Professional Documents
Culture Documents
Furnish: to supply and deliver to the project site, ready 2004 CSI MASTERFORMAT
to install. In 2001, a task team with associates from both
Install: to place in position for service or use. Provide: the CSI and the Construction Specifications Canada
to furnish and install, complete, ready for use. (CSC) was charged with examining whether there was a
need to revise and possibly expand the 16 division
➢ Avoid using abbreviations in the body of a edition in response to the many changes that had taken
specification place in the industry. The 2004 version composed of
➢ Every word in a specification is important. Do (1) General Requirements,
not underline, bold, italicize, highlight. (2) Facility Construction
(3) Facility Services,
SPECIFICATION WRITING (4) Site and Infrastructure, and
UNIFORM SYSTEM: MASTERFORMAT (5) Process Equipment
A format developed by the Construction
Specifications Institute for coordinating specifications, GENERAL REQUIREMENTS SUB-GROUP
Division 1: General Requirements Division 45: Industry-Specific Manufacturing Equipment
Divisions 46 - 47: (Reserved)
FACILITY CONSTRUCTION SUB-GROUP Division 48: Electrical Power Generation
Division 2: Existing Conditions Division 49: (Reserved)
Division 3: Concrete
Division 4: Masonry THREE PART SECTION FORMAT
Division 5: Metals PARTS
Division 6: Wood, Plastics, and Composites 1. GENERAL
Division 7: Thermal and Moisture Protection Defines specific administrative and
Division 8: Openings procedural requirements unique to
Division 9: Finishes this section.
Division 10: Specialties ● Scope
Division 11: Equipment ○ Related Work Specified
Division 12: Furnishings ○ Furnished by others
Division 13: Special Construction ○ Furnished but not installed
Division 14: Conveying Systems ○ Furnish by the Owner
Divisions 15 - 19: (Reserved) ● Description of Systems
○ Water Supply System
FACILITY SERVICES SUB-GROUP ○ Chilled Water System
Division 20: (Reserved) ○ Wiring System
Division 21: Fire Suppression ○ Telephone System
Division 22: Plumbing ○ Fire Detection System
Division 23: Heating, Ventilating, and Air Conditioning ○ Integrated Ceiling System
Division 24: (Reserved) ○ Curtain Wall System
Division 25: Integrated Automation ● Requirements of Regulatory
Divisions 26: Electrical Agencies
Division 27: Communications ○ Permits
Division 28: Electronic Safety and Security ○ Codes
Division 29: (Reserved) ○ Ordinances
○ U.L. Regulations
SITE & INFRASTRUCTURE SUB-GROUP ○ Tests by Agencies
Division 30: (Reserved) ○ Design Conditions
Divisions 31: Earthwork ● Qualifications
Division 32: Exterior Improvements ○ Qualification of
Division 33: Utilities Manufacturer
Division 34: Transportation ○ Qualification of Applicators
Division 35: Waterway and Marine Construction ○ Qualification of Welders
Divisions 36 - 39: (Reserved) ○ Qualification of Erectors
○ Qualifications of Testing
PROCESS EQUIPMENT SUB-GROUP Agency
Divisions 40 - 43: Process Integration, Material ● Submittals
Processing and Handling Equipment; Process ○ Time and Sequence
Heating, Cooling, and Drying Equipment; and Schedules
Process Gas and Liquid Handling, Purification, ○ Shod Drawings
and Storage Equipment ○ Samples
Divisions 44: Pollution Control Equipment
○ Manufacturer’s Literature ○ Asphalt Binder Mix
List ○ Asphalt Topping Mix
○ Parts List ○ Terrazzo Mix
○ Certificates
○ Guarantees and Bonds ● Mixes
● Mock-Up Product Handling ● Equipment
○ Sample Panels ● Fabrication
○ Models ○ Fabrication of Structural
○ Window Assembly Steel
○ Door Assembly ○ Fabrication of Reinforcing
○ Curtain Wall Assembly Steel
○ Panel Wall Assembly ○ Fabrication of Doors
○ Integrated Ceiling Assembly ○ Fabrication of Windows
● Environmental Conditions ○ Fabrication of Toilet
○ Temperature Partitions
○ Humidity ● Source Quality Control
○ Lighting ○ Mill Tests
○ Ventilation ○ Factory Tests
● Protection ○ Plan Tests
○ Drop Cloths ○ Shop Tests
○ Removal of Hardware
○ Removal or Flammable 3. EXECUTION
Rubbish Smoke Describes in detail, the quality of
● Operating Instructions items that are required for
○ For Mechanical and incorporation into the project under
Electrical System this section.
● Extra Stock
○ Spare Parts ● Condition of Surfaces
○ Extra Tiles ● Preparation
○ Extra Wall Covering ○ Fine Grading
○ Resilient Flooring ○ Treatment of Formwork
○ Extra Brick ○ Treatment of Galvanized
○ Tools Surfaces
○ Maintenance Materials ○ Treatment of Wood
● Alternates Surfaces
● Measurement and Payment ● Installation
○ Placing Concrete
2. PRODUCTS ○ Laying Bricks
Describes in detail, the quality of ○ Framing Floors
items that are required for ○ Applying Paint
incorporation into the project under ○ Clearing Site
this section. ○ Erection of Trusses
● Field Quality Control
● Materials ○ Soil Composition Tests
○ Plaster Mix ○ Pile Load Tests
○ Concrete Mix
○ Concrete Compression V = 0.20 m. x 0.30 m. x 1.00 m
Tests V (column) = 0.06 cu.m.
○ Concrete Slump Tests
○ Plumbing Tests V = 0.43 cu.m + 0.06 cu.m.
● Adjusting V (structure)= 0.49 cu.m.
● Patching
● Cleaning V (backfill) = V (excavation) - V (structure)
● Schedules V = 1.44 cu.m – 0.49 cu.m
V (backfill) = 0.95 cu.m
CONCRETE WORKS
ESTIMATES PROBLEM:
Estimate the quantity of cement, sand and gravel
needed for 1 piece of the footing. Use Class AA
concrete – 40kg cement bag for footings
REBARS
EXCAVATION & BACKFILL Architectural Materials & Finishes
PROBLEM: Masonry Works:
Find the volume of excavation if the size of column o CHB (thickness) – 4”, 6”, 8”
footing is 1.20 meters square having a depth of 1.00 o CHB (dimension) – 20cm x 40cm
meter. o 12.5 pcs of CHB per 1 square meter
V = 1.20 m. x 1.20 m. x 1.00 m.
V = 1.44 cu.m.
PROBLEM:
Find the volume of backfill if the size of column footing
is 1.20m x 1.20m, footing thickness is 0.30 meters
having a depth of 1.00 meter. Column Size is 0.20m x
0.30m