SR Number

25963
29191
25036
25203
19755
28665
25939
26912
28922
29024
24694
26626
27027
27050
27051
27052
27537
27935
27980
28380
28636
28861
28914
29035
SR Description
OTIF report from Qlik for reagents
Pending Order Report - Remarks Review
PO cancellation process via approval process
Master data for Inventory & Customer
Report in Import Module & Seepz SEZ Import shipments in EBS & Import Module
Engineer address Automation
auto-mailer in EBS for all RR & Direct Customers against pending orders for Reagents Exp confirmation – Sh
Need a Qlik Report of products that are manufactured in the month, locally procured or imported
Addition of dropdown & Restriction on Age in Mediclaim Details section - EBS
Changes to be incorporated in Qlik BI CSD_IRS
Changes to made in the Payment validation report
FG item master categories to be changed to match the target nomenclature
develop the Auto Payment batch processing program, which shall be interfaced through snorkel to HDFC p
Develop BI report for FG run rate - both instrument and Reagent
RM MSL report for reagents and Instruments
Pls develop the itemwise consumption report in BI (This report is already developed in EBS in Name - Pre-
Develop Global Inventory report (detailed) in BI
Develop the report of Payment details in EBS and Qlik based on the reverse file received from HDFC- refer
"Notification for the invoices falling between " Automailer to be Split renamed to ""Cash flow requireme
Develop BPA, PO, receipt entry and MRN report for Service PO
MRP Name and MRP run date should be updated on MRN copy
Develop MRP wise PR, PO, MRN, AP invoice, Payment voucher Report
Linking of MRP, PR.,PO, BOE, AP invoice of Imported items to AP invoice of freight forwarder, CHA, Courie
Personalisation for all the R&D orgs - RNDR, RNDI,RRV,RIB for mandatory project code, while generating
Status Remark End Date
Not Started working. Report is already available in EBS.
Done Close SR.
Not Started working. Bajrang Ji SR.
Not Started working. Bajrang Ji SR.
WIP. 31-Mar-24
WIP. 7-Mar-24
Not Duable in Qlik
Not Started working.
Not Started working. 29-Feb-24
WIP. 20-Feb-24
Not Started working on it. Bajrang Ji SR.
Hold.
UAT.
Not Duable in Qlik Report is already available in EBS.
Not Duable in Qlik Report is already available in EBS.
Not Started working on it. Report is already available in EBS.
Not Started working on it. Report is already available in EBS.
WIP.
Not Started working on it. Bajrang Ji SR.
Not Started working on it. Bajrang Ji SR.
WIP.
Not Started working on it. Bajrang Ji SR.
WIP.
UAT. 29-Feb-24