Professional Documents
Culture Documents
Q1: Moiz limited produces three products from a single raw material that is limited in supply. Product
for the period 7 are as follows:
Raw material cost per unit (Rs. 100 per kg) Rs. 250 Rs. 300 Rs. 150
The planned production optimizes the use of the 6000 kg of raw material that is available for Moiz
Limited normal supplier at the price Rs. 100 per kg. However a new supplier has been found that is
prepared to supply a further 1000 kg of the material. What is the maximum price that Moiz limited
should be prepared to pay for the additional 1000 kg of the material?
a) Rs. 460,000.
b) Rs. 420,000.
c) Rs. 448,000.
d) Rs. 493,000.
Answer:
Q2: Jawad and Sons reported cost of sales of Rs. 150 million and an inventory turnover ratio of 2. The
Company is now adopting just in time inventory system. If the new system is able to reduce the
company’s inventory level and increase the company’s inventory turnover to 5, while maintaining the
same level of sales, how much cash will be freed up?
a) Rs. 40 million.
b) Rs. 45 million.
c) Rs. 50 million.
d) Rs. 30 million.
Answer:
Current average inventory = CGS/ Inventory T.O = 150 million/2 = Rs. 75 million.
New average inventory = CGS/ Inventory T.O = 150 million/5 = Rs. 30 million.
=-\]
Cash freed up= 75 – 30 = 45 million.
Q3: If the quantity discount is accepted this will have the following effects, except:
d) None of these.
EOQ generally minimizes the total inventory cost. However, EOQ may not be optimal when discounts
are factored into the calculation. The optimal order quantity when discounts are involved is either: ...
Any one of the minimum order quantities above EOQ that qualify for additional discount.
Q4: Beenish furniture limited (BFL) requires raw material “G” in one of its product. The annual demand
of raw material is 1500,000 units. The cost of raw material “G” is Rs. 225 per unit. Procurement costs for
each order are Rs. 3000 and the lead time is estimated to be 3 days. The carrying cost of the inventory is
Rs. 15 per unit and the stock out cost is Rs. 30 per unit. Assuming 250 working days per year the optimal
reorder level will be:
a) 750 units.
b) 6000 units.
c) 24000 units.
d) 18000 units.
Answer:
Q5: Williams & Sons last year reported cost of sales of $18 million and an inventory turnover ratio of
2. The company is now adopting a new inventory system. If the new system is able to reduce the
firm's inventory level and increase the firm's inventory turnover ratio to 5 while maintaining the same
level of sales and COGS, how much cash will be freed up?
a) Rs. 2 Million.
b) Rs. 6 Million.
c) Rs. 4 Million.
=-\]
d) Rs. 8 Million.
Answer:
Q6: Which of the following costs have no relationship with the level of output?
a) Fixed costs.
b) Variable costs.
d) Semi-variable cost.
b) there is no uncertainty.
Q8: Identify the most appropriate feature that distinguishes throughput accounting from other costing
techniques.
d) a and b.
Q9: Responsibility centers are departments or organizational functions whose performance is the
direct responsibility of specific managers. One type of responsibility center is a revenue center, which
is responsible for:
b) sales.
=-\]
c) sales and profits.
d) profits.
Q10: Yasir Limited (YL) manufactures a single product “M”, which requires 5 hours of machine time for
each unit. Machine time has been identified by YL as the bottleneck resource because of limited number
of machines available for manufacturing. Currently, the company has only 12 machines which are
operated for 12 hours per day and 5 days per week. The following information pertains to each unit of
product M:
The costs are based on weekly production and sales of 200 units. The throughput accounting ratio of
product M would be:
a) 0.285.
b) 1.0909.
c) 2.00.
d) 0.571
Answer:
Throughput accounting ratio (TPAR) = Return per factory hour/cost per factory hour.
Return per factory hour = Throughput per unit / Product's time taken for the limited resource.
Cost per factory hour = Total factory costs / total time available on bottleneck resource.
=-\]
Another method:
=-\]