Professional Documents
Culture Documents
The decision regardingtoling and jigs andfixtures are dependent onnthe quanti A
of production batch.
In batch production too, there can be three types namely:
(a) Abatch produced only once. S
(b) Abatch produced repeatedly at regular intervals, when the need arises. S
55
Systems
oachie PPCand Production
Systems
Average number of Total flow time for all jobs completion time = 43 days
jobs in the system (1) Total flow time = 143 days
Total
Total processing time (i) Total flow time 143 =28.6 days
(c) Average job
lateness-It is the average amount of time that each jobs actual
Completion time (or date) Average flow time= No. of jobs 5
exceeds its promised due time (or (ii)
date). Average number of)
Total flovw time 143 = 3.325 jobs
Total processing time 43
Average job lateness= Total job lateness
Number of jobs in the (v) jobs in the system
22 = 4.4 days
(d) Change over
cost-It is the total cost of making all the system
Total job lateness
in a group of jobs. lateness = No. of jobs 5
machine change overs (v) Average job
Illustration. The processing time and due dates for 5
in the table
below: jobs, A, B. C, Sequencing Problems discussed so
D&Eare given scheduling, loading and sequencing have been specified
Job work-centres as
Processing time (days) Several techniques for unique and they move through the job
A Due date (days from Manyjobs in job shopsare operations are same for some jobs,
environment,
B
10 now) far.
sheets. The sequences
of assembly line
by the route work centres. In
C
8
18 varying loads in different essentially the same. The
6 22 orders may require durations and the sequences may be of the following
combination of one or other
D
12 27 most operations, their
models will differ in the
7 17 Various sequencing
Sequence these
(0) Total
jobs according to EDU rule 42 factors:
jobs 'n.
and calculate (a) The number of machines/equipments
(ii) Total completion time. 'm'.
filow time. number of shop.
(ii) Average flow time.
(b) The
production facility, viz., flow shop or jobviz, 'static' or 'dynamic.
(iv) Average number of (©) The type of which the jobs arrive at the facility, evaluated (e.g. utilization
jobs in the system. (0) The manner in alternatives will be
(v) Average job
lateness. The criterion by which the sequencing processing time, the average lateness of
(e)
machines/equipments as measured by the inventory.
O
time and the minimization of work- in-progress
Jo0, the total set up
may be classified as:
The solution techniques
(a) Machines in series.
67
ProductionSystems
66 PPC and
(b) Machines in parallel.
(c) Series- paralll machines.
Production Sysa PPCand
(b)Consider the
shortestprocessing(SPT)
sequencing rule. Then the job sequence
Flow time (mins.)
C B,A.
The sequencing problems are referred to as 'n'job-'m' isF E, D, Processing/operation time (mins.)
problems. machine problems ar Jobsequence
1 1+2=3
1
A
Operation time (f) on the criteria of
Processing
Due date
(days from
Imins. Jobs
B time the start)
6 mins. (n the order
C (days)
D
4 mins. of arrival)
3 mins. 3 10
A 7
F
2 mins. 7
1 min. 4 4
C
Solution. 2 8
(a) Consider the D 5 12
is A, B, C, D, E, F. longest processing (LPI)
sequencing rule. Then the job F
Job sequence
Processing 1 operation time (mins.) sequence on one machine
Solution. Scheduling n jobs(FCFS) Method
Served
7 Flow time (mins.) ()Firm Come, First Due Date Flow Time Late by
Schedule of Processing time (days from now) no. ofdays
6
7
(days)
4 jobs (days) 0+3= 3 0
137+6= 13
D
9 0
A 3 3+7= 10
2
+4 = 17 10 7
17+3 = B 7 10 + 4 = 14
1
20 +2 =20 4
7
14 + 2 = 16
12
22 +1 =22 2
4
16 + 5 = 21 13
Average flow time = 7+13 +17 + 20 +22 + 23 102 23
5 17
6 = 17 mins. 12 21 + 8 = 29
6
F
8.166666667 Average per job
69
68
PPC and.
Total Flow Time = 3+ 10+ 14 + 16 + 21 + 29 = 93 davs
Mean Flow Time = 15.5 days
Production Sip, PPCandProductionSystems
(v)'Shortest
Processing Time(SPT)
Method
Due Date
Fow Time
Late by
no. of days
Processingtime (daysfrom now) (days)
(ii) Last Come, First Served (LCFS) Method Scheduleof| (days) 0+2=2
Schedule of Processing time Due Date Flow Time jobs 4
2+3=5 0
4 1
C 2.25 machines
0.75 three
D
1.5 2.5
Sequencing n jobson
E 2.0 3.0 machinesinseries
F 2.0 4.0 'n'jobs, m =3
jobs.
Solution, Job Chas the
3.5 No. passing of
shortest processing time in
hour), As this time happens to be on WC, assign job C either work
Cross out the processing times for job C, which is
as the
first job incentre
the
(i.e. 0.75 Machunes
Johnson's rule.
already sequence. known as n/3
remaining processing times, job Ahas the shortest time ( i.e. 1 assigned. Scanning the
Jobs
extension ofJohnson's
rule
WC,. Assign job Aas the last job in the sequence and cross out theHour) inwork centre is given by followingexample.
times for job A.
The solution
explained in the
This rule is
3
72
PPC and 73
:To sequence
Job M, M,
Note
get optimal convert an n/3 isBAcD
(a) The sequence, certainproblem into an n/2
A 7 14
13
Applying Johnson's rule
the sequence will be
on machine smallest
M,. duration condi
on tions have to be problmet,em and apply 18
18
(b) The
smallest duration
machine M,is at least as They are Johnson's rue, D
4
11 21 E A D B
on machine M,. on great as the largest duration
Since the above machi ne M, is at
least as
E 6 16
optimal sequence. Eventwoif conditions are met great as the Applying Johnson's rule, the sequence will be
conditions are not met,example, the largest
optimal solution. the in this duration Solution 2. In this, the 'n' jobs x 2 machines problem is derived by adding the
the rule still solution gives processing time on the first two machines (M, + M,) and the last twO machines (M, +
Sequenci
n' inhs ng n jobs on m
and provides a near
an
M) for each job.
elapsed time. 'm' machines, flow shop,machines
Static arrivadl
Processing time in hours
M, + M,
patern, Job M, + M,
Jobs minimizations of total
B
7+ 11 = 18
18 + 15 = 33
2 + 14 = 16
18 + 13 = 31
Applying Johnson's rule
the sequence will be
Machines 4 + 11 = 15 14 + 18 = 32
D 11 + 27 = 38 32 + 21 = 53 E A
E 6 + 16 = 22 14 +16 = 30
74 PPC and
Pr oduct
Solution 3. Inthis, the 'n' jobs x2 machines problem is derived
ion :
processing time on thefirst three i.e.,(M, + M, + M,) andthelàst by at ing
+ M, + M,) for each job. three maching
Processing time in hours
Job M, +M, +M, M, +M, +M,
A 20 27
B
Applying Johnson's rule
51 46 the optimal sequence willbe
C 29 43
D 70 80
E 36
ACE D B
46
Since there are m= 4 machines, there will be (m -1) or (4 - 1)
x 2 machines problems generated by this heuristic. =3 nos. of 'h'w
The three sequences obtained are:
1. S, ’ CEADB
2. S, -’ CE|D BA
3. S, - ACE DB
From the above three,
flow time or cycle time has sequences, the sequence which gives the
to be chosen as the optimal minimum totl
drawing the Gantt Machine loading chart as sequence. This is done by
Sequence S,: illustrated below:
Machines
0(C)4 (E) 10 %4: 17 (D) 28 (B) 46
M
(4) (6) (7) (11) (18) Jdling
0 4 (C) 15 l= ldling
(E) 31 (A) 42 (D) 69
M, (B) 84
(4) (11) (16)
J= ldling (11) (27) (15) Idling
15| (C) 29 31 (E) 45(A)47
69 (D) 101 (B)
M, Idling
l19
(15) (14) l(2) (14) (2) (22)
(32) Idling
| l= ldling (18)
0
29| 47 (E)63
M. 77 101
ldling D) 122
B) 135
(29) (18) (16) (04)
(24)
I
ldling (21) 03)