Unless otherwise specified, this specification shall not be binding for insulation of
incinerators, boilers, economizers, air pre-heater / ducting of fired heaters etc. for which
requirements may be covered in respective package specification. This specification
shall not apply to licensed units, where licensor’s standard/ specification is applicable.
HOT INSULATION
SYSTEM
°C
°C
°C
°C
°C
Note-1: Supplier shall provide test certificate for each production Batch
Note-2: Max 20ppm allowed for application over carbon steel and low alloy steel
Note-3: Supplier shall provide Type test certificate no older than 2 years
4.1.5 For temperature 176°C and above, for application over steel and
low alloy steel pipe, insulation blanket wherever used shall have metal facing as
per ASTM A167 type SS 304 with 25mm mesh and 0.8mm wire diameter,
stitched with 0.41mm dia. tie wires.
4.1.6 For austenitic stainless steel and alloy 20 piping, irrespective of operating
temperature, insulation blanket wherever used shall have metal facing as per
ASTM A167 type SS 304 with 25mm mesh and 0.8mm wire diameter, stitched
with 0.41mm dia. tie wires.
Note-1: Batch test - Supplier shall provide test certificate for each production Batch
Note-2: Max 20ppm allowed for application over carbon steel and low alloy steel
Note-3: Type test - Supplier shall provide Type test certificate no older than 2 years
Nominal pipe diameter Form of Fibrous Material
9270C
for 24hrs, max.
Note-1: Batch test - Supplier shall provide test certificate for each production Batch
Note-2: Type test - Supplier shall provide Type test certificate no older than 2 years
Note-1: Batch test - Supplier shall provide test certificate for each production Batch
Note-2: Type test - Supplier shall provide Type test certificate no older than 2 years
Note-1: Batch test - Supplier shall provide test certificate for each production Batch
Note-2: Type test - Supplier shall provide Type test certificate no older than 2 years
Note-1: Batch test - Supplier shall provide test certificate for each production Batch
Note-2: Type test - Supplier shall provide Type test certificate no older than 2 years
.
0
C
0
C
0
C
Note-1: Batch test - Supplier shall provide test certificate for each production Batch
Note-2: Type test - Supplier shall provide Type test certificate no older than 2 years
Volume change (shrinkage) upon drying, max,
ASTM C166
Note: For grade piping in offsites the cladding material shall be Galvanized steel.
-
-
-
-
-
-
-
-
-
APPLY MOISTURE BARRIER OVER
THE INSULATION
FIGURE – 0 1
PIPE INSULATION DETAILS
(FIBROUS &RIGID INSULATION)
APPLY MOISTURE BARRIER OVER
THE INSULATION
FIGURE – 0 2
PIPE INSULATION METHOD OF STAGGERING OF SECTIONS
RIGID & FIBROUS INSULATION (PREFORMED PIPE SECTIONS ONLY)
FIGURE – 0 3
HORIZONTAL PIPE : FIBROUS INSULATION; DETAIL OF SPACER RINGS FOR CLADDING
SUPPORT
FIGURE – 0 4
DETAIL OF SPACER RING FIBROUS INSLUATION (MATTRESS)
FIGURE – 0 5
BOLTED ON INSULATION SUPPORT FOR VERTICAL PIPE
APPLY MULTIPLEX FOIL OVER THE
INSULATION
FIGURE – 0 6
INSULATION DETAILS FOR BENDS / ELBOWS
FIGURE – 0 7
INSULATION DETAILS : PIPE BENDS & ELBOWS
FIGURE – 0 8
INSULATION DETAILS: PIPE BRANCHED & REDUCER
NOTE
FIGURE – 0 9
EXAMPLE OF REMOVABLE FLANGE BOX, HORIZONTAL
NOTE
FIGURE – 1 0
REMOVABLE FLANGE BOX, VERTICAL
FIGURE – 1 1
INSULATION DETAILS PIPE SUPPORTS
FIGURE – 1 2
INSULATION OF TRACED PIPING
FIGURE – 1 3
HORIZONTAL EQUIPMENT INSULATION
FIGURE – 1 4
HORIZONTAL EQUIPMENT HEADS
FIGURE – 1 5
USE OF FLEXIBLE INSULATION IN COMBINATION WITH RIGID INSULATION TO
COMPENSATE FOR VESSEL EXPANSION
FIGURE – 1 6
INSULATION DETAILS : VERTICAL VESSEL
FIGURE – 1 7
INSULATION DETAILS VERTICAL VESSEL HEADS
FIGURE – 1 8
INSULATION DETAILS : VERTICAL VESSELS
FIGURE – 1 9
INSULATION DETAILS : VERTICAL STORAGE TANK
FIGURE – 2 0
INSULATION DETAILS : SPHERE
FIGURE – 2 1
NON- INSULATED FLANGES, HORIZONTAL AND VERTICAL
FIGURE – 2 2
REMOVABLE VALVE BOX, "T" CONNECTION, HORIZONTAL
FIGURE – 2 3
REMOVABLE VALVE BOX, "T" CONNECTION, VERTICAL
FIGURE – 2 4
HANGER SUPPORT
FIGURE – 2 5
PERSONAL PROTECTION
FIGURE – 2 6
DETAILS OF LIFTING LUGS
FIGURE – 2 7
REMOVABLE BOX FOR PUMP