Sr no Points Remarks

1 Cable tags are missing Planned on next visit

2 DB tags are missing Done

3 We cannot open multiple faceplates. Done

4 There must be proper alarm list, where we can find the alarm as per area, mimic name and meter number. Done

5 Ethernet connectors are not proper. Done

6 There must be a proper drawing in every DB as accordingly their termination. Planned on next visit

7 In every drawing must mention the spare IO's of plc. Planned on next visit

8 There must be spare terminal blocks as per spare IO's of plc. Done

9 Whrp1 mimic is not proper Done

10 Whrp2 mimic is not proper. Done

11 ODF boxes are not properly fixed in DB. Done

12 Ethernet cables are not properly dressed in DB's due to their size. Done

13 Their should be alarm for every PLC communication. Done

14 Their must be a file of all meters addresses and baud rate for communication area wise. Done

15 Add mimic for solar power plant FP2 & FP7 after PGP. Done

16 Add bar for load of every area at home screen. Done

17 Mention system is running in operator or administrator mode. Done

18 Mention panel names with meter names. Done

19 Need totalizer for all the areas power generation. Done

20 Station Trafo-2 showing alarm at cfpp mimic. Planned on next visit

21 Alarm bar should be on top of screen Done

22 Fiber patch cords core must be highlighted as sender & reciever with tags. Planned on next visit

23 Many meter are not showing PF at PGP & Grid. Done

24 Add generator breaker status and running hours at cfpp, pgp, Whrp1 & whrp2 Done

Kindly confirm status after


25 BFW 2 kwh are not matched there is difference of 6 units, waiting for pump startup than it will be checked.
pump startup

Please Provide Power


26 Reports alignment should be same as our old at power scada system. Even the area names order.
Scada Report Format

Discussed cant be
27 G1 PLC should be CFPP and G2 PGP. Done
changed.

28 Chnage CFPP SLD as per power scada's SLD. Done

29 Generator breaker status needs connection with generator symbol at CFPP SLD. Done

30 Cable dressing required outside and inside of DB's. Done

31 Cable tags for Gen breaker status required. Planned on next visit

32 FP6 communication alarm - MLCF Shutdown Needed

33 K03 communication alarm - MLCF Done

34 Original windows in system & DVD required.

35 Original Office in system & DVD required.

36 System redundancy check required.