Professional Documents
Culture Documents
@@@@@@@@@@@@@@@@@@@@(JD)@@@@@@@@@@@@@@@@@@@@@@ (CORE-14)
(d) What is a second order determinant? or What is the determinant of order two?
(e) What is third order determinant? or Write a note on determinant of third order?
===≠===}===≠===}
(a) A determinant is a scalar value that can be computed from the elements of a
square matrix and encapsulates certain properties of the matrix.
(c) The minor of a determinant is the determinant obtained by removing the row and
column containing a particular element of the original determinant.
(j) The value of a determinant becomes zero when the rows or columns of the matrix
are linearly dependent, meaning one row or column can be expressed as a linear
combination of the others.
______________________
(i) What is a matrix ?
===≠===}===≠===}
(i) (i) A matrix is a rectangular array of numbers, symbols, or expressions
arranged in rows and columns. It provides a compact and organized way to represent
and manipulate data, making it essential in various fields like mathematics,
computer science, and engineering.
(ii) A scalar matrix is a square matrix in which all the diagonal elements are
equal, and all other elements are zero. It represents a scaling operation and is
commonly used in transformations and linear algebra operations.
(iii)
(a) A square matrix has an equal number of rows and columns.
(b) A diagonal matrix is a square matrix in which all non-diagonal elements are
zero.
(d) A scalar matrix is a diagonal matrix in which all diagonal elements are equal.
(f) A rectangular matrix is a matrix that does not have an equal number of rows and
columns.
(g) Comparable matrices are matrices that have the same dimensions and can be added
or subtracted element-wise.
(i) A singular matrix is a square matrix that does not have an inverse.
(iv)
(a) A zero or null matrix is a matrix in which all elements are zero.
(b) The transpose of a matrix is obtained by interchanging its rows and columns.
(c) The inverse of a matrix is another matrix that, when multiplied with the
original matrix, gives the identity matrix.
(d) The adjoint of a matrix is the transpose of the cofactor matrix of the original
matrix.
(e) Singular matrices are matrices that do not have an inverse, while non-singular
matrices are those that have an inverse.
______________________
Explain Within 75 words
---
1) Write short note on sub-matrix.
===≠===}
A sub-matrix is a matrix formed by selecting a subset of rows and columns from a
larger matrix. It retains the structure of the original matrix but may have fewer
rows and columns. In business mathematics, sub-matrices are useful for analyzing
specific subsets of data within a larger dataset. For example, in financial
analysis, sub-matrices can be used to isolate certain financial instruments or time
periods for focused examination and decision-making.
(i) **Function:**
A function is a relation between a set of inputs (domain) and a set of possible
outputs (range), such that each input is related to exactly one output. In business
mathematics, functions are commonly used to model various relationships, such as
cost functions, revenue functions, and demand functions, which help analyze and
optimize business processes.
____________________________________________
Chapter _4
Integration
______________________####
. Short - Answer Type Questions
___________@)
What do you mean by:
(a) Integration
(b) Integral
(e) Integrand
===≠===}===≠===}
(a) **Integration:**
Integration is a fundamental concept in calculus that involves finding the
accumulation of quantities over a certain interval. It is the reverse process of
differentiation and is used to compute areas, volumes, and other quantities by
summing infinitesimal contributions. In business mathematics, integration plays a
vital role in modeling and analyzing various aspects such as revenue, cost, profit,
and resource allocation.
(b) **Integral:**
An integral is a mathematical object that represents the accumulation of quantities
over an interval. It is denoted by the symbol ∫ and is used to find the total value
of a function over a specified range. Integrals have applications in diverse
fields, including physics, engineering, finance, and economics.
(e) **Integrand:**
The integrand is the function that is being integrated. It is the expression inside
the integral symbol and represents the quantity being accumulated or evaluated. In
business mathematics, the integrand can represent various quantities, such as
revenue functions, cost functions, or demand functions, depending on the specific
context of the problem.
(d) Polynomial in x
(vii) What is the formula for calculating time period when principal, simple
interest and rate o interest are given ?
(viii) What is the formula for finding the amount when interest is compounded
quarterly?
(iv) **Interest:**
Interest is the cost of borrowing money or the return on investment earned over a
specified period. It is typically expressed as a percentage of the principal amount
and is calculated based on the interest rate and the duration of the loan or
investment.
____________________________________________Chapter _6
Annuities
______________________####
. Short - Answer Type Questions
___________@)
Filled in the blanks
iv) If the installments of the annuity are payable at the end of 1, 2, ..., n years
from the present value, it is known as **Immediate annuity**.
vii) When annual payments continue until the happening of a certain event, it is
known as **contingent annuity**.
ix) Any periodical payment of a fixed amount made at a regular interval is called
**annuity**.
______________________
2. Answer in Two Sentences
===≠===}===≠===}
(i) **Annuity:**
An annuity is a financial product or investment vehicle that provides a series of
periodic payments or income over a specified period. It is typically used for
retirement income, insurance payouts, or structured settlements. Annuities can be
classified based on the timing of payments, such as immediate annuities, annuities
due, or deferred annuities.
(iv) Perpetuity
**Annuity Due:**
An annuity due is a type of annuity where payments are made at the beginning of
each period, such as monthly or annually. Unlike ordinary annuities where payments
are made at the end of each period, annuity due payments are made at the beginning,
resulting in slightly higher present value due to the time value of money.
**Sinking Fund:**
A sinking fund is a type of investment or savings account established to set aside
money regularly to repay a debt or fund a future financial obligation, such as the
replacement of a capital asset or repayment of a loan. It involves making periodic
contributions to accumulate a predetermined amount by a specific date, ensuring
financial stability and liquidity when needed.
**Perpetuity:**
A perpetuity is a type of annuity that continues indefinitely, providing a constant
stream of payments that never ends. It is characterized by regular payments that
continue indefinitely without a predetermined end date. Perpetuities are often used
for long-term financial planning and investment, providing a reliable source of
income in perpetuity.
**Contingent Annuity:**
A contingent annuity is an annuity where payments are contingent upon the
occurrence of a specific event, such as reaching a certain age, surviving a
critical illness, or achieving a milestone. Payments begin only when the triggering
event happens, providing a form of financial protection or income supplementation
in specific circumstances.
**Deferred Annuity:**
A deferred annuity is an annuity where payments are postponed or deferred until a
future date, allowing the invested amount to grow over time through interest or
investment returns. Deferred annuities are often used for retirement planning,
providing a source of income in later years when individuals may need it most.
**Immediate Annuity:**
An immediate annuity is an annuity where payments begin immediately after a lump-
sum investment or premium is made. The annuitant starts receiving regular income
payments without any deferral period. Immediate annuities are suitable for
individuals seeking immediate income upon retirement or payout of a settlement.
**Annuity Certain:**
An annuity certain is a type of annuity where payments are guaranteed to be made
for a specific period, regardless of the annuitant's lifespan. It provides a fixed
stream of income for a predetermined number of periods, ensuring financial
stability and income certainty for the annuitant.
**Amount of Annuity:**
The amount of annuity refers to the total value of all payments or cash flows
received or paid under an annuity contract. It represents the sum of all periodic
payments made or received over the life of the annuity, calculated based on the
annuity's terms, interest rate, and duration.
4. **Discrete Decision Variables:** LPPs often assume that decision variables can
take on continuous values, which may not always be feasible in practice, especially
in scenarios where decisions are discrete or binary.
1. **Identify the Objective:** The first step is to clearly define the objective of
the problem. Determine whether the goal is to maximize profit, minimize cost,
optimize resource allocation, or achieve some other specific objective.
7. **Write the Mathematical Model:** Combine the objective function and the
constraints to form the complete mathematical model of the linear programming
problem. The model should consist of the objective function, the constraints, and
any non-negativity constraints.
10. **Test the Model:** Test the formulated model using sample data or hypothetical
scenarios to verify its correctness and effectiveness in solving the problem.
Adjust the model as needed based on the test results.
3. What are the three major problems that can be solved using the linear
programming techniques. Discuss each of them briefly.
===≠===}
Linear programming (LP) techniques are versatile tools that can be applied to solve
a wide range of optimization problems in business mathematics. Three major types of
problems commonly addressed using linear programming techniques are:
In summary, linear programming techniques are powerful tools for solving a variety
of optimization problems in business mathematics, including resource allocation,
production planning, inventory management, and transportation logistics. By
formulating mathematical models that capture the complex interrelationships between
resources, constraints, and objectives, businesses can use LP techniques to make
informed decisions, improve operational efficiency, and achieve strategic goals.
**Primal Problem:**
The primal problem is the original linear programming problem that seeks to
maximize or minimize an objective function subject to linear constraints. It
involves decision variables, an objective function, and a set of linear
constraints. The primal problem aims to find the optimal solution that maximizes
(or minimizes) the objective function while satisfying all the constraints.
**Dual Problem:**
The dual problem is derived from the primal problem and provides an alternative
perspective on the optimization problem. It involves formulating a new optimization
problem that is related to the primal problem but focuses on the constraints rather
than the objective function. The dual problem aims to find the optimal values for a
set of dual variables (also known as shadow prices or prices of resources) that
represent the marginal contribution or cost of each constraint to the objective
function.
**Duality Relationship:**
The relationship between the primal and dual problems is characterized by duality
theory, which establishes a fundamental connection between the two problems. The
duality theory states that for every primal problem, there exists a corresponding
dual problem, and vice versa. Moreover, the optimal objective values of the primal
and dual problems are always equal, regardless of the specific values of the
decision variables and dual variables.
**Distinguishing Features:**
3. **Direction of Optimization:**
- The primal problem seeks to optimize the objective function in the direction
of maximizing or minimizing.
- The dual problem seeks to optimize the constraints in the direction of
minimizing or maximizing.
4. **Nature of Solutions:**
- The optimal solution of the primal problem provides the optimal values of
decision variables that maximize (or minimize) the objective function while
satisfying the constraints.
- The optimal solution of the dual problem provides the optimal values of dual
variables that minimize (or maximize) the cost or contribution of each constraint
to the objective function.
In summary, duality in linear programming refers to the relationship between the
primal and dual problems, where each problem provides complementary perspectives on
the optimization problem. Understanding duality and solving both the primal and
dual problems can provide valuable insights into the underlying structure of the
optimization problem and help in interpreting the solutions more effectively.
(a)bjective function.
(b) Constraint functions.
(c) Non-negativity condition.
===≠===}
Linear programming is a mathematical technique used in business mathematics to
optimize the allocation of resources. In a linear programming problem, there are
three fundamental concepts: the objective function, constraint functions, and the
non-negativity condition.
In summary, the objective function defines the goal of the linear programming
problem, the constraint functions represent the limitations or restrictions on the
decision variables, and the non-negativity condition ensures that the decision
variables are realistic and feasible within the context of the problem. By
simultaneously optimizing the objective function subject to the constraints and the
non-negativity condition, linear programming enables businesses to make efficient
decisions and allocate resources effectively.
i) **Degeneracy**:
Degeneracy in linear programming refers to a situation where the basic feasible
solution of a linear programming problem has one or more variables at zero value.
These zero-valued variables don't contribute to the solution, leading to redundant
constraints and potentially affecting the efficiency of certain solution
algorithms. Degeneracy can occur in both primal and dual problems.
2. **Certainty Assumption**: LP assumes that all parameters in the model are known
with certainty. In reality, business environments are often uncertain and dynamic,
making it challenging to accurately estimate parameters.
____________________________________________Chapter _8
Network Analysis ( CPM and PERT)
______________________####
. Short - Answer Type Questions
___________@)
**Events:**
In a network diagram, an event represents a point in time when something
significant occurs within the project. These significant occurrences can include
the start or completion of an activity, the occurrence of a milestone, or the
availability of resources. Events are depicted as nodes or circles in the network
diagram, often labeled with unique identifiers or names.
An event does not consume any resources or time; rather, it marks the beginning or
end of one or more activities. Events can be classified into different types based
on their relationship with activities:
1. **Start Event (SE):** This marks the initiation of the project or the beginning
of a specific phase within the project. It signifies the point in time when work on
the project officially begins.
2. **Finish Event (FE):** Conversely, the finish event indicates the completion of
the project or a particular phase within the project. It represents the point in
time when all activities have been successfully executed, and the project
objectives have been achieved.
3. **Intermediate Event (IE):** These events occur between the start and finish
events and represent significant milestones or checkpoints within the project.
Intermediate events help in tracking progress and identifying critical paths.
**Activities:**
Activities, on the other hand, represent the tasks or work packages that need to be
completed to achieve project objectives. They are the building blocks of a project
and are depicted as arrows or lines between events in the network diagram. Each
activity has a defined duration, dependencies, and resources associated with it.
In summary, these terms play vital roles in PERT/CPM for analyzing project
schedules, identifying critical activities and paths, and managing project
timelines effectively. By understanding and leveraging these terms, project
managers can develop realistic schedules, allocate resources efficiently, and
mitigate risks to ensure successful project delivery.
3. Define 'critical path', 'Slack time'. 'Resource levelling' and 'Dummy activity'
with reference to PERT/CPM.
===≠===}
Certainly! In the realm of PERT/CPM (Program Evaluation and Review
Technique/Critical Path Method), several terms play crucial roles in project
scheduling and management. Let's define each term:
1. **Critical Path:**
The critical path is the longest sequence of dependent activities in a network
diagram that determines the shortest possible duration for completing the project.
Activities on the critical path have zero slack time, meaning any delay in these
activities will directly delay the project's overall completion. Therefore, the
critical path highlights the activities that must be closely monitored and managed
to ensure the project stays on schedule.
2. **Slack Time:**
Slack time, also known as float or buffer, refers to the amount of time an activity
can be delayed without delaying the project's overall completion. Positive slack
indicates that an activity can be delayed without impacting the project timeline,
while zero or negative slack indicates that any delay in the activity will extend
the project duration. Slack time allows project managers to identify non-critical
activities and allocate resources more effectively.
3. **Resource Leveling:**
Resource leveling is a technique used in PERT/CPM to optimize resource utilization
and minimize resource conflicts throughout the project. It involves adjusting the
start and finish times of activities to ensure that resource requirements do not
exceed the available resources at any given time. Resource leveling helps prevent
overallocation or underutilization of resources, thereby reducing project delays
and costs.
4. **Dummy Activity:**
A dummy activity is a fictitious task added to the network diagram to represent a
logical relationship between two dependent activities. Dummy activities are
typically denoted by dashed lines and do not consume any time or resources. They
are used to clarify the precedence relationships between activities and ensure that
the network diagram accurately reflects the project's logical flow. Dummy
activities are particularly useful in situations where multiple activities converge
or diverge, and the relationships between them need to be clearly defined.
3. **Focus on Uncertainty:**
- PERT: PERT is well-suited for projects with high levels of uncertainty and
variability in activity durations. It incorporates probabilistic time estimates to
account for uncertainty and risk in project schedules.
- CPM: CPM is more suitable for projects with relatively low uncertainty, where
activity durations can be estimated with a high degree of confidence. It does not
explicitly account for uncertainty and focuses on determining the critical path and
project duration based on deterministic estimates.
4. **Probability Analysis:**
- PERT: PERT allows for probabilistic analysis of project schedules, including
the calculation of the probability of completing the project within a specified
timeframe.
- CPM: CPM does not incorporate probabilistic analysis and focuses on
identifying the critical path and project duration based on deterministic estimates
of activity durations.
5. **Application Areas:**
- PERT: PERT is commonly used in research and development projects, product
development, and projects with high levels of uncertainty and risk.
- CPM: CPM is widely used in construction, manufacturing, and engineering
projects where activity durations can be estimated with a reasonable level of
certainty.
In summary, while both PERT and CPM are used for project management, they differ in
their approach to time estimation, handling of uncertainty, and application areas.
PERT is suited for projects with high uncertainty, while CPM is better suited for
projects with well-defined activities and durations.
2. **Risk Management:**
- PERT incorporates probabilistic time estimates and allows for risk analysis by
calculating the probability of completing the project within a specified timeframe.
By assessing the impact of uncertainties and risks on project schedules, decision-
makers can develop contingency plans, allocate resources strategically, and
mitigate potential delays or disruptions.
3. **Time Management:**
- CPM provides a deterministic approach to project scheduling, allowing
decision-makers to identify the critical path and prioritize activities that
directly affect the project's duration. By focusing efforts on critical activities,
decision-makers can streamline project timelines, meet deadlines, and ensure timely
project completion.
4. **Performance Evaluation:**
- Both PERT and CPM provide mechanisms for monitoring and controlling project
progress. By comparing actual performance against planned schedules, decision-
makers can identify deviations, assess project health, and take corrective actions
as needed. This enables continuous improvement and ensures project objectives are
met efficiently.
5. **Strategic Planning:**
- PERT and CPM facilitate strategic planning by providing insights into project
dependencies, timelines, and resource requirements. Decision-makers can use this
information to prioritize projects, allocate resources effectively, and align
project activities with organizational goals and objectives. This strategic
alignment enhances overall organizational performance and competitiveness.
7. **Cost Management:**
- By identifying critical activities and paths, PERT and CPM enable decision-
makers to optimize project schedules, minimize delays, and reduce project costs.
Additionally, by monitoring resource utilization and efficiency, decision-makers
can identify cost-saving opportunities, streamline processes, and improve overall
project cost management.
In summary, PERT and CPM techniques provide decision-makers with valuable insights
into project schedules, resource requirements, risks, and performance. By
leveraging these techniques, decision-makers can make informed decisions, optimize
resource allocation, mitigate risks, and ensure successful project outcomes.
The decision to crash activities involves a trade-off between time and cost. By
allocating additional resources to critical activities, the project manager can
reduce the overall project duration, but this usually comes at an increased cost.
Therefore, crashing should be carefully evaluated to ensure that the benefits of
time reduction outweigh the additional costs incurred.
3. Calculate Crash Costs: For each crashable activity, project managers need to
determine the additional resources required to shorten its duration. This may
involve analyzing resource constraints, negotiating with suppliers or contractors,
and estimating the cost implications of crashing.
6. Monitor and Control: Throughout the project execution phase, project managers
must continuously monitor the progress and performance of the crashed activities.
Any deviations from the planned schedule or budget should be promptly addressed
through appropriate corrective actions.
7. Discuss in brief:
(i) Total float
(ii) Free float
(iii) Independent float.
===≠===}
In the realm of project management, particularly within network analysis methods
like PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method),
float refers to the flexibility or slack time available for activities in a project
schedule. Understanding different types of float is crucial for effective project
planning and management. Let's delve into each type:
(e) Variance.
===≠===}
In PERT (Program Evaluation and Review Technique), various time estimates are used
to assess the duration of project activities and calculate the overall project
schedule. These estimates are essential for managing project timelines and
understanding the uncertainty associated with activity durations. Let's delve into
each term:
(e) **Variance:**
- Variance (σ^2) measures the dispersion or spread of the time estimates around
the expected time. It quantifies the uncertainty or variability associated with the
activity's duration. Variance is calculated using the formula: Variance = ((b -
a) / 6)^2. A higher variance indicates greater uncertainty or risk associated with
the activity's duration, while a lower variance suggests more confidence in the
estimated duration.
In summary, these terms in PERT help project managers assess the uncertainty
associated with activity durations, plan project schedules more effectively, and
manage project risks. By considering optimistic, normal, and pessimistic scenarios,
along with their respective time estimates and variances, project managers can make
informed decisions, allocate resources efficiently, and mitigate potential delays
or disruptions in project execution.
9. Give the procedure of resource levelling using PERT/CPM. Describe the term
'resource of levelling' in the network analysis.
===≠===}
Resource leveling is a technique used in project management, particularly in
PERT/CPM (Program Evaluation and Review Technique/Critical Path Method), to
optimize resource utilization and prevent resource conflicts throughout the
project. The goal of resource leveling is to ensure that the project's resource
requirements do not exceed the available resources at any given time, thereby
minimizing resource bottlenecks and avoiding overallocation or underutilization of
resources.
The procedure of resource leveling using PERT/CPM involves the following steps:
The term "resource leveling" in network analysis refers to the process of smoothing
out resource utilization over the project duration to prevent resource bottlenecks
and conflicts. It involves adjusting the start and finish times of activities to
ensure that resource requirements do not exceed available resources at any given
time, thereby optimizing resource utilization and minimizing project delays.
(a) Node
(b) Network diagram
(e) Critical path
(d) GERT
(e) LOB
(f) MOST
===≠===}
Sure, I'll explain each term briefly:
(c) **Critical path**: The critical path in a network diagram is the sequence of
activities that determines the shortest possible duration for completing the
project. It represents the longest path through the network and identifies the
tasks that must be completed on time to prevent delays in the project's overall
schedule.
In business mathematics, particularly in network analysis using PERT and CPM, these
concepts are essential for effectively planning, scheduling, and managing projects.
They provide project managers with valuable tools and techniques for optimizing
resource allocation, identifying critical tasks, and minimizing project duration
and costs.
(b) **Crashing:**
- Crashing is a project management technique used to reduce the project duration
by allocating additional resources to critical activities. This typically involves
expediting activities by adding more resources, such as manpower, equipment, or
finances, to accelerate their completion. Crashing allows project managers to
compress the project schedule and meet tight deadlines, but it often comes with
increased costs. Project managers must carefully weigh the trade-offs between time,
cost, and resource utilization when deciding whether to crash activities.
(d) **Slack:**
- Slack, also known as float or buffer, represents the amount of time an
activity can be delayed without delaying the project's overall completion. Positive
slack indicates that an activity can be delayed without affecting the project
schedule, while zero or negative slack indicates that any delay in the activity
will extend the project duration. Slack allows project managers to identify non-
critical activities and allocate resources more effectively. Total slack refers to
the amount of time an activity can be delayed without affecting subsequent
activities or the project's completion, while free slack refers to the amount of
time an activity can be delayed without delaying the early start of its successor
activities. Slack management is crucial for optimizing project schedules and
mitigating risks.
===≠===}===≠===}===≠===}===≠===} ⚡⚡
💯💯✌✌
END OF THE WORLD... OF THIS SUBJECT!
CONGRATULATIONS🎉🥳👏 YOU'VE REACHED THE
==≠===}===≠===}===≠===}===≠===}
_____________________THE END ______________