Professional Documents
Culture Documents
5.1 Introduction
This chapter describes the pressure testing of land and subsea carbon steel
pipelines. Chapter 11 addresses pressure testing pipeline bundles and stainless
steel and flexible pipelines. Procedures for pressure testing with nitrogen are also
discussed in Chapter 11.
5.2 Overview
5.2.1 Reasons to Pressure Test a Pipeline
The reasons to pressure test a pipeline after construction are listed below:
For safety reasons, the most common tests used in the pipeline industry are the
hydrostatic pressure-strength test and the leak test. These tests can be combined
but are more often performed separately to fit into construction schedules.
An air pressure leak test is sometimes used as a pre-lay test on short pipeline
sections, such as small river or road crossings. The test pressure is not normally
more than 7 bar (100 psi).
• Planning
• Engineering
• Preparing procedures
• Selecting equipment and instrumentation *
These general preparatory steps required for pressure testing are described in
detail below.
Engineering
The steps in Table 5.1 comprise the engineering work involved in preparing for
pressure testing.
Preparing Procedures
Detailed, step-by-step operations procedures and contingency procedures are
normally required for pressure testing operations. The operations procedures are
described in further detail later in this section.
• Test cabin
• Equipment container
• Workshop container
• Personnel messing, changing, and toilet facilities (land only)
• Water supply pumps
• Pressurizing pumps
• Breaktank
• Hose reel and hoses (offshore only)
• Various hoses and piping
• Air compressor (if necessary)
• Generator (if necessary)
• Lighting towers (land only)
• Filters
• Flowmeters
• Temporary test heads
• Chemical injection pumps
• Chemical tanks
• Stroke counters
• Subsea temperature recorders (offshore only)
• Ground temperature recorders (land only)
• Ambient temperature recorders
• Pipewall temperature recorders
• Pressure recorders
• Pressure gauges
• Deadweighttester
• Data loggers (offshore only)
• Barometric recorders (offshore only)
• Hand tools
• Small fittings, such as hex nipples
Inspecting Equipment
Before mobilization, the client's representative will visit the Halliburton base to
make the following inspections:
• Engineering
• Producing procedures, including quality plans and safety procedures
• Assembling equipment and instrumentation
• Mobilizing
• Doing the work
• Demobilizing
• Producing the final documentation
The dates for submitting key documents and for completing the work are agreed
upon with the client and are available in the contract. An example of an overall
schedule is shown in Appendix B.
• Pipeline volume
• Volume to pressurize
• Chemical injection rates
• Pressure drop per °C
Formulas and examples for these calculations are found in Chapter 13.
This test limit drawing should show the connection points for the Halliburton
pressure pumps and instrumentation.
If the test is performed from a land site or from a platform, connection points will
be available on the temporary test head or permanent pig trap (Figure 5.1).
If the pipeline has not been tied in to the platform on a subsea pipeline, connec-
tion points will be available on the temporary subsea head. Figure 5.2 shows an
example of a subsea valve arrangement for a hydrotest.
PG PS
Drain to
Chemical
Tanks
Drain
206
205
TIM
PLR
217 218
219 220
Transducer
208
"tJ
"6.
(J)
§r
(J)
ig.
iii·
!/)
114-in HP Hose I~ ? I 0 I
n : s s u r e Gauge Instrument Cabin
~.
Gauge Recorders
f
§. - ~ I
and Dead Weights
(J.)
:::l!:::: :~~~~:~I~~:...
.... ~
(J.)
c
:.:::i
I--D
c I 50-
+"'
:.:::i C Secondary Micron Fill
+"' (J.) I
C
E I Break Tank Filter Pump
(J.) ,...-------,
:::::I
I E .....
+"'
I
c:::::l
.- .... I I en I
~-
I I +"' l ________ I c
~~ c I
-
Pipeline T""" - Pipeline I
~o Break
V Tank
HP HD Water
T """
Z Temperature
Flow- Triplex
~ C( I 0 I meter Pump Recorder
Instrument Cabin
l pre:ure Gauge, ' ,,
(J.)
(ij
(J.)
(ij
m
CI) CI)
Gauge Recorders Water
and Dead Weights I Pumps
.. .. I
~~i
~~:
- -Pipeline
-----~
~ Sea
~
c:
III
-
~
~
'I
Figure 5.3-Hydrotest Equipment Setup
Size the Equipment and Instrumentation
The design of the equipment requirements is determined based on the calcula-
tions performed to fulfill the requirements of the contract. filling and dewatering
the line require a different set of calculations than the hydrotest. The rates and
pressure for filling the line must be known, as well as the factors listed below:
Knowing the parameters and performing the calculations helps determine the
equipment requirements for the job.
Obtain full data sheets for all pieces of equipment, and include them with the
procedure.
When designing the piping or hose connections between the pressure pumps and
the connection to the pipeline, include a check valve to ensure that the full
pressure in the pipeline cannot back up into the pumps. Chemical valves should
also include a check valve.
Include a pressure safety valve in the system, located as near to the pipeline as
possible.
• An introduction
• A section listing all relevant National Codes and Standards and the
client's specifications
• A detailed schedule of operations
• A list of the pipeline parameters, including length, diameter, wall thick-
ness, and test pressure
• A list of pumping rates, chemical injection rates, and volumes
• A sketch or drawing of the test limits that also shows the connection
points for Halliburton's pumps and instrumentation
• An equipment layout drawing
• A detailed list of equipment and instrumentation
• A detailed, step-by-step procedure
• Test acceptance criteria
• A quality plan showing witness and hold points
• A section containing relevant safety regulations
• An appendix containing equipment and instrumentation data sheets
• An appendix containing calculations
• An appendix containing sample report sheets
• An appendix containing chemical data sheets
NOTE The approved procedure taken to the site will also contain
equipment and instrument calibration certificates.
1. Write a simple introduction stating the project title and the scope of
Halliburton work and describing the project.
2. Copy the section listing the relevant national codes and standards and the
client's specifications directly from the contract document.
3. Prepare a detailed schedule of operations, including an employee schedule.
Write the method statement using command statements, similar to the following
statements:
"Permanent valves or other equipment, such as pig trap closure doors, are
operated only under the supervision and control ofthe prime client's operations
staff. Halliburton provides labor assistance."
Copy the test-acceptance criteria directly from the specification. Remember that a
quality plan showing witness and hold points is not always required. However, if
one is necessary, an example is given in Table 4.2 in Chapter 4 (Page 4-15).
A pressure test consists of the stages listed below. These stages apply to both
subsea and land pressure tests, except where noted.
• Pressurizing
• Stabilizing
• Test-hold period
• Accepting the test
• Depressurizing
• Disposing of test water
• Recording and reporting data (This process is described in Section 5.3.8.)
Pressurizing
Pressurizing is performed at a controlled rate. During pressurizing, the pumps are
stopped at predetermined pressures to allow for the stabilizing of pressure surges
and to check the following items:
When pressurizing, ensure that all pressure and temperature chart recorders are
working, and replace charts where necessary before pressurizing. All parties
Stabilizing
The stabilizing period allows pressure surges to settle and allows the fill water
and pipeline temperatures to adjust to the surrounding conditions. The stabilizing
period is normally at least 24 hours, but it can be longer, depending on the length
and diameter of the pipeline.
• Log pressure at IS-minute intervals for the first 4 hours of the stabilizing
period.
• After 4 hours, log the pressure at 30-min intervals.
• Maintain a pressure-versus-time plot during the stabilizing period.
During the stabilizing period, the pressure usually decays quickly over the first 2
to 4 hours. After that time, the decay slows. When the pressure appears to have
stabilized, restart the pump and bring the pressure back to the test pressure level.
Log both the volume of water required to repressurize the pipeline and the
pressure rise in the pipeline.
Land pipeline pressure tests are very sensitive to temperature changes. There may
be a requirement to maintain the pressure between two specified figures. This
requirement could result in water being added to the test piece or being bled from
the test piece.
Log both the volume of water removed or injected and the change in pressure.
Test-Hold Period
The test-hold period monitors the ability of the pipeline to hold pressure. The
test-hold period for a strength test is the 24-hour period during which the pressure
is maintained within specified plus-and-minus limits. Repressurizing and depres-
surizing are allowed during the 24-hour period; however, volumes extracted and
added and the subsequent pressure changes must be recorded and logged.
The test-hold period for a leak test is the 24-hour period during which no pres-
sure decay is allowed except for that which can be attributed by calculation to
external factors, such as temperature.
Depressurizing
Refer to Chapter 6 on Disposal of Treated Water.
NOTE Platforms, boats, and rigs need advance warning that fresh water
makers are closing down to allow time to fill potable water
tanks.
The data shown in Table 5.2 are collected during pressure testing:
The original copy of all records becomes the property of the client.
5.5 References
1. Gray, J. c.: "How Temperature Affects Pipeline Hydrostatic Testing,"
Pipeline and Gas Journal (December 1976).