Tri‐State Generation and Transmission Association

2016‐2026 Transmission Plan


Southwest Weld Expansion Project

Project Sponsor: Tri‐State Generation and Transmission Association


Additional Project Participants:
Project Description: Construct approximately 49 aggregated miles of 115 kV and 230 kV
transmission lines with six potential load‐serving substations and/or
line taps.

Voltage Class: 230 kV


Facility Rating: 300 MW
Point of Origin/Location: JM Shafer
Point of Termination: Del Camino, South Kersey, Henry Lake
Intermediate Points: Davis, Colfer (Hudson)
Length of Line (in Miles): 49 miles
Type of Project: Other
Development Status: Under Construction
Routing:
Subregional Planning Group: CCPG

Purpose of Project: Load‐serving

Project Driver (Primary): Reliability


Project Driver (Secondary):

Estimated Cost (in 2014 Dollars): $112,000,000

Schedule:
Construction Date:
Planned In‐Service Date: 2018
Regulatory Info: CPCN filed 8/2014
Regulatory Date:
Permitting Info:
Permitting Date:

Contact Information: Chris Pink


Email cpink@tristategt.org
Phone (303) 254‐3339
Website Information Http://www.tristategt.org/transmissionPlanning/puc2627_Transmissi
onProjects.cfm
#
* #
*
#
* #
* # *
#
* #
*
#
*
#
* Highland Unc Cogen
#
* Unc Switch
Boomerang Kersey West
#
* Evans #
* #
*
Arrowhead Lake
ale - Weld Rosedale #
*
Rosed Kersey Kersey Tap

Weld - Fort St.Vrain


Wind Godfrey Sw #
* #
*
so r
South Kersey
#
* Lasalle
#
*
- Fort

Johnstown
#
* Milton #
*
Gilcrest
!
(
Box Elder 44kv - Tap
St Vra

#
*
Gilcrest 44kv - Lasalle 44kv
Neres Canal Box Elder

!
(
in

Fort Saint Vrain Vasquez #


*
#
*
Rattlesnake Ridge

!
(
Vasquez - Fort Lupton

Del Camino Switch


#
*
Del Camino (Up)
#
*
Ennis
Fort Lupton - Pawnee

#
* *Davis
# Colfer
Rinn Valley Hudson - Ft Lupton
#
*
Frederick
Davis Tap
Greenhouse J.m Shafer
Hudson
Ennis - Hudson
#
* Keenesburg - RMEC
#
* !
(
#
*
#
*
#
*#* *# #
*
Fort Lupton
Spindle Parkway - Fulton
#
*
RMEC
!
( #
*
Keenesburg

Dacono #
*
Green Valley - Keenesburg

Fulton

Erie Switch
Erie - Sipres Henry Lake - Sipres Erie - Hoyt Henry Lake - Story
#
* #
* *Sipres #
#
Brighton 34.5kv * *Lochbuie
#
Henry Lake

Platte Valley #
*United Power Solar #
# #
*
* Hanger 160 Solar * *
#
Bromley
#
*
Tri-State Generation
and Transmission
#
*
#
*
Station - Tri-State

Station - Other Utility !


( Project Feature 0 1.
25

Las t Update d:11/


20/
2015
2.
5 5
Mi
l
es
¹
Transmission Line - Tri-State Author:yk e vrop
Southwest Weld Transmission Line - Other Utility
Expansion Project Project Area
Tri
-State Ge ne rati
datatoai
onandTrans mi
dthe de ve l opme nt ofTri
ssi
-
onAs s oci
State proj
ati
ec
onprovi
de s GI
ts .Nous e r ofTri
S
-
State ’s GI
Sdataandmaps mays e l lanyporti onofthe inf
ormati on
Project Feature provi
acc
de d the re i
urac yor c
n. Tri
ompl
-State make s no w arrante e re gardi
e te ne s s ofthe dataandmaps .Us e rs s hal
ng
lre l
y
onlyuponprope r f i
el dve ri fi
cati
onofTri -State GISdata.

Doc
ume nt Path:\
\hqs tore \
ge os tore \
Produc
ts \
Syste mPl
anni
ng\
2016_PUC\
Maps \
MXD\
Ove rvi
e w _Southw e s tWe l
dExpans i
onProj
ect.
mxd
Southwest Weld Expansion Project

Due to large scale oil and gas development in Southwest Weld County and native load growth,
Tri-State is planning on constructing approximately 49 aggregate miles of 115kV and 230 kV
transmission lines to meet the forecasted demand of approximately 300MW within the next five
years. Six potential 115kV load-serving substations and/or line taps will be constructed by Tri-
State, while new 69kV transmission lines and substations will be constructed by United Power
for the project.