection of the regulation type depending on the type the parameters and make new adjustments.
of load. According to the type of regulation: impedance or current, the
wished operation points change according to the position of the
Table 7. Profiles to select the type of regulation transformer TAP as seen in table 9 and 10.

REGULATION REGULATION PROFILE CONDICTIONS In order to guarantee protection to the transformer due to the
TYPE TO. OR
DELAYS different condition during the furnace operation, two (2) levels
REGULATION
LOAD TYPE Load 80 –
20
Active energy less or equal to eleven
(11) MWh
of protection in the secondary one exist:
BY Load 100 % Active energy less or equal to one (1)
IMPEDANCE MWh
INTERRUPCTION Less than an Last: two (2) extra MWh to the active
· Instantaneous protection
hour delay energy at the interruption moment · Time-lag protection
More than an Last: eight (8) extra MWh to the active
hour delay energy at the interruption moment (cool
furnace).
Table 8. Parameters of Control, by fusion stages
LOAD TYPE Load 80 – 20 Active energy higher to eleven (11) STAGE CONDITION PROPORTIONAL INTEGRAL DERIVATIVE
REGULATIÓN MWh (P) (I) (D)
BY Load 100 % Active energy higher to one (1) MWh
ELECTRICAL First of Energy F1: 2.2 F1: 0.04 All = 0
CURRENT INTERRUPCTIÓN Less than an Last: from two (2) MWh consumed Impedance smaller to 1 F2: 2.4 F2: 0.08
hour delay alter the interruption. MWh F3: 2.3 F3: 0.04
More than an Last: from eight (8) MWh consumed Second of Energy F1: 1.6 F1: 0.08 All = 0
hour delay alter the interruption. Impedance greater to 1 F2: 2.0 F2: 0.04
MWh and F3: 2.2 F3: 0.01
regulating
by
4. RESULTS Impedance
First of Current Regulating F1: 2.5 F1: 0.01 All = 0
According to the strategy of control used in the melting stages by Current F2: 2.9 F2: 0.0095
different parameters for tuning the control loops were founded. and TAP F3: 2.6 F3: 0.035
different
These parameters can be selected depending on each stage, from one (1)
which is defined based on the consumed energy (MWh). Second of Regulating F1: 2.7 F1: 0.008 All = 0
Current by equal F2: 2.5 F2: 0.008
Current and F3: 2.6 F3: 0.005
In table 8 the parameters values for control of each one of the TAP to one
PID depending on the fusion stages are showed. The values for (1)

the derivative action of the PID are in zero for all the selections,
Table 9. Set point values for Regulation by Impedance. which is an integration of the values of energy sample in each
cycle of the PLC shows that did not happen interruption during
TAP WISHED WISHED WISHED this tap since the line is ascending in continuous way.
IMPEDANCE IMPEDANCE IMPEDANCE
PHASE 1 PHASE 2 PHASE 3
(MOHMS) (MOHMS) (MOHMS) Table 10. Set values Point for Regulation by Current
1 9.987 9.987 9.956 TAP Wished current Wished current Wished current Phase 3
2 9.580 9.580 9.580 Phase 1 (kAmp) Phase 2 (kAmp) (kAmp)
3 9.800 9.800 9.800 1 61.8 62.0 61.0
4 8.726 8.726 8.726
2 63.0 63.0 63.0
5 8.726 8.726 8.726
6 8.626 8.534 8.760 3 63.0 63.0 63.0
7 7.695 7.695 7.695 4 64.0 64.0 64.0
8 7.695 7.695 7.695
5 64.0 64.0 64.0
9 7.587 7.500 7.695
10 7.160 7.160 7.160 6 67.0 67.0 66.0
11 7.160 7.160 7.160 7 66.0 67.0 66.0
12 6.772 6.682 6.772 8 66.0 67.0 66.0
13 7.000 7.000 7.000
9 66.0 67.0 66.0
14 7.000 7.000 7.000
15 8.000 8.000 8.000 10 66.0 67.0 66.0
16 8.000 8.000 8.000 11 68.0 67.0 66.0
17 8.000 8.000 8.000
12 70.0 70.0 68.0
18 8.000 8.000 8.000
19 8.000 8.000 8.000 13 70.0 70.0 70.0
20 8.000 8.000 8.000 14 70.0 70.0 70.0
21 8.000 8.000 8.000 15 52.0 52.0 52.0
16 52.0 52.0 52.0
They protection have been developed by software, programming 17 52.0 52.0 52.0
the PLC controlling the electrode regulation. 18 50.0 50.0 50.0
19 48.0 48.0 48.0
The instantaneous protection in each cycle of the PLC (20 20 46.0 46.0 46.0
miliseg) takes a sample from current and it is compared with the 21 44.0 44.0 44.0
established value on each TAP of the transformer, if the current
is equal or greater to the established, an alarm is generated.
The Figure 4 shows the TAP values, power and consumed
The time-lag protection makes the time-lag to 3 seconds, to energy, which is an integration of the samples values of energy
compare the real current with the established one in the time-lag in each cycle of the PLC, for a tap with a load of 100% HRD. In
table of currents associated to each TAP and, if this is equal or this case after one minute the move to TAP 1 and the control by
greater to this an alarm is generated. electrical current is established.

When the alarm of instantaneous protection is generated the 125


19
566
electrodes change to work from automatic way to manual and
raise at 100 % of the maximum velocity until reaching the 100
16
472
electrical current value of reestablishment.
90 12
When the generated alarm is the time-lag also the electrodes 378
POWER
change to manual way allowing these to rise until a value of (KW)
284 10
reestablishment of the electrical current, which will not let to 60

extinguish the arc in the phases. The adjustment of these TAP ENERGY
(KW)
protections occurred to be a commitment between the protection 190 40 6

of the transformer and the stability of the electrical arc, because


if the phase rises until reaching a very low current, then the arc is 96 20 3

destabilized, for this reason the electric current was adjusted to


avoid the electric arc be extinguished . The values of ENERGY
(MW/H)
POWER
(MW) TAP

protection, instantaneous as much time-lag and the values of 0:56 1:06 1:16 1:26 1:34 1:43 1.53 2:03 TIME(HOURS)

reestablishment depend on the position of the TAP of the


Transformer.
Figure 3. Loads 85 % HRD. 55 min. Power ON; Power
The Figure 3 shows the TAP behaviour of the transformer Average of 98 MW; Consumed Energy 90MW/h. Total Load
throughout the tap values, for a load with 85% of HRD and the 212 metric tons.
rest is scrap iron. The power shows the typical behaviour of the
melting stage and the flat bath stage. The consumed energy,
111
minutes by tapping, which gave one additional tapping in a 24
30
hours operation program, this was achieved increasing the
average power from 90MW to 95MW and obtained through the
25
94 electrical arc stabilization on the meltdown bath. If the additional
tap achieved is quantified in terms of US$ this represent an
20 addition of 48,000 dollars to the production by day.
74
POWER
(MW)
142 114 27
15 55

119 96 24

TAP ENERGY
10 37 (KW/H)
96 76 19

POWER
(KW)
18 71 57
5 14

47 38 10
ENENGY POWER TAP
(KW/H) (MW) ENERGY
TAP
16:19 16:27 16:42 16:50 16:58 17:06 17:13 TIME (HOURS) (KW)
24 19 5

Figure 4. Loads 100% HRD.100MW Power average; 105 MW/h 12 8 3


Consumed Energy, 63 Power ON of min. Total Load 220 metric POWER ENERGY
tons. (KW) (KW) TAP

1:53 2:09 2:25 2:41 2:56 3:12 3:28 TIME (HOURS)


The Figure 5 shows a tap with interruption, the TAP variation is
noticed. The cut of the energy consumed that is the integration of Figure 5. TAP Transformer behaviour and the power before
the samples of energy taken in each cycle from the PLC, and the some interruption of the process
reestablishment of the power after the tap resumption. As it is
indicated in table 7 if the interruption of the process is less than REFERENCES
one hour the furnace is connected by impedance the first 2 MWh Astigarra, J. (1995). Hornos de arco Eléctrico para Fusión de
consumed and then it goes to be regulate by current, if the acero, Mc Graw Hill, 1.995.
interruption of the process is greater to one hour it will start Smith, D.J. (2001). Reliability Maintainability and Risk, editorial
ageing with impedance during the first 8 MWh consumed and Butterworth Heinemann, sixth edition.
then it goes to be regulate by current, all this guarantee the arc Crespo, G. (1995). Síntesis curricular.
stability, due to that ILAFA, (1988). INSTITUTO LATINO AMERICANO DEL
FIERRO Y EL ACERO. Tecnología de control Ambiental
5. CONCLUSIONS en la Industria Siderúrgica.
The main target of the present work was to design a model for SIDOR, (2003). SIDERÚRGICA DEL ORINOCO. El Modelo
the electrodes regulation using the FEMA methodology, this was Organizativo del Mantenimiento en Sidor y Servicios.
achieved. The regulation system is one of the most important Primera Edición.
steps on the steel melting process, the operation of this system MMI. (1986). MANUAL DE MANTENIMIENTO
impact directly in the life cycle of the electrodes, the refractory INDUSTRIAL, TOMO 1, compañía editora Continental,
consumption and the saving of electrical energy. When potential Decimocuarta edición.
failure modes in the system are eliminated, this produce benefits Mannesman, Deman (1971). Manual De Especificaciones De
in the short as much as in the long term of the overall operation. Operación De Hornos De Fusión Aceria De Palanquillas,
In the short term, it represents savings on the maintenance SIDOR.
repairs costs and the equipment downtime. The use of the FEMA Elonka, ]S. (1986). Equipos Industriales. Guía Práctica Para
help to support and reinforce, the continuous improvement of the Reparación y Mantenimiento. Mc Graw Hill.
systems, the use of the potential failure modes list, classified Pérez, E.J. and Delgado, A.(1999). Evolución del Mantenimiento
according to its probable effect on the product, will provide a de Equipos Eléctrico de A.T.,
document that has an open format to suggest actions that reduce http://www.esi2.us.es/ANT/ingenio/ingenio9/norcon.html
the risk. The FEMA help to detect failures where is necessary to NORCONTROL, February.
set some auto-correction activities or a slight protection is Granela, H.(2000). Experiencias en la Aplicación del
needed, also identifies failure modes known and the potential Mantenimiento Centrado en Confiabilidad.
ones, that could occurred unnoticed, it is an early detection for http://www.datastream.net/latinamerica/infostream/adjuntos/
initial failures with a minimum initial impact which can Congresos/Pon.%20Hugo%20EDITADA.doc
transform into important secondary failures, it provides a point Huerta, R. (2001). El Análisis de Criticidad, una Metodología
of fresh sight in the understanding of the functions of the system. para mejorar la Confiabilidad Operacional.
With the improvements detected in the implementation of the http://www.datastream.net/latinamerica/mm/articulos/6anali
model, specially in the control loops, the smelting time was sis.asp PDVSA. September.
reduced from an average of 65 minutes to an average of 60

You might also like