Dear all,
Kindly find below project update for Asset Tracking Management (2D Barcode Solution ) as per Jan 22:
100% Business Requirement Gathering and Analysis Wk 4 Dec Wk 1 Jan Completed HW/DP
100% Business Process & System Design Approval Wk 1 Jan Wk 2 Jan Completed MU/DP Discussed with SK and received some inputs
95% Functional Design Specification Wk 3 Jan - In-Progress MU/DP Next step SSR submission
0% System Development & Testing Wk 2 Feb - Planned SB
0% Conduct In-Field Testing Wk 4 Feb - Planned RB/MU
0% Business Acceptance TBD - Planned RB/MU/DP
0% Go Live Preparation TBD - Planned RB/MU/DP
0% Go Live at Pilot Site TBD - Planned All
PIC:
SB = Stephan Bahana
AW = Ario Wibisono
DP = Donny Purwinto
RB = Rini Bagyo
MU = Masrizal Umar
SK = Suyono Kurniawan
Regards,
Donny Purwinto