Guideline
Revision history
Version Date Revision description
1.0 18-Sep-18 First issue
1.1 07-Aug-19 Updates to escalation factors
RMS regularly reviews and updates documents in the ILC Management System
in accordance with the principle of continual improvement.
Therefore, the version you are working with might now have been superseded.
Note
The most recent version of this document is available on the RMS intranet in the
TechInfo site.
Table of contents
1 Overview ........................................................................................................................................... 4
1 Overview
This guideline is only to be used by RMS internal staff.
Note
This document is only to be used for major projects with a total cost of over $10M.
The costs have been adjusted to August 2018 costs.
Note
The following cost data is derived from historical Roads and Maritime project data for the
construction of road and bridge infrastructure in NSW.
The intention of this document is not to use the rates to replace estimates prepared using an
estimating methodology but to provide broad strategic information on historic costs that might
be useful in preparing the first strategic estimate of cost for a new proposal or for benchmarking
project estimates.
For more specific estimating requirements, Roads and Maritime staff are encouraged to consult
the Engineering Estimation Unit within the Project Services Branch.
The listed rates reflect road project costs where a reasonably efficient route has been selected.
For example, one that minimises earthworks and avoids sensitive sites such as SEPP14
wetlands, residential areas, areas of local or aboriginal heritage significance and national parks.
1. Concept development
(a) Route / concept / EIS Value of construction % of construction costs
(infrastructure costs and
utilities)
rural urban
Up to $50m 2% - 4% 4% − 6%
$50m − $150m 4% - 6%
Over $150m 3% − 5%
(b) Project management services Refer to project management costs table above.
(c) Client representation 10% of project management costs.
Comments For D & C and DCM projects, the design cost will be at the lower
end. However an additional cost will be incurred in infrastructure
costs associated with design and verification.
For alliance contracts, add an additional 2% to 3% of the
construction cost for alliance preliminary costs.
3. Property acquisitions
(a) Acquire property Sydney Region Property Services – Indicative
Notes: strategic/concept rates for property acquisition
The purpose of the rates is to Location Parks Rural Residential Industrial
provide an approximate $/sqm $/sqm $/sqm $/sqm $/sqm
budgetary allowance for the Prime location N/A N/A 6000 3500
purpose of high level strategic
route analysis. Inner urban 1500 N/A 3000 2000
4. Utility adjustments
(a) Adjust utilities The construction costs include the costs associated with the utility
relocation of past projects.
• 2%-4% of infrastructure costs in mainly rural areas.
• 12%-25% of infrastructure costs in urban areas.
(b) Project management services Refer to project management costs table on page 1.
(c) Client representation 10% of project management costs.
Comments Where major utilities obviously require relocation, additional
allowance should be made for these costs.
5. Infrastructure construction
(a) Road construction (excluding bridges and utilities)
Category Description L − Length of the road
(proposed development in a single stage)
L < 1km L 1km − 2km L > 2km
Urban 4 / 6 lane $4.0 $3.2 million / $2.8 million /
Growth centre roads Includes costs such as million / lane km lane km
similar to Camden earthworks (average height lane km
Valley Way, < 2.0m), drainage,
Cowpasture Road, pavement, culvert, minor
Schofields Road. retaining walls (height <
2m) and landscaping.
Mountainous terrain $7.5 $6.5 million / $5.5 million /
Similar to Great Western million / lane km lane km
Highway projects lane km
6. Finalisation
(a) Refurbish old route for Determine costs associated with refurbishment of local roads
handover to local authority
(b) Project data and post 1.0% of infrastructure costs
completion review
(c) Project management services Refer to project management costs table.
(d) Client representation 10% of project management costs
Comments Estimator should list all the assumptions in the estimate summary
sheet with reference to all the documents used.
confident and
confident and
Not confident
activity
Reasonably
and not
reliable
reliable
reliable
Highly
DECREASE contingency =
INCREASE contingency =
Project Is it well defined? No 9% 12% 15%
scope Yes
Is there room to vary the No
works? Yes
Are there many options? No
Yes
Risks Are there significant risks with No 9% 12% 15%
the project? Yes
• Political
• Community
• Technical
• Financial
Has a detailed risk analysis No
been conducted? Yes
Constructa- Has a constructability review No 6% 8% 10%
bility been conducted? Yes
Does constructability present No
problems? Yes
Key dates Are the project dates known? No 3% 4% 5%
Yes
Is the project planned for the No
distant future? Yes
Information Have any investigations been No 9% 12% 15%
conducted (including desk top Yes
studies)?
• Geotechnical
• Heritage
• Environmental
• Technical
• Hydraulic
Length of Is the project short in length? No 4% 7% 10%
project < 1 km = short project Yes
> 25 km = long project
Total:
3 Further information
3.1 Acronyms, abbreviations and definitions
Term Meaning
EIS Environment impact statement
ITS Intelligent transport systems
PSC Prestressed concrete