MMGSY-2 (Batch-1) 2023-24

(Nashik R&D)
Survey No of No of
Sr DPR Length Total No
Block Length Prepared Pending Date Of Completion Remarks
No (KM) of DPR
(KM) DPR DPR

1 Dindori 18.62 18.62 5 5 0 26 March 2024

2 Yeola 35.44 35.00 7 7 0 03 April 2024

3 Niphad 34.99 35.00 7 2 5 05 April 2024 In Progress

4 Chandwad & Deola 35.26 35.00 7 0 7 09 April 2024 In Progress

5 Kalwan & Surgana 46.07 35.00 13 0 13 14 April 2024 In Progress


21.72 KM Survey
6 Nashik 13.28 35.00 3 0 3 17 April 2024
Pending
Total - 183.66 193.62 42 14 28